### sec.73A Development permits for building work given by private certifiers
This section applies to a development application for a development permit that—
is for building work; and
is made to a private certifier as assessment manager.
Subsection (3) applies to the development application if any part of the building work requires impact assessment.
A development permit given by the private certifier for the building work does not authorise the carrying out of the part requiring impact assessment, unless a relevant preliminary approval is in effect for the part.
Subsection (5) applies to the development application if—
any part of the building work must be assessed against, or having regard to, a matter that is not a building assessment provision; and
none of the referral agencies are required to assess the application against, or having regard to, the matter.
A development permit given by the private certifier for the building work does not authorise the carrying out of the part requiring assessment against, or having regard to, the matter, unless a relevant preliminary approval is in effect for the part.
In this section—
relevant preliminary approval means a preliminary approval given under the old Act by an entity other than a private certifier.
s 73A ins 2017 No. 12 s 37
(sec.73A-ssec.1) This section applies to a development application for a development permit that— is for building work; and is made to a private certifier as assessment manager.
(sec.73A-ssec.2) Subsection (3) applies to the development application if any part of the building work requires impact assessment.
(sec.73A-ssec.3) A development permit given by the private certifier for the building work does not authorise the carrying out of the part requiring impact assessment, unless a relevant preliminary approval is in effect for the part.
(sec.73A-ssec.4) Subsection (5) applies to the development application if— any part of the building work must be assessed against, or having regard to, a matter that is not a building assessment provision; and none of the referral agencies are required to assess the application against, or having regard to, the matter.
(sec.73A-ssec.5) A development permit given by the private certifier for the building work does not authorise the carrying out of the part requiring assessment against, or having regard to, the matter, unless a relevant preliminary approval is in effect for the part.
(sec.73A-ssec.6) In this section— relevant preliminary approval means a preliminary approval given under the old Act by an entity other than a private certifier.
- (a) is for building work; and
- (b) is made to a private certifier as assessment manager.
- (a) any part of the building work must be assessed against, or having regard to, a matter that is not a building assessment provision; and
- (b) none of the referral agencies are required to assess the application against, or having regard to, the matter.