### sec.129A Limitation for Stanwell Magnesium Plant
This section applies if, apart from this section, an electricity restriction regulation or emergency rationing order applies to the supply of electricity to, or the use of electricity at, the Stanwell Magnesium Plant.
The regulation or rationing order applies only to the supply of electricity to, or the use of electricity at, the plant that is more than the demand prescribed under a regulation.
The prescribed demand—
must be at least 50MW; but
must not be more than 100MW.
Subsection (2) applies despite any other provision of this part.
In this section—
Stanwell Magnesium Plant means the magnesium production plant that Australian Magnesium Operations Pty Ltd (ABN 38 058 918 175) has built, or proposes to build, adjacent to the electricity generating facility at Stanwell called the ‘Stanwell Power Station.
s 129A ins 2001 No. 46 s 6
exp 31 December 2033 (see s 129B)
(sec.129A-ssec.1) This section applies if, apart from this section, an electricity restriction regulation or emergency rationing order applies to the supply of electricity to, or the use of electricity at, the Stanwell Magnesium Plant.
(sec.129A-ssec.2) The regulation or rationing order applies only to the supply of electricity to, or the use of electricity at, the plant that is more than the demand prescribed under a regulation.
(sec.129A-ssec.3) The prescribed demand— must be at least 50MW; but must not be more than 100MW.
(sec.129A-ssec.4) Subsection (2) applies despite any other provision of this part.
(sec.129A-ssec.5) In this section— Stanwell Magnesium Plant means the magnesium production plant that Australian Magnesium Operations Pty Ltd (ABN 38 058 918 175) has built, or proposes to build, adjacent to the electricity generating facility at Stanwell called the ‘Stanwell Power Station.
- (a) must be at least 50MW; but