### sec.8 Minimum submission period for draft EIS or draft IAR
The submission period set by the Coordinator-General for a draft EIS or draft IAR must be at least 28 days starting on the day after—
for a draft EIS—the day it is publicly notified under section 33 (1) of the Act ; or
for a draft IAR—the day it is publicly notified under section 33 (1) of the Act , as applied under section 34H (2) of the Act .
- (a) for a draft EIS—the day it is publicly notified under section 33 (1) of the Act ; or
- (b) for a draft IAR—the day it is publicly notified under section 33 (1) of the Act , as applied under section 34H (2) of the Act .