Ground 4
49The appellants submitted that, even if the Court rejected the submission that the words "after the Date of Final Acceptance (as defined under the Head Contract)" must be ignored for the purposes of determining whether they were entitled to the release of the retention monies, it was still necessary to ascertain the Date of Final Acceptance. They submitted that that task was to be undertaken by reference to the terms of the Head Contract as at the date the subcontracts were entered into. This was central to the appellants' argument, because after the appellants had entered into their subcontracts, Lend Lease and the Commonwealth, without the appellants' knowledge, had agreed to an extension of the Date of Final Acceptance on four separate occasions by entering into deeds of agreement which were not in conformity with the provisions of cl 14 of the Head Contract relating to extension of time under the Head Contract.
50The appellants submitted that upon the proper construction of the Head Contract, unaltered by the amending deeds, the Date for Final Acceptance and for the expiration of the Defects Liability Period were objectively ascertainable and in fact had passed.
51The process of construction on this argument was as follows. First, under the Head Contract, the defined Date for Final Acceptance was 48 months from the Commencement Date, which was admitted to be 8 June 2007. Accordingly, the Date for Final Acceptance was 8 June 2011. Secondly, by reference to the provisions of the subcontract, the Defects Liability Period expired 24 months after the Date of Final Acceptance. The appellants contended, therefore, that they were entitled to the release of the retention monies as and from 8 June 2013 and they had given notice claiming those monies as required by the terms of the subcontract. The appellants submitted that this construction was supported by the commercial purpose of these clauses in the subcontract.
52Lend Lease submitted that this was an incorrect construction of the Head Contract with no basis in principle. Lend Lease pointed out that, on the terms set out in the Head Contract prior to its amendment by the four amending deeds, it was not necessarily required to achieve Final Acceptance 48 months after the commencement of the Head Contract. Rather, cl 14.1 of the Head Contract provided that Lend Lease must "achieve Final Acceptance of the Works ... by the relevant Date for Final Acceptance".
53Lend Lease submitted that the Date for Final Acceptance was not a set date. Rather, it was a date which was to be determined having regard to the manner in which the contract worked itself out. There may be an acceleration of the works or there may be delays. In either case, the contract made provision for the consequences thereof which may affect the Date for Final Acceptance.
54It followed, on Lend Lease's submission, that the construction that the appellants seek to advance required that the words of the subcontract be "notionally replaced" or read as "Defects Liability Period will expire 24 months after the Date for Final Acceptance", not "Date of Final Acceptance", being the expression used in the Appendix of the subcontracts (emphases added). Senior Counsel for the appellants frankly admitted that this was the consequence of his submission.
55In my opinion, there is merit in the appellants' argument that their subcontracts should be construed by reference to the Head Contract in its form as at the date of entry into the appellants' respective subcontracts. However, accepting that to be so, I consider that the appellants' construction of the Defects Liability Period should be rejected. Senior Counsel for the appellants accepted that on the appellants' construction, it was necessary to draw an inference that in the absence of evidence of extensions of time, the Date of Final Acceptance was the same as the Date for Final Acceptance. He submitted that that followed from the provisions of cl 14(1)(c) of the Head Contract, namely, that Lend Lease must "achieve Final Acceptance of the Works ... by the relevant Date for Final Acceptance".
56The difficulty in drawing that inference, however, is that there was no evidence to support it. There was a complete absence of evidence as to whether the Date for Final Acceptance had been achieved by reference to the terms of the Head Contract in its unamended form. At the most, the appellants were able to assert that, if all had remained constant in the performance of the contract so that there had been no basis upon which an extension of time might have been granted, the Date for Final Acceptance was 8 June 2011 and, it would follow, on the appellants' argument, that the Date of Final Acceptance would have been the same.
57It is readily apparent that the appellants cannot succeed on an argument that required evidence for its success. They had the legal onus of adducing at least some evidence to establish that nothing had occurred in the performance of the contract by Lend Lease such as to entitle it to an extension of time. Indeed, it is highly unlikely that that would have been the case and the amending deeds, although not providing for extensions in accordance with cl 14 of the Head Contract, would tend to indicate that that was not likely.
58I should also add that the appellants pointed out that that it was possible, at least theoretically, that Final Acceptance under the Head Contract may never be achieved, so that they could be kept out of the retention monies permanently. However, this last submission failed to take into account the availability of other legal principles, including principles relating to the frustration of contract and those which require parties to do all such things as are necessary to enable the other party to have the benefit of the contract: see Mackay v Dick (1881) 6 App Cas 251.
