QLDIn ForceAct
South Bank Corporation Act 1989
sec.137Application of unamended Act to development approvals for sites 9A and 9B
Start here
Get a plain-English read of sec.137
Turn the raw legal text into a practical explanation grounded in South Bank Corporation Act 1989.
### sec.137 Application of unamended Act to development approvals for sites 9A and 9B
This section applies in relation to land in sites 9A and 9B.
Without limiting section 133, the unamended Act, part 6 and part 7, division 3 continue to apply in relation to the following as if the part and the division had not been amended by the amending Act—
a development approval for sites 9A and 9B, or any part of sites 9A and 9B, that is in effect immediately before the commencement;
an application made by a relevant applicant after the commencement—
for another development approval for sites 9A and 9B; and
to change a development approval mentioned in paragraph (a); and
to cancel a development approval mentioned in paragraph (a);
a development approval for an application mentioned in paragraph (b)(i) or (ii).
In this section—
relevant applicant means a person who before the commencement was the applicant for a development approval mentioned in subsection (2)(a).
sites 9A and 9B means all of the following land—
the part of lot 812 on SP 205159 as shown in the approved development plan;
lot 100 on SP 116313;
lot 900 on SP 204999;
lot 3 on SP 121757;
lot 1 on CP M332199;
lot 5 on SP 205135.
s 137 ins 2012 No. 43 s 281
(sec.137-ssec.1) This section applies in relation to land in sites 9A and 9B.
(sec.137-ssec.2) Without limiting section 133, the unamended Act, part 6 and part 7, division 3 continue to apply in relation to the following as if the part and the division had not been amended by the amending Act— a development approval for sites 9A and 9B, or any part of sites 9A and 9B, that is in effect immediately before the commencement; an application made by a relevant applicant after the commencement— for another development approval for sites 9A and 9B; and to change a development approval mentioned in paragraph (a); and to cancel a development approval mentioned in paragraph (a); a development approval for an application mentioned in paragraph (b)(i) or (ii).
(sec.137-ssec.3) In this section— relevant applicant means a person who before the commencement was the applicant for a development approval mentioned in subsection (2)(a). sites 9A and 9B means all of the following land— the part of lot 812 on SP 205159 as shown in the approved development plan; lot 100 on SP 116313; lot 900 on SP 204999; lot 3 on SP 121757; lot 1 on CP M332199; lot 5 on SP 205135.
- (a) a development approval for sites 9A and 9B, or any part of sites 9A and 9B, that is in effect immediately before the commencement;
- (b) an application made by a relevant applicant after the commencement— (i) for another development approval for sites 9A and 9B; and (ii) to change a development approval mentioned in paragraph (a); and (iii) to cancel a development approval mentioned in paragraph (a);
- (i) for another development approval for sites 9A and 9B; and
- (ii) to change a development approval mentioned in paragraph (a); and
- (iii) to cancel a development approval mentioned in paragraph (a);
- (c) a development approval for an application mentioned in paragraph (b)(i) or (ii).
- (i) for another development approval for sites 9A and 9B; and
- (ii) to change a development approval mentioned in paragraph (a); and
- (iii) to cancel a development approval mentioned in paragraph (a);
- (a) the part of lot 812 on SP 205159 as shown in the approved development plan;
- (b) lot 100 on SP 116313;
- (c) lot 900 on SP 204999;
- (d) lot 3 on SP 121757;
- (e) lot 1 on CP M332199;
- (f) lot 5 on SP 205135.