### sch.6-sec.41 Claims relating to defective work—work substantially complete
This section applies to the residential construction work if the work is substantially complete.
The maximum amount the commission may pay for all claims mentioned in sections 15 and 20 in relation to the residential construction work is—
if optional additional cover is in force for the work—$300,000; or
if paragraph (a) does not apply—$200,000.
However, for all claims mentioned in section 20 in relation to the residential construction work, the commission must not pay more than—
if optional additional cover is in force for the work—$10,000; or
if paragraph (a) does not apply—$5,000.
(sch.6-sec.41-ssec.1) This section applies to the residential construction work if the work is substantially complete.
(sch.6-sec.41-ssec.2) The maximum amount the commission may pay for all claims mentioned in sections 15 and 20 in relation to the residential construction work is— if optional additional cover is in force for the work—$300,000; or if paragraph (a) does not apply—$200,000.
(sch.6-sec.41-ssec.3) However, for all claims mentioned in section 20 in relation to the residential construction work, the commission must not pay more than— if optional additional cover is in force for the work—$10,000; or if paragraph (a) does not apply—$5,000.
- (a) if optional additional cover is in force for the work—$300,000; or
- (b) if paragraph (a) does not apply—$200,000.
- (a) if optional additional cover is in force for the work—$10,000; or
- (b) if paragraph (a) does not apply—$5,000.