### sch.1B-sec.37 Withdrawal procedure
To withdraw from a regulated contract under schedule section 35 , the building owner must, within the time allowed under the section for the withdrawal—
give a withdrawal notice to the building contractor; or
leave a withdrawal notice at the address shown as the building contractor’s address in the contract; or
serve a withdrawal notice on the building contractor in accordance with any provision in the contract providing for service of notices on the building contractor by the building owner.
In this section—
withdrawal notice means a written notice signed by the building owner under a regulated contract stating—
that the building owner withdraws from the contract; and
the section of this schedule under which the withdrawal is made.
sch 1B s 37 ins 2014 No. 57 s 60
(sch.1B-sec.37-ssec.1) To withdraw from a regulated contract under schedule section 35 , the building owner must, within the time allowed under the section for the withdrawal— give a withdrawal notice to the building contractor; or leave a withdrawal notice at the address shown as the building contractor’s address in the contract; or serve a withdrawal notice on the building contractor in accordance with any provision in the contract providing for service of notices on the building contractor by the building owner.
(sch.1B-sec.37-ssec.2) In this section— withdrawal notice means a written notice signed by the building owner under a regulated contract stating— that the building owner withdraws from the contract; and the section of this schedule under which the withdrawal is made.
- (a) give a withdrawal notice to the building contractor; or
- (b) leave a withdrawal notice at the address shown as the building contractor’s address in the contract; or
- (c) serve a withdrawal notice on the building contractor in accordance with any provision in the contract providing for service of notices on the building contractor by the building owner.
- (a) that the building owner withdraws from the contract; and
- (b) the section of this schedule under which the withdrawal is made.