### sch.45-sec.12 Eligibility criteria—minor infrastructure grant
An applicant for a minor infrastructure grant is eligible to receive financial assistance under the scheme if—
the applicant is the owner of an eligible business; and
the applicant is applying for financial assistance for an eligible project to provide a berth for use by an eligible vessel; and
the applicant demonstrates to the satisfaction of the authority that—
the matters mentioned in section 11 (2) (a) and (b) apply in relation to the eligible vessel; and
the applicant has the ability to pay the remaining cost of the eligible project; and
if the total cost of the eligible infrastructure expenses for the eligible project is more than $10,000 (excluding GST)—
the applicant has obtained at least 2 quotes for the eligible project; or
despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
In this section—
remaining cost , of an eligible project, means the difference between—
the total amount of the eligible infrastructure expenses (including GST) for the eligible project; and
the maximum amount of assistance under section 10 (3) for a minor infrastructure grant for the eligible project.
sch 45 s 12 ins 2022 SL No. 137 s 6
(sch.45-sec.12-ssec.1) An applicant for a minor infrastructure grant is eligible to receive financial assistance under the scheme if— the applicant is the owner of an eligible business; and the applicant is applying for financial assistance for an eligible project to provide a berth for use by an eligible vessel; and the applicant demonstrates to the satisfaction of the authority that— the matters mentioned in section 11 (2) (a) and (b) apply in relation to the eligible vessel; and the applicant has the ability to pay the remaining cost of the eligible project; and if the total cost of the eligible infrastructure expenses for the eligible project is more than $10,000 (excluding GST)— the applicant has obtained at least 2 quotes for the eligible project; or despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
(sch.45-sec.12-ssec.2) In this section— remaining cost , of an eligible project, means the difference between— the total amount of the eligible infrastructure expenses (including GST) for the eligible project; and the maximum amount of assistance under section 10 (3) for a minor infrastructure grant for the eligible project.
- (a) the applicant is the owner of an eligible business; and
- (b) the applicant is applying for financial assistance for an eligible project to provide a berth for use by an eligible vessel; and
- (c) the applicant demonstrates to the satisfaction of the authority that— (i) the matters mentioned in section 11 (2) (a) and (b) apply in relation to the eligible vessel; and (ii) the applicant has the ability to pay the remaining cost of the eligible project; and (iii) if the total cost of the eligible infrastructure expenses for the eligible project is more than $10,000 (excluding GST)— (A) the applicant has obtained at least 2 quotes for the eligible project; or (B) despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
- (i) the matters mentioned in section 11 (2) (a) and (b) apply in relation to the eligible vessel; and
- (ii) the applicant has the ability to pay the remaining cost of the eligible project; and
- (iii) if the total cost of the eligible infrastructure expenses for the eligible project is more than $10,000 (excluding GST)— (A) the applicant has obtained at least 2 quotes for the eligible project; or (B) despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
- (A) the applicant has obtained at least 2 quotes for the eligible project; or
- (B) despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
- (i) the matters mentioned in section 11 (2) (a) and (b) apply in relation to the eligible vessel; and
- (ii) the applicant has the ability to pay the remaining cost of the eligible project; and
- (iii) if the total cost of the eligible infrastructure expenses for the eligible project is more than $10,000 (excluding GST)— (A) the applicant has obtained at least 2 quotes for the eligible project; or (B) despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
- (A) the applicant has obtained at least 2 quotes for the eligible project; or
- (B) despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
- (A) the applicant has obtained at least 2 quotes for the eligible project; or
- (B) despite making reasonable attempts, the applicant has not been able to obtain at least 2 quotes for the eligible project, but the project represents value for money.
- (a) the total amount of the eligible infrastructure expenses (including GST) for the eligible project; and
- (b) the maximum amount of assistance under section 10 (3) for a minor infrastructure grant for the eligible project.