QLDIn ForceAct
Queensland Building and Construction Commission Act 1991
sec.67UVoid payment provision in construction management trade contract or subcontract
Start here
Get a plain-English read of sec.67U
Turn the raw legal text into a practical explanation grounded in Queensland Building and Construction Commission Act 1991.
### sec.67U Void payment provision in construction management trade contract or subcontract
A provision in a construction management trade contract or subcontract is void to the extent it provides for payment of a progress payment by a contracting party to a contracted party later than 25 business days after submission of a payment claim.
In this section—
business day means a day that is not—
a Saturday or Sunday; or
a public holiday, special holiday or bank holiday in the place in which any relevant act is to be or may be done; or
a day in the period from 22 December in a particular year to 10 January in the following year, both days inclusive.
s 67U ins 1999 No. 43 s 29
sub 2004 No. 6 s 113 sch 1
amd 2020 No. 24 s 131
(sec.67U-ssec.1) A provision in a construction management trade contract or subcontract is void to the extent it provides for payment of a progress payment by a contracting party to a contracted party later than 25 business days after submission of a payment claim.
(sec.67U-ssec.2) In this section— business day means a day that is not— a Saturday or Sunday; or a public holiday, special holiday or bank holiday in the place in which any relevant act is to be or may be done; or a day in the period from 22 December in a particular year to 10 January in the following year, both days inclusive.
- (a) a Saturday or Sunday; or
- (b) a public holiday, special holiday or bank holiday in the place in which any relevant act is to be or may be done; or
- (c) a day in the period from 22 December in a particular year to 10 January in the following year, both days inclusive.