### sec.71 Notice of submitted scheme
The authority must, as soon as practicable after giving the Minister the submitted scheme, give each person (a submitter ) who made a submission received within the submission period about the scheme a notice stating that—
the scheme has been made and submitted to the Minister; and
the authority’s report about the submitted scheme can be inspected on its website; and
if the submitter is an affected owner for the relevant declared project or reconstruction area—the submitter may, within 20 business days after receiving the notice, ask the Minister to amend the submitted scheme to protect the owner’s interests.
- (a) the scheme has been made and submitted to the Minister; and
- (b) the authority’s report about the submitted scheme can be inspected on its website; and
- (c) if the submitter is an affected owner for the relevant declared project or reconstruction area—the submitter may, within 20 business days after receiving the notice, ask the Minister to amend the submitted scheme to protect the owner’s interests.