QLDIn ForceAct
Environmental Protection Act 1994
sec.573Notice of decision
Start here
Get a plain-English read of sec.573
Turn the raw legal text into a practical explanation grounded in Environmental Protection Act 1994.
### sec.573 Notice of decision
The chief executive must, within 10 business days after the decision is made, give the applicant written notice of the decision.
The notice must—
if the decision is to approve the application—be accompanied by a certificate of approval; and
if the decision is to refuse the application—state the reasons for the decision.
s 573 prev s 573 ins 2000 No. 64 s 46
om 2011 No. 6 s 92
pres s 573 ins 2012 No. 16 s 58
(sec.573-ssec.1) The chief executive must, within 10 business days after the decision is made, give the applicant written notice of the decision.
(sec.573-ssec.2) The notice must— if the decision is to approve the application—be accompanied by a certificate of approval; and if the decision is to refuse the application—state the reasons for the decision.
- (a) if the decision is to approve the application—be accompanied by a certificate of approval; and
- (b) if the decision is to refuse the application—state the reasons for the decision.