### sec.278A Effect of cancellation or suspension of environmental authority on PRCP schedule
If a PRCP schedule applies for carrying out a relevant activity to which a suspended environmental authority relates, the schedule—
continues in force for the relevant activity; and
is not affected by the suspension.
If a PRCP schedule applies for carrying out a relevant activity under an environmental authority that is cancelled, the schedule ceases to have effect on the cancellation.
s 278A prev s 278A ins 2005 No. 53 s 75
om 2012 No. 16 s 7
pres s 278A ins 2018 No. 30 s 171
(sec.278A-ssec.1) If a PRCP schedule applies for carrying out a relevant activity to which a suspended environmental authority relates, the schedule— continues in force for the relevant activity; and is not affected by the suspension.
(sec.278A-ssec.2) If a PRCP schedule applies for carrying out a relevant activity under an environmental authority that is cancelled, the schedule ceases to have effect on the cancellation.
- (a) continues in force for the relevant activity; and
- (b) is not affected by the suspension.