### sec.40B Extension of period for complying with termination order
This section applies if the tribunal has made a termination order in relation to a site agreement.
The home owner may apply to the tribunal, before the termination day, for an order extending—
the period for complying with an order made under section 39B (1) (a) or (b) ; or
the period for complying with another order made by the tribunal in the termination order.
On the making of an application under subsection (2) , the termination order is suspended until the application is decided.
The tribunal may—
extend the period mentioned in subsection (2) (a) or (b) by the period (the extension period ) the tribunal considers reasonable; and
make any other order the tribunal considers appropriate.
If the tribunal makes an order under subsection (4) (a) , the termination day under the termination order is taken to be changed to the last day of the extension period.
s 40B ins 2024 No. 28 s 10
(sec.40B-ssec.1) This section applies if the tribunal has made a termination order in relation to a site agreement.
(sec.40B-ssec.2) The home owner may apply to the tribunal, before the termination day, for an order extending— the period for complying with an order made under section 39B (1) (a) or (b) ; or the period for complying with another order made by the tribunal in the termination order.
(sec.40B-ssec.3) On the making of an application under subsection (2) , the termination order is suspended until the application is decided.
(sec.40B-ssec.4) The tribunal may— extend the period mentioned in subsection (2) (a) or (b) by the period (the extension period ) the tribunal considers reasonable; and make any other order the tribunal considers appropriate.
(sec.40B-ssec.5) If the tribunal makes an order under subsection (4) (a) , the termination day under the termination order is taken to be changed to the last day of the extension period.
- (a) the period for complying with an order made under section 39B (1) (a) or (b) ; or
- (b) the period for complying with another order made by the tribunal in the termination order.
- (a) extend the period mentioned in subsection (2) (a) or (b) by the period (the extension period ) the tribunal considers reasonable; and
- (b) make any other order the tribunal considers appropriate.