59Having regard to this conclusion, leave should not be granted to the appellants to put to the Court this alternative argument, which was not advanced in the court below. Accordingly, I propose the following orders:
(1) Leave for the appellants to amend their notices of appeal refused;
(2) Appeal dismissed with costs.
60MACFARLAN JA: I agree with Beazley P.
61EMMETT JA: These appeals are concerned with the proper construction of subcontracts entered into between the appellants, on the one hand, and the respondent, Lend Lease Building Pty Ltd (LLB), on the other. Three subcontracts were entered into by Christopher and Cathy Wright (the Wrights) and a fourth subcontract was entered into by Intercon Engineering Pty Ltd (Intercon). The four subcontracts are relevantly in identical terms and the same question arises in each appeal.
62On 8 June 2007, LLB entered into a deed of agreement with the Commonwealth of Australia (the Head Contract) for the design, construction, commissioning and qualification of the modernised Mulwala facility. By cl 3.1(a), LLB undertook an obligation to design, construct, complete, commission and qualify the Works, in return for which the Commonwealth was obliged to pay to LLB the Contract Price. The Contract Price consisted of a lump sum in Australian dollars, US dollars and Great Britain pounds. The Head Contract expressly contemplated that there would be subcontractors in respect of the activities of LLB under the Head Contract. Neither the Wrights, nor Intercon, were parties to the Head Contract. Indeed, it was common ground that when the subcontracts were entered into, they did not have access to the Head Contract.
63By the subcontracts, the subcontractors agreed to execute and complete, diligently and expeditiously, the whole of the Works as defined in the relevant subcontract. LLB was obliged to pay each subcontractor a lump sum in Australian dollars. The subcontracts referred to the Head Contract as the agreement, arrangement or understanding with the Commonwealth under which LLB was to execute certain work, of which the Works described in the subcontracts formed part.
64Part 10 of the subcontracts dealt with measurement, payment and adjustment to the subcontract sum. Under cl 10.5.1, the subcontractor was required to deliver to LLB claims for payment at the times specified. The prerequisites for a payment claim were set out in cl 10.5.1. Clause 10.7 specified certain conditions precedent to payment.
65Under cl 10.8.1.1, LLB was required, within ten business days of receipt of a claim for payment, to assess the claim and to issue a payment schedule setting out the retention to be deducted (at the rate and to the limit specified) and setting out amounts otherwise due under the subcontract from LLB to the subcontractor and from the subcontractor to LLB. The payment schedule was also required to set out any amount that LLB is entitled to retain under the subcontract. Clause 10.9 provided that, in lieu of the retention referred to in cl 10.8.1.1, the subcontractor may provide irrevocable banker's undertakings for the amount equal to the limit of the retention specified in the subcontract.
66The critical clause for present purposes is cl 10.10.1. Clause 10.10.1 contemplated release in two tranches of the retention, whether in the form of money or in the form of a banker's undertaking. One half of the banker's undertaking or money retained was to be released on the later of Substantial Completion and receipt by LLB of a written request from the subcontractor for release. There is no dispute concerning the release of the first tranche of the retention.
67The dispute concerns the provisions of cl 10.10.1 relating to the release of the remainder of the retention by the banker's undertaking or money. LLB is required to release the remaining banker's undertaking or the balance of the money retained upon the later of:
(1)the making good of defects and other matters not in accordance with the subcontract;
(2)the expiration of the Defects Liability Periods; and
(3)receipt by LLB of a written request from the subcontractor for release.
68Clause 9.7 of the subcontracts deals with Defects Liability Periods. Under cl 9.7.1, the Defects Liability Period for the Works was to commence on the Date of Substantial Completion. Date of Substantial Completion is the date on which the Works are brought to Substantial Completion. Substantial Completion is when the Works are complete except for minor omissions and minor defects. There is no dispute that the Date of Substantial Completion has occurred.
69Clause 9.7.2 of the subcontracts provides that each of the Defects Liability Periods will expire at the end of the period stated in the Appendix to the subcontracts. The Appendix provides that the Defects Liability Periods will expire 24 months after the Date of Final Acceptance, as defined under the Head Contract. Thus, it is necessary to have regard to the Head Contract to determine when the Defects Liability Period expires for the purposes of determining whether LLB is under an obligation to release the remaining retention to the subcontractors.
