### sec.99BRDC Working out cost for required offset or refund
This section applies if—
a distributor-retailer has given an applicant for a water approval—
a water approval under which the applicant is required to provide trunk infrastructure; and
an infrastructure charges notice that includes details of an offset or refund under this part relating to the establishment cost of the trunk infrastructure; and
the applicant does not agree with the value of the establishment cost.
The applicant may, by notice to the distributor-retailer, require it to use the method under the relevant infrastructure charges schedule to recalculate the establishment cost.
A notice under subsection (2) must be given to the distributor-retailer before the levied charge under the infrastructure charges notice becomes payable under section 99BRCL .
By notice to the applicant, the distributor-retailer must amend the existing infrastructure charges notice.
The amended infrastructure charges notice must adopt the method to work out the establishment cost.
s 99BRDC ins 2014 No. 36 s 45
(sec.99BRDC-ssec.1) This section applies if— a distributor-retailer has given an applicant for a water approval— a water approval under which the applicant is required to provide trunk infrastructure; and an infrastructure charges notice that includes details of an offset or refund under this part relating to the establishment cost of the trunk infrastructure; and the applicant does not agree with the value of the establishment cost.
(sec.99BRDC-ssec.2) The applicant may, by notice to the distributor-retailer, require it to use the method under the relevant infrastructure charges schedule to recalculate the establishment cost.
(sec.99BRDC-ssec.2A) A notice under subsection (2) must be given to the distributor-retailer before the levied charge under the infrastructure charges notice becomes payable under section 99BRCL .
(sec.99BRDC-ssec.3) By notice to the applicant, the distributor-retailer must amend the existing infrastructure charges notice.
(sec.99BRDC-ssec.4) The amended infrastructure charges notice must adopt the method to work out the establishment cost.
- (a) a distributor-retailer has given an applicant for a water approval— (i) a water approval under which the applicant is required to provide trunk infrastructure; and (ii) an infrastructure charges notice that includes details of an offset or refund under this part relating to the establishment cost of the trunk infrastructure; and
- (i) a water approval under which the applicant is required to provide trunk infrastructure; and
- (ii) an infrastructure charges notice that includes details of an offset or refund under this part relating to the establishment cost of the trunk infrastructure; and
- (b) the applicant does not agree with the value of the establishment cost.
- (i) a water approval under which the applicant is required to provide trunk infrastructure; and
- (ii) an infrastructure charges notice that includes details of an offset or refund under this part relating to the establishment cost of the trunk infrastructure; and