### sec.54M Cancellation of declaration
The Coordinator-General may cancel a bilateral project declaration for a coordinated project before making a decision under section 54T if—
the proponent of the project makes a written request to the Coordinator-General to cancel the declaration; or
the coordinated project declaration for the project is cancelled under section 27AF ; or
the Coordinator-General is no longer satisfied about either or both of the matters mentioned in section 54J (2) ; or
the Coordinator-General considers the project is a project mentioned in section 54J (3) (a) to (c) .
If the Coordinator-General decides under subsection (1) (b) to (d) to cancel the declaration, the Coordinator-General must, within 14 days after the decision, give the proponent written notice of the decision and the reasons for it.
A decision to cancel the declaration takes effect on the later of—
the day the written notice is given to the proponent; or
the day of effect stated in the written notice.
s 54M ins 2014 No. 36 s 52
(sec.54M-ssec.1) The Coordinator-General may cancel a bilateral project declaration for a coordinated project before making a decision under section 54T if— the proponent of the project makes a written request to the Coordinator-General to cancel the declaration; or the coordinated project declaration for the project is cancelled under section 27AF ; or the Coordinator-General is no longer satisfied about either or both of the matters mentioned in section 54J (2) ; or the Coordinator-General considers the project is a project mentioned in section 54J (3) (a) to (c) .
(sec.54M-ssec.2) If the Coordinator-General decides under subsection (1) (b) to (d) to cancel the declaration, the Coordinator-General must, within 14 days after the decision, give the proponent written notice of the decision and the reasons for it.
(sec.54M-ssec.3) A decision to cancel the declaration takes effect on the later of— the day the written notice is given to the proponent; or the day of effect stated in the written notice.
- (a) the proponent of the project makes a written request to the Coordinator-General to cancel the declaration; or
- (b) the coordinated project declaration for the project is cancelled under section 27AF ; or
- (c) the Coordinator-General is no longer satisfied about either or both of the matters mentioned in section 54J (2) ; or
- (d) the Coordinator-General considers the project is a project mentioned in section 54J (3) (a) to (c) .
- (a) the day the written notice is given to the proponent; or
- (b) the day of effect stated in the written notice.