QLDIn ForceAct
South-East Queensland Water (Distribution and Retail Restructuring) Act 2009
sec.150Infrastructure charges notice for particular other development approval
Start here
Get a plain-English read of sec.150
Turn the raw legal text into a practical explanation grounded in South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.
### sec.150 Infrastructure charges notice for particular other development approval
This section applies if—
notice (the original notice ) levying a charge is given under the Planning Act, or was given under the repealed SPA , for a development approval—
that was given before 1 July 2014; and
the water connection aspect of which did not become a water approval for a staged water connection under section 135(2); and
a following application is approved under the Planning Act—
a change application under that Act to change the development approval;
an extension application under that Act for any part of the development approval.
The distributor-retailer for the water infrastructure to which the development approval relates may give the holder of the approval an infrastructure charges notice under chapter 4C, part 7, division 3, subdivision 3 to replace the original notice.
Chapter 4C, part 7, division 3, subdivision 3 applies to the giving of the infrastructure charges notice, as if—
the original notice were an infrastructure charges notice; and
a reference in chapter 4C, part 7, division 3, subdivision 3 to a water approval were a reference to a development approval.
However, section 99BRDC does not apply to an infrastructure charges notice given under subsection (2).
s 150 ins 2016 No. 27 s 499
(sec.150-ssec.1) This section applies if— notice (the original notice ) levying a charge is given under the Planning Act, or was given under the repealed SPA , for a development approval— that was given before 1 July 2014; and the water connection aspect of which did not become a water approval for a staged water connection under section 135(2); and a following application is approved under the Planning Act— a change application under that Act to change the development approval; an extension application under that Act for any part of the development approval.
(sec.150-ssec.2) The distributor-retailer for the water infrastructure to which the development approval relates may give the holder of the approval an infrastructure charges notice under chapter 4C, part 7, division 3, subdivision 3 to replace the original notice.
(sec.150-ssec.3) Chapter 4C, part 7, division 3, subdivision 3 applies to the giving of the infrastructure charges notice, as if— the original notice were an infrastructure charges notice; and a reference in chapter 4C, part 7, division 3, subdivision 3 to a water approval were a reference to a development approval.
(sec.150-ssec.4) However, section 99BRDC does not apply to an infrastructure charges notice given under subsection (2).
- (a) notice (the original notice ) levying a charge is given under the Planning Act, or was given under the repealed SPA , for a development approval— (i) that was given before 1 July 2014; and (ii) the water connection aspect of which did not become a water approval for a staged water connection under section 135(2); and
- (i) that was given before 1 July 2014; and
- (ii) the water connection aspect of which did not become a water approval for a staged water connection under section 135(2); and
- (b) a following application is approved under the Planning Act— (i) a change application under that Act to change the development approval; (ii) an extension application under that Act for any part of the development approval.
- (i) a change application under that Act to change the development approval;
- (ii) an extension application under that Act for any part of the development approval.
- (i) that was given before 1 July 2014; and
- (ii) the water connection aspect of which did not become a water approval for a staged water connection under section 135(2); and
- (i) a change application under that Act to change the development approval;
- (ii) an extension application under that Act for any part of the development approval.
- (a) the original notice were an infrastructure charges notice; and
- (b) a reference in chapter 4C, part 7, division 3, subdivision 3 to a water approval were a reference to a development approval.