### sec.99BRDH Effect of and action after conversion
This section applies if the decision on a conversion application is to convert the non-trunk infrastructure to trunk infrastructure.
See schedule, definition trunk infrastructure .
The relevant water approval condition requiring the non-trunk infrastructure to be provided no longer has effect.
Within 20 business days after making the decision, the distributor-retailer may amend the water approval by imposing a necessary infrastructure condition for the trunk infrastructure.
If a necessary infrastructure condition is imposed, the distributor-retailer must also do either of the following within 10 business days after the imposition for the purposes of section 99BRCT (2) or (3) (b) —
give an infrastructure charges notice;
amend, by notice to the applicant, any existing infrastructure charges notice for the water approval.
For taking action under subsections (3) and (4) , divisions 3 and 4 and part 4 apply as if—
a water approval were a reference to the conversion; and
a levied charge were a reference to the amendment of the levied charge.
s 99BRDH ins 2014 No. 36 s 45
(sec.99BRDH-ssec.1) This section applies if the decision on a conversion application is to convert the non-trunk infrastructure to trunk infrastructure. See schedule, definition trunk infrastructure .
(sec.99BRDH-ssec.2) The relevant water approval condition requiring the non-trunk infrastructure to be provided no longer has effect.
(sec.99BRDH-ssec.3) Within 20 business days after making the decision, the distributor-retailer may amend the water approval by imposing a necessary infrastructure condition for the trunk infrastructure.
(sec.99BRDH-ssec.4) If a necessary infrastructure condition is imposed, the distributor-retailer must also do either of the following within 10 business days after the imposition for the purposes of section 99BRCT (2) or (3) (b) — give an infrastructure charges notice; amend, by notice to the applicant, any existing infrastructure charges notice for the water approval.
(sec.99BRDH-ssec.5) For taking action under subsections (3) and (4) , divisions 3 and 4 and part 4 apply as if— a water approval were a reference to the conversion; and a levied charge were a reference to the amendment of the levied charge.
- (a) give an infrastructure charges notice;
- (b) amend, by notice to the applicant, any existing infrastructure charges notice for the water approval.
- (a) a water approval were a reference to the conversion; and