### sec.76I Progression notice
The Coordinator-General may, by written notice (a progression notice ) given to the decision maker for a prescribed process, require the decision maker to undertake, within the period stated in the notice, administrative processes required to complete the process.
The progression notice must—
be accompanied by a copy of the declaration for the prescribed project to which the prescribed process relates; and
identify the process; and
state the decision maker must—
undertake the process within the stated period; and
inform the Coordinator-General of the completion of the process within 5 business days after it is completed.
On receiving the progression notice, the decision maker must—
subject to subsection (5) , undertake the prescribed process within the period stated in the notice for that purpose; and
inform the Coordinator-General of the completion of the process within 5 business days after it is completed.
The Coordinator-General may, by written notice given to the decision maker and without the decision maker’s agreement, extend the period for undertaking the prescribed process, having regard to the nature of the prescribed project to which the process relates.
If the Coordinator-General extends the period for undertaking the prescribed process under subsection (4) , the decision maker must undertake the process within the extended period.
Before giving a progression notice for a prescribed process the Coordinator-General must have regard to the requirements, if any, under the relevant law for the undertaking of the process.
Subject to this section, the relevant law for the prescribed process continues to apply to the undertaking of the process.
s 76I ins 2006 No. 54 s 7
amd 2016 No. 27 s 532
(sec.76I-ssec.1) The Coordinator-General may, by written notice (a progression notice ) given to the decision maker for a prescribed process, require the decision maker to undertake, within the period stated in the notice, administrative processes required to complete the process.
(sec.76I-ssec.2) The progression notice must— be accompanied by a copy of the declaration for the prescribed project to which the prescribed process relates; and identify the process; and state the decision maker must— undertake the process within the stated period; and inform the Coordinator-General of the completion of the process within 5 business days after it is completed.
(sec.76I-ssec.3) On receiving the progression notice, the decision maker must— subject to subsection (5) , undertake the prescribed process within the period stated in the notice for that purpose; and inform the Coordinator-General of the completion of the process within 5 business days after it is completed.
(sec.76I-ssec.4) The Coordinator-General may, by written notice given to the decision maker and without the decision maker’s agreement, extend the period for undertaking the prescribed process, having regard to the nature of the prescribed project to which the process relates.
(sec.76I-ssec.5) If the Coordinator-General extends the period for undertaking the prescribed process under subsection (4) , the decision maker must undertake the process within the extended period.
(sec.76I-ssec.6) Before giving a progression notice for a prescribed process the Coordinator-General must have regard to the requirements, if any, under the relevant law for the undertaking of the process.
(sec.76I-ssec.7) Subject to this section, the relevant law for the prescribed process continues to apply to the undertaking of the process.
- (a) be accompanied by a copy of the declaration for the prescribed project to which the prescribed process relates; and
- (b) identify the process; and
- (c) state the decision maker must— (i) undertake the process within the stated period; and (ii) inform the Coordinator-General of the completion of the process within 5 business days after it is completed.
- (i) undertake the process within the stated period; and
- (ii) inform the Coordinator-General of the completion of the process within 5 business days after it is completed.
- (i) undertake the process within the stated period; and
- (ii) inform the Coordinator-General of the completion of the process within 5 business days after it is completed.
- (a) subject to subsection (5) , undertake the prescribed process within the period stated in the notice for that purpose; and
- (b) inform the Coordinator-General of the completion of the process within 5 business days after it is completed.