### sec.79 Conditions of allocation notice
The chief executive may impose conditions on the allocation notice the chief executive considers necessary or desirable for coastal management, including, for example, conditions about—
the maximum rate at which the quarry material may be removed; and
monitoring the impact of the removal of the quarry material or placement of spoil on coastal management; and
the nature and extent of surveys to be carried out in relation to the removal of the quarry material or placement of spoil; and
when the royalty, or price payable, for the removal of the quarry material must be paid; and
giving the chief executive information about the rate at which the quarry material is removed during stated intervals.
s 79 ins 2001 No. 93 s 15
amd 2011 No. 6 s 27
- (a) the maximum rate at which the quarry material may be removed; and
- (b) monitoring the impact of the removal of the quarry material or placement of spoil on coastal management; and
- (c) the nature and extent of surveys to be carried out in relation to the removal of the quarry material or placement of spoil; and
- (d) when the royalty, or price payable, for the removal of the quarry material must be paid; and