### sec.218 Resumption for constructing authorities
A resumption may be for a constructing authority other than the State.
The costs incurred by the State for the resumption must be paid by the constructing authority.
The costs incurred are payable even if the resumption is discontinued.
Costs outstanding are a debt payable to the State and may be recovered by the State from the constructing authority in a court of competent jurisdiction.
This section is subject to the Acquisition of Land Act 1967 , section 5 (3) .
Under the Acquisition of Land Act 1967 , section 5 (3) the resumption must be for a purpose for which a constructing authority may take land.
s 218 amd 2013 No. 23 s 352 sch 1 pt 1
(sec.218-ssec.1) A resumption may be for a constructing authority other than the State.
(sec.218-ssec.2) The costs incurred by the State for the resumption must be paid by the constructing authority.
(sec.218-ssec.3) The costs incurred are payable even if the resumption is discontinued.
(sec.218-ssec.4) Costs outstanding are a debt payable to the State and may be recovered by the State from the constructing authority in a court of competent jurisdiction.
(sec.218-ssec.5) This section is subject to the Acquisition of Land Act 1967 , section 5 (3) . Under the Acquisition of Land Act 1967 , section 5 (3) the resumption must be for a purpose for which a constructing authority may take land.