### sec.41B Requirements for PRCP schedule decisions
The administering authority must, for making the PRCP schedule decision—
carry out a PRCP objective assessment against each PRCP objective, and PRCP performance outcome for each PRCP objective, mentioned in schedule 8A , part 3 ; and
consider any environmental values declared under this regulation; and
consider each of the following under any relevant environmental protection policies—
the management hierarchy;
environmental values;
quality objectives;
the management intent.
The administering authority may approve or amend a PRCP schedule only if each PRCP objective for the PRCP schedule is achieved under schedule 8A .
s 41B ins 2019 SL No. 198 s 8
(sec.41B-ssec.1) The administering authority must, for making the PRCP schedule decision— carry out a PRCP objective assessment against each PRCP objective, and PRCP performance outcome for each PRCP objective, mentioned in schedule 8A , part 3 ; and consider any environmental values declared under this regulation; and consider each of the following under any relevant environmental protection policies— the management hierarchy; environmental values; quality objectives; the management intent.
(sec.41B-ssec.2) The administering authority may approve or amend a PRCP schedule only if each PRCP objective for the PRCP schedule is achieved under schedule 8A .
- (a) carry out a PRCP objective assessment against each PRCP objective, and PRCP performance outcome for each PRCP objective, mentioned in schedule 8A , part 3 ; and
- (b) consider any environmental values declared under this regulation; and
- (c) consider each of the following under any relevant environmental protection policies— (i) the management hierarchy; (ii) environmental values; (iii) quality objectives; (iv) the management intent.
- (i) the management hierarchy;
- (ii) environmental values;
- (iii) quality objectives;
- (iv) the management intent.
- (i) the management hierarchy;
- (ii) environmental values;
- (iii) quality objectives;
- (iv) the management intent.