QLDIn ForceAct
Petroleum and Gas (Production and Safety) Act 2004
sec.412AProvisions about grant and conditions of licence for coordinated project
Start here
Get a plain-English read of sec.412A
Turn the raw legal text into a practical explanation grounded in Petroleum and Gas (Production and Safety) Act 2004.
### sec.412A Provisions about grant and conditions of licence for coordinated project
This section applies if a pipeline licence or proposed pipeline licence is for a coordinated project.
The Minister must not grant the licence until the Minister has been given the Coordinator-General’s report for the project.
Any Coordinator-General’s conditions for the licence must be stated in the licence.
Any other condition of the licence stated under section 412 must not be inconsistent with the Coordinator-General’s conditions.
If a mandatory condition for pipeline licences conflicts with any of the Coordinator-General’s conditions, the Coordinator-General’s condition prevails to the extent of the inconsistency.
s 412A ins 2005 No. 57 s 12
amd 2012 No. 43 s 325 sch 2
(sec.412A-ssec.1) This section applies if a pipeline licence or proposed pipeline licence is for a coordinated project.
(sec.412A-ssec.2) The Minister must not grant the licence until the Minister has been given the Coordinator-General’s report for the project.
(sec.412A-ssec.3) Any Coordinator-General’s conditions for the licence must be stated in the licence.
(sec.412A-ssec.4) Any other condition of the licence stated under section 412 must not be inconsistent with the Coordinator-General’s conditions.
(sec.412A-ssec.5) If a mandatory condition for pipeline licences conflicts with any of the Coordinator-General’s conditions, the Coordinator-General’s condition prevails to the extent of the inconsistency.