### sec.32 Drawings of electrical installations
The site senior executive for a coal mine must ensure up-to-date drawings of the mine’s electrical installations are available for use at the mine when electrical equipment and electrical installations are commissioned or modified.
The drawings must be updated as soon as practicable, but not later than 8 days, after—
the commissioning of any electrical equipment or electrical installation at the mine; or
any major modification to electrical equipment or an electrical installation at the mine.
The drawings must be kept in a location that is easily accessible by each coal mine worker authorised by an electrical supervisor or the coal mine’s electrical engineering manager to access the drawings.
(sec.32-ssec.1) The site senior executive for a coal mine must ensure up-to-date drawings of the mine’s electrical installations are available for use at the mine when electrical equipment and electrical installations are commissioned or modified.
(sec.32-ssec.2) The drawings must be updated as soon as practicable, but not later than 8 days, after— the commissioning of any electrical equipment or electrical installation at the mine; or any major modification to electrical equipment or an electrical installation at the mine.
(sec.32-ssec.3) The drawings must be kept in a location that is easily accessible by each coal mine worker authorised by an electrical supervisor or the coal mine’s electrical engineering manager to access the drawings.
- (a) the commissioning of any electrical equipment or electrical installation at the mine; or
- (b) any major modification to electrical equipment or an electrical installation at the mine.