QLDIn ForceRegulation
Rural and Regional Adjustment Regulation 2011
sch.45-sec.6Meaning of eligible infrastructure expense
Start here
Get a plain-English read of sch.45-sec.6
Turn the raw legal text into a practical explanation grounded in Rural and Regional Adjustment Regulation 2011.
### sch.45-sec.6 Meaning of eligible infrastructure expense
An eligible infrastructure expense is a cost incurred, or to be incurred, during the relevant period in relation to carrying out work for an eligible project, including, for example, the cost of—
obtaining a permit or other approval (however described) required for carrying out the work; and
purchasing infrastructure; and
repairing, improving or replacing existing infrastructure; and
installing and commissioning infrastructure.
costs incurred in expanding an existing jetty or pontoon
costs incurred in installing infrastructure for utilities, including electricity and water, to support the use of a berth
However, an eligible infrastructure expense does not include—
a cost paid before 1 July 2022; or
a cost incurred after the infrastructure is installed and ready for use, including, for example, any cost for ongoing maintenance, administration, operation or subsequent improvement of the infrastructure.
sch 45 s 6 ins 2022 SL No. 137 s 6
(sch.45-sec.6-ssec.1) An eligible infrastructure expense is a cost incurred, or to be incurred, during the relevant period in relation to carrying out work for an eligible project, including, for example, the cost of— obtaining a permit or other approval (however described) required for carrying out the work; and purchasing infrastructure; and repairing, improving or replacing existing infrastructure; and installing and commissioning infrastructure. costs incurred in expanding an existing jetty or pontoon costs incurred in installing infrastructure for utilities, including electricity and water, to support the use of a berth
(sch.45-sec.6-ssec.2) However, an eligible infrastructure expense does not include— a cost paid before 1 July 2022; or a cost incurred after the infrastructure is installed and ready for use, including, for example, any cost for ongoing maintenance, administration, operation or subsequent improvement of the infrastructure.
- (a) obtaining a permit or other approval (however described) required for carrying out the work; and
- (b) purchasing infrastructure; and
- (c) repairing, improving or replacing existing infrastructure; and
- (d) installing and commissioning infrastructure.
- • costs incurred in expanding an existing jetty or pontoon
- • costs incurred in installing infrastructure for utilities, including electricity and water, to support the use of a berth
- (a) a cost paid before 1 July 2022; or
- (b) a cost incurred after the infrastructure is installed and ready for use, including, for example, any cost for ongoing maintenance, administration, operation or subsequent improvement of the infrastructure.