QLDIn ForceAct
Petroleum and Gas (Production and Safety) Act 2004
sec.851ABPeriod of effect of particular later work programs
Start here
Get a plain-English read of sec.851AB
Turn the raw legal text into a practical explanation grounded in Petroleum and Gas (Production and Safety) Act 2004.
### sec.851AB Period of effect of particular later work programs
This section applies if—
before the commencement of this section, the holder of an authority to prospect was given, under section 58 , a notice (the notice ) of the approval of a proposed later work program for the authority; and
the notice was given to the holder of the authority after the start of the period of the proposed program as stated in the proposed program.
For an Act, the approval has effect, and is taken to have had effect, from—
the start of the period; or
if the notice stated a later day of effect—the later day.
The notice is, and is taken always to have been, valid and effective—
even though the notice was given after the commencement of the period stated for the proposed program; and
whether or not the notice purported, expressly or impliedly, to approve the carrying out of work under the program before the approval was given; and
regardless of the extent to which section 57 (2) (b) and (c) was complied with.
It does not matter if a work program was considered under section 57 (2) (b) but was not current at the time of its consideration.
This section applies despite chapter 2 , part 1 , division 3 .
s 851AB ins 2014 No. 29 s 128
(sec.851AB-ssec.1) This section applies if— before the commencement of this section, the holder of an authority to prospect was given, under section 58 , a notice (the notice ) of the approval of a proposed later work program for the authority; and the notice was given to the holder of the authority after the start of the period of the proposed program as stated in the proposed program.
(sec.851AB-ssec.2) For an Act, the approval has effect, and is taken to have had effect, from— the start of the period; or if the notice stated a later day of effect—the later day.
(sec.851AB-ssec.3) The notice is, and is taken always to have been, valid and effective— even though the notice was given after the commencement of the period stated for the proposed program; and whether or not the notice purported, expressly or impliedly, to approve the carrying out of work under the program before the approval was given; and regardless of the extent to which section 57 (2) (b) and (c) was complied with. It does not matter if a work program was considered under section 57 (2) (b) but was not current at the time of its consideration.
(sec.851AB-ssec.4) This section applies despite chapter 2 , part 1 , division 3 .
- (a) before the commencement of this section, the holder of an authority to prospect was given, under section 58 , a notice (the notice ) of the approval of a proposed later work program for the authority; and
- (b) the notice was given to the holder of the authority after the start of the period of the proposed program as stated in the proposed program.
- (a) the start of the period; or
- (b) if the notice stated a later day of effect—the later day.
- (a) even though the notice was given after the commencement of the period stated for the proposed program; and
- (b) whether or not the notice purported, expressly or impliedly, to approve the carrying out of work under the program before the approval was given; and
- (c) regardless of the extent to which section 57 (2) (b) and (c) was complied with. Example for paragraph (c) — It does not matter if a work program was considered under section 57 (2) (b) but was not current at the time of its consideration.