### sec.9 Prescribed matters for EIS assessment report— Act , s 59
For section 59 (e) of the Act , the following matters are prescribed—
a description of the following—
the project;
the places affected by the project;
any matters of national environmental significance likely to be affected by the project;
a summary of the project’s relevant impacts;
a summary of feasible mitigation measures or changes to the project or procedures to prevent or minimise the project’s relevant impacts, proposed by the proponent or suggested in a relevant submission;
to the extent practicable, a summary of feasible alternatives to the project identified in the assessment process and the likely impact of the alternatives on matters of national environmental significance;
to the extent practicable, a recommendation for any conditions of approval for the project that may be imposed to address impacts identified in the assessment process on matters of national environmental significance.
In this section—
relevant submission means a properly made submission under section 55 (2) of the Act or a submission accepted by the chief executive under section 55 (3) of the Act .
(sec.9-ssec.1) For section 59 (e) of the Act , the following matters are prescribed— a description of the following— the project; the places affected by the project; any matters of national environmental significance likely to be affected by the project; a summary of the project’s relevant impacts; a summary of feasible mitigation measures or changes to the project or procedures to prevent or minimise the project’s relevant impacts, proposed by the proponent or suggested in a relevant submission; to the extent practicable, a summary of feasible alternatives to the project identified in the assessment process and the likely impact of the alternatives on matters of national environmental significance; to the extent practicable, a recommendation for any conditions of approval for the project that may be imposed to address impacts identified in the assessment process on matters of national environmental significance.
(sec.9-ssec.2) In this section— relevant submission means a properly made submission under section 55 (2) of the Act or a submission accepted by the chief executive under section 55 (3) of the Act .
- (a) a description of the following— (i) the project; (ii) the places affected by the project; (iii) any matters of national environmental significance likely to be affected by the project;
- (i) the project;
- (ii) the places affected by the project;
- (iii) any matters of national environmental significance likely to be affected by the project;
- (b) a summary of the project’s relevant impacts;
- (c) a summary of feasible mitigation measures or changes to the project or procedures to prevent or minimise the project’s relevant impacts, proposed by the proponent or suggested in a relevant submission;
- (d) to the extent practicable, a summary of feasible alternatives to the project identified in the assessment process and the likely impact of the alternatives on matters of national environmental significance;
- (e) to the extent practicable, a recommendation for any conditions of approval for the project that may be imposed to address impacts identified in the assessment process on matters of national environmental significance.
- (i) the project;
- (ii) the places affected by the project;
- (iii) any matters of national environmental significance likely to be affected by the project;