### sch.1B-sec.16 Copy of commencement notice
This section applies to a level 2 regulated contract.
Within 10 business days of starting the subject work at the building site, the building contractor must give the building owner a commencement notice signed by the contractor and stating—
the date the subject work started at the building site; and
the date for practical completion.
Maximum penalty—40 penalty units.
sch 1B s 16 ins 2014 No. 57 s 60
(sch.1B-sec.16-ssec.1) This section applies to a level 2 regulated contract.
(sch.1B-sec.16-ssec.2) Within 10 business days of starting the subject work at the building site, the building contractor must give the building owner a commencement notice signed by the contractor and stating— the date the subject work started at the building site; and the date for practical completion. Maximum penalty—40 penalty units.
- (a) the date the subject work started at the building site; and
- (b) the date for practical completion.