This section applies if, before the commencement—
the commission directed a person to rectify building work that was defective or incomplete under former section 72; and
the direction had not been complied with in full.
The direction continues to apply to the person, and former section 72 continues to apply for that purpose, as if the section had not been replaced by the Amendment Act.
The direction is taken, for section 73, to be a direction of the commission to rectify building work that is defective or incomplete, or to remedy consequential damage.
sch 1 s 61 ins 2014 No. 57 s 59
(sch.1-sec.61-ssec.1) This section applies if, before the commencement— the commission directed a person to rectify building work that was defective or incomplete under former section 72; and the direction had not been complied with in full.
(sch.1-sec.61-ssec.2) The direction continues to apply to the person, and former section 72 continues to apply for that purpose, as if the section had not been replaced by the Amendment Act.
(sch.1-sec.61-ssec.3) The direction is taken, for section 73, to be a direction of the commission to rectify building work that is defective or incomplete, or to remedy consequential damage.
- (a) the commission directed a person to rectify building work that was defective or incomplete under former section 72; and
- (b) the direction had not been complied with in full.