### sec.966 Particular requirements for infrastructure reports under s 552A for existing petroleum leases
This section applies to the holder of an existing petroleum lease.
The first infrastructure report lodged after the commencement by the holder under section 552A for an existing petroleum lease must, in addition to the requirements mentioned in section 552B, also state—
details of the authorised activities for the lease carried out since the lease was granted; and
details of infrastructure and works constructed in the area of the lease since the lease was granted, including the location of the infrastructure and works.
s 966 ins 2012 No. 20 s 278
(sec.966-ssec.1) This section applies to the holder of an existing petroleum lease.
(sec.966-ssec.2) The first infrastructure report lodged after the commencement by the holder under section 552A for an existing petroleum lease must, in addition to the requirements mentioned in section 552B, also state— details of the authorised activities for the lease carried out since the lease was granted; and details of infrastructure and works constructed in the area of the lease since the lease was granted, including the location of the infrastructure and works.
- (a) details of the authorised activities for the lease carried out since the lease was granted; and
- (b) details of infrastructure and works constructed in the area of the lease since the lease was granted, including the location of the infrastructure and works.