© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2016] NSWCA 97
Court of Appeal (NSW)
2016-04-15
Gleeson JA, Payne JA
Original judgment source is linked above.
Solicitors: Hall Partners (Appellants) Howard S Charles & Co (Respondents) File Number(s): 2015/219634 Decision under appeal Court or tribunal: District Court of New South Wales Jurisdiction: Civil Date of Decision: 29 May 2015 Before: Sorby DCJ File Number(s): 2013/205075
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This Headnote is not to be read as part of the judgment] By contract dated 13 July 2007 the respondents sold a business to the appellants. Pursuant to the contract the appellants took immediate possession of the business, paid a deposit, and were required to pay the balance (subject to certain adjustments) after the expiry of a 30-day settlement period. The appellants failed to complete, and the respondents commenced proceedings in the District Court of NSW calling on the balance of the contract price. The respondents also claimed interest pursuant to special condition 9 of the contract, which provided that if the purchaser did not complete, "without default by the vendor", interest ran on the outstanding amount. By cross-claim the appellants alleged that the respondents had breached special condition 16 of the contract. That clause obliged one of the respondents, Mr Gooding, to "assist" the appellants in respect of various matters including by providing tuition and introducing the appellants to clients of the business. In relation to the main claim the primary judge found that the appellants were obliged to pay the balance of the contract price. The respondents were also entitled to interest under the contract. In relation to the cross-claim the primary judge found that the respondents had not breached special condition 16 of the contract. The appellants appealed from the primary judge's decision. They contended that the primary judge erred in awarding interest because the respondents had failed to adjust for certain employee entitlements. This, they submitted, engaged the "default" exception in special condition 9. They also appealed the primary judge's finding on the cross-claim that the respondents were not in breach of special condition 16. Held by Payne JA (Gleeson JA and Emmett AJA agreeing): (1) The argument that the respondents failed to adjust for employee entitlements, and were therefore in "default" for the purposes of special condition 9, was not put before the primary judge: [46]-[48]. The appellants were not entitled to raise a new argument in the appeal: [50]-[52]. Whisprun Pty Ltd v Dixon [2003] HCA 48; 200 ALR 447 (2) The appellants were not entitled to adduce further evidence on the appeal because no "special grounds" pursuant to s 75A(8) of the Supreme Court Act 1970 (NSW) had been made out: [55]. (3) The word "default" in special condition 9 was a default referrable to completion: [59]-[60]. (4) On a proper construction of special condition 16, Mr Gooding was obliged to take reasonable steps to assist the purchaser as and when requested to do so by the purchaser: [68]-[72]. He was not required to act absent any request from the purchaser: [73]-[74]. (5) Even if breach had been established, the appellants' evidence was insufficient to discharge the onus of proving, on the balance of probabilities, that Mr Gooding's breach caused any loss: [88]-[107]. Placer (Granny Smith) Pty Ltd v Thiess Contractors Pty Ltd [2003] HCA 10; 77 ALJR 768; 196 ALR 257 Dasreef Pty Ltd v Hawchar [2011] HCA 21; 243 CLR 588
Judgment
Relevant facts
The proceedings in the District Court
Issues on this Appeal
Vendor's Primary Claim
Purchaser's Cross-Claim 2) Was special condition 16 of the Contract breached? 3) Assuming special condition 16 of the Contract was breached, did Zaps Transport prove that it suffered any loss or damage by reason of that breach? If so, what was the appropriate basis to calculate that loss and what was its quantum?
Issue 1 - Were the vendors entitled to interest under the Contract on the amount awarded by the primary judge as the Contract price?
Issue 2 - Was special condition 16 of the Contract breached?
Issue 3 - Causation and loss on the cross claim
Orders
Amendments 10 May 2016 - At [64] "Keifel" was changed to "Kiefel". DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 10 May 2016
Zaps Transport (Aust) Pty Ltd
PJG Warehousing & Distribution Pty Ltd
[1998] HCA 42
[1994] HCA 4
[2003] HCA 48
(1996) 67 FCR 402
(1982) 149 CLR 337
[2003] HCA 10
[2011] HCA 21