70Clause 14.1 of the Head Contract provided that LLB must regularly and diligently progress the Activities (as defined), achieve Practical Completion (as defined) of the Works by the relevant date for Practical Completion and must achieve Final Acceptance of the Works by the relevant Date for Final Acceptance. Thus, the Head Contract draws an obvious distinction between achieving Final Acceptance of the Works, on the one hand, and the date by which LLB was contractually bound to achieve Final Acceptance, on the other. The Head Contract provides in Schedule 1 that the Date for Final Acceptance for the Works was 48 months from the Commencement Date. Relevantly, the Commencement Date was 8 June 2007, the date of signing the Head Contract.
71Under the Head Contract, Final Acceptance is when:
- Practical Completion of the Works has occurred;
- LLB has completed all items of minor defects that do not prevent the Works from being reasonably capable of being used for their intended purpose;
- The Works have successfully been commissioned and tested;
- LLB has carried out and passed certain performance tests;
- All documents and other information required for the use, operation and maintenance of the Works have been supplied;
- All subcontractor warranties required under the Head Contract have been supplied; and
- LLB has done everything that the Head Contract requires it to do as a condition precedent to Final Acceptance of the Works.
Thus, Final Acceptance describes the final completion of the Works to be performed by LLB under the Head Contract. The Date of Final Acceptance is then defined as the date by which the Works achieve Final Acceptance and all other pre-conditions to Final Acceptance are satisfied. Clearly enough, one could not know in advance what the Date of Final Acceptance might be. That is to say, the time when the Works achieve Final Acceptance will depend upon the vagaries of performance and the like. On the other hand, the Date for Final Acceptance was fixed in advance and was known to the parties to the Head Contract.
72Final Acceptance of the Works under the Head Contract has not yet been achieved. However, there was no evidence that the subcontractors had failed to make good defects or other matters not in accordance with the subcontracts.
73Clause 6.9.1 of the subcontracts provides that, at any time prior to the expiry of a Defects Liability Period, LLB may, by notice, instruct the subcontractor to make good a defect or other matter not in accordance with the subcontracts. Under cl 6.9.3, if the subcontractor fails to comply promptly with an instruction or make good a defect by the date stipulated, LLB may carry out or complete the instruction and the subcontractor will be liable for losses suffered by LLB. It was common ground that there was no written notice under cl 6.9.1 that had not been complied with.
74LLB contends that the time for release of the remaining retention has not yet arrived because the Defects Liability Period has not expired. It relies on the fact that there has not yet been Final Acceptance of the Works by the Commonwealth under the Head Contract and therefore the date of Final Acceptance has not yet arrived.
75It might have been open to the subcontractors to adduce evidence to the effect that the failure to achieve Final Acceptance was the result of some default on the part of LLB. No suggestion to that effect was made. Further, it may have been possible for the subcontractors to adduce evidence to show that, while Final Acceptance of the Works under the Head Contract had not yet been achieved, Final Acceptance of the Works under each of the subcontracts had been achieved. Once again, there was no evidence to that effect.
76The contentions advanced on the appeal by the subcontractors come down to the construction of cl 10.10.1. First, they contend that, because the Date of Final Acceptance could not be ascertained at the date of the subcontracts and may never occur, the Defects Liability Period should be understood as expiring at the end of the only period stated in the Appendix, being 24 months. Alternatively, they contend that the Date of Final Acceptance should be understood as referring to the Date for Final Acceptance. The Date for Final Acceptance was 48 months after the commencement of the Head Contract. That period has now expired.
77In fact, the Date for Final Acceptance was varied by the Commonwealth and LLB on 9 February 2011 to provide that the Date for Final Acceptance was to be 24 February 2013. However, there was no evidence as to the circumstances in which that variation occurred. In particular, there was no evidence to indicate that there was any lack of good faith or that there was default on the part of LLB.
78There is no ambiguity in the language of cl 10.10.1 or in the definition of the terms that are employed for the purposes of determining the expiration of the Defects Liability Period. The primary judge concluded that the Defects Liability Period, for the purpose of the subcontracts, has not yet expired and that, accordingly, the subcontractors are not yet entitled to the release of the remaining retention.
79I have had the advantage of reading in draft form the proposed reasons of the President. I agree with her Honour, for the reasons proposed by her, that leave to amend the notice of appeal should be refused and that the appeal should be dismissed with costs.