Turn the raw legal text into a practical explanation grounded in South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.
### sec.99BRBV Work under water approval not to start if appeal is started and not decided or withdrawn
If an appeal, other than an appeal under section 99BRBP , is started under this division, any work under a water approval must not be started until the appeal is decided or withdrawn.
However, if the Planning and Environment Court is satisfied the outcome of the appeal would not be affected if all or part of the work were to start before the appeal is decided, the court may allow all or that part of the work to start before the appeal is decided.
s 99BRBV ins 2014 No. 16 s 21
amd 2014 No. 36 s 43 ; 2016 No. 27 s 477
(sec.99BRBV-ssec.1) If an appeal, other than an appeal under section 99BRBP , is started under this division, any work under a water approval must not be started until the appeal is decided or withdrawn.
(sec.99BRBV-ssec.2) However, if the Planning and Environment Court is satisfied the outcome of the appeal would not be affected if all or part of the work were to start before the appeal is decided, the court may allow all or that part of the work to start before the appeal is decided.