### sec.105 Certificates for a building occupied in stages
This section applies if—
the building is unfinished; and
its owner has been given a certificate of occupancy for part of it; and
the building certifier has consented to the occupation of a further part of the building.
The building certifier must ensure the owner is given a further certificate of occupancy for the further part.
The further certificate must comply with the certificate requirements.
See also section 132 .
s 105 ins 2006 No. 36 s 5
amd 2020 No. 24 s 153 s ch 1 pt 2
(sec.105-ssec.1) This section applies if— the building is unfinished; and its owner has been given a certificate of occupancy for part of it; and the building certifier has consented to the occupation of a further part of the building.
(sec.105-ssec.2) The building certifier must ensure the owner is given a further certificate of occupancy for the further part.
(sec.105-ssec.3) The further certificate must comply with the certificate requirements. See also section 132 .
- (a) the building is unfinished; and
- (b) its owner has been given a certificate of occupancy for part of it; and
- (c) the building certifier has consented to the occupation of a further part of the building.