Electricity Act 1994
sec.59Authorisation given by special approval
Start here
Get a plain-English read of sec.59
Turn the raw legal text into a practical explanation grounded in Electricity Act 1994.
### sec.59 Authorisation given by special approval
A special approval authorises its holder to do the things stated in the approval, even though the things would otherwise require the holder to be the holder of a generation, transmission or distribution authority to do the things.
Despite subsection (1) , a special approval does not make the holder an electricity entity, unless a regulation provides that the holder is to be treated as an electricity entity.
However, for things authorised by the special approval, the special approval holder is taken to be a person who has the relevant authority and the special approval is taken to be the relevant authority.
If a special approval authorises the holder to connect generating plant to a transmission grid or supply network, the holder is taken, for that activity, to be the holder of a generation authority.
If a special approval authorises the holder to operate a transmission grid, the holder is taken, for that activity, to be the holder of a transmission authority.
The approval does not relieve the holder or anyone else from complying with laws relevant to the doing of the things authorised by the approval.
s 59 amd 1997 No. 26 s 23 ; 2014 No. 48 s 37
(sec.59-ssec.1) A special approval authorises its holder to do the things stated in the approval, even though the things would otherwise require the holder to be the holder of a generation, transmission or distribution authority to do the things.
(sec.59-ssec.2) Despite subsection (1) , a special approval does not make the holder an electricity entity, unless a regulation provides that the holder is to be treated as an electricity entity.
(sec.59-ssec.3) However, for things authorised by the special approval, the special approval holder is taken to be a person who has the relevant authority and the special approval is taken to be the relevant authority. If a special approval authorises the holder to connect generating plant to a transmission grid or supply network, the holder is taken, for that activity, to be the holder of a generation authority. If a special approval authorises the holder to operate a transmission grid, the holder is taken, for that activity, to be the holder of a transmission authority.
(sec.59-ssec.4) The approval does not relieve the holder or anyone else from complying with laws relevant to the doing of the things authorised by the approval.
- 1 If a special approval authorises the holder to connect generating plant to a transmission grid or supply network, the holder is taken, for that activity, to be the holder of a generation authority.
- 2 If a special approval authorises the holder to operate a transmission grid, the holder is taken, for that activity, to be the holder of a transmission authority.