QLDIn ForceRegulation
State Development and Public Works Organisation Regulation 2020
sch.5-sec.5Fees if SDA applications involve more than 1 aspect of development
Start here
Get a plain-English read of sch.5-sec.5
Turn the raw legal text into a practical explanation grounded in State Development and Public Works Organisation Regulation 2020.
### sch.5-sec.5 Fees if SDA applications involve more than 1 aspect of development
Despite sections 3 and 4 , if an SDA application is for 2 or more aspects of development, the fee for the SDA application is each fee payable under sections 3 and 4 for each aspect of development.
An SDA application is for a material change of use and operational work. The required fee for the SDA application is the total of the amount payable under section 3 for an SDA application for operational work and the amount payable under section 4 for an SDA application for the material change of use.
An SDA application is for a material change of use for an extractive activity and a gas transportation infrastructure facility. The required fee for the SDA application is the total of the amount payable under section 4 for an SDA application for a material change of use for an extractive industry and the amount payable under that section for an SDA application for a material change of use for a gas transportation infrastructure facility.
- 1 An SDA application is for a material change of use and operational work. The required fee for the SDA application is the total of the amount payable under section 3 for an SDA application for operational work and the amount payable under section 4 for an SDA application for the material change of use.
- 2 An SDA application is for a material change of use for an extractive activity and a gas transportation infrastructure facility. The required fee for the SDA application is the total of the amount payable under section 4 for an SDA application for a material change of use for an extractive industry and the amount payable under that section for an SDA application for a material change of use for a gas transportation infrastructure facility.