QLDIn ForceAct
Regional Planning Interests Act 2014
sec.101Application for SCL protection decision
Start here
Get a plain-English read of sec.101
Turn the raw legal text into a practical explanation grounded in Regional Planning Interests Act 2014.
### sec.101 Application for SCL protection decision
This section applies to an application for an SCL protection decision for a resource activity made under the repealed Act, section 95 if—
at the commencement, the application had not been decided or withdrawn; and
the application is for a resource activity in an area that is in the strategic cropping area under this Act.
The chief executive (natural resources) must deal with and decide, or continue to deal with and decide, the application under the repealed Act as if this Act has not been enacted.
(sec.101-ssec.1) This section applies to an application for an SCL protection decision for a resource activity made under the repealed Act, section 95 if— at the commencement, the application had not been decided or withdrawn; and the application is for a resource activity in an area that is in the strategic cropping area under this Act.
(sec.101-ssec.2) The chief executive (natural resources) must deal with and decide, or continue to deal with and decide, the application under the repealed Act as if this Act has not been enacted.
- (a) at the commencement, the application had not been decided or withdrawn; and
- (b) the application is for a resource activity in an area that is in the strategic cropping area under this Act.