### sec.865 Declaration about Mineral Resources Regulation 2003
The repealed Mineral Resources Regulation 2003 , as in force from time to time before its repeal, is taken to have had effect for the declaration period as if it were amended as provided in this section.
Schedule 4, part 2, section 2, after ‘royalty rate for bauxite’—
insert—
sold, disposed of or used in a return period by the holder of the mining lease for the bauxite
Schedule 4, part 2, section 2(a), from ‘if it is sold’ to ‘for the bauxite’—
omit, insert—
if the bauxite is mined for consumption outside the State
Schedule 4, part 2, section 2(b), from ‘if it is sold’ to ‘for the bauxite’—
omit, insert—
if the bauxite is mined for consumption within the State
Schedule 4, part 2, section 2(b)(i), from ‘for a holder’ to ‘outside the State’—
omit, insert—
for a holder who has also sold, disposed of or used bauxite in the return period that is mined for consumption outside the State
In this section—
declaration period means the period from the commencement of the Mines and Energy Legislation Amendment Regulation (No. 2) 2008 until the commencement of the Mineral Resources Regulation 2003 .
s 865 ins 2019 No. 8 s 60B
(sec.865-ssec.1) The repealed Mineral Resources Regulation 2003 , as in force from time to time before its repeal, is taken to have had effect for the declaration period as if it were amended as provided in this section.
(sec.865-ssec.2) Schedule 4, part 2, section 2, after ‘royalty rate for bauxite’— insert— sold, disposed of or used in a return period by the holder of the mining lease for the bauxite
(sec.865-ssec.3) Schedule 4, part 2, section 2(a), from ‘if it is sold’ to ‘for the bauxite’— omit, insert— if the bauxite is mined for consumption outside the State
(sec.865-ssec.4) Schedule 4, part 2, section 2(b), from ‘if it is sold’ to ‘for the bauxite’— omit, insert— if the bauxite is mined for consumption within the State
(sec.865-ssec.5) Schedule 4, part 2, section 2(b)(i), from ‘for a holder’ to ‘outside the State’— omit, insert— for a holder who has also sold, disposed of or used bauxite in the return period that is mined for consumption outside the State
(sec.865-ssec.6) In this section— declaration period means the period from the commencement of the Mines and Energy Legislation Amendment Regulation (No. 2) 2008 until the commencement of the Mineral Resources Regulation 2003 .