### sec.406ZD Notice of hearing
The registrar must, at least 7 days before a certification application will be heard, place a notice in the registry stating details of—
the names of the parties to the agreement proposed to be a negotiated agreement; and
a relevant contract determination for the proposed negotiated agreement; and
the hearing date.
A relevant contract determination for a proposed negotiated agreement is a contract determination that—
regulates any working conditions of the independent couriers engaged in the same kind of work as the work performed by the independent couriers to be covered by the proposed agreement; and
immediately before the day the proposed agreement is certified, covers a principal contractor who engages independent couriers mentioned in paragraph (a) .
s 406ZD ins 2022 No. 27 s 66
(sec.406ZD-ssec.1) The registrar must, at least 7 days before a certification application will be heard, place a notice in the registry stating details of— the names of the parties to the agreement proposed to be a negotiated agreement; and a relevant contract determination for the proposed negotiated agreement; and the hearing date.
(sec.406ZD-ssec.2) A relevant contract determination for a proposed negotiated agreement is a contract determination that— regulates any working conditions of the independent couriers engaged in the same kind of work as the work performed by the independent couriers to be covered by the proposed agreement; and immediately before the day the proposed agreement is certified, covers a principal contractor who engages independent couriers mentioned in paragraph (a) .
- (a) the names of the parties to the agreement proposed to be a negotiated agreement; and
- (b) a relevant contract determination for the proposed negotiated agreement; and
- (c) the hearing date.
- (a) regulates any working conditions of the independent couriers engaged in the same kind of work as the work performed by the independent couriers to be covered by the proposed agreement; and
- (b) immediately before the day the proposed agreement is certified, covers a principal contractor who engages independent couriers mentioned in paragraph (a) .