7 The agreed statement of facts are:
(1) At approximately 7:35pm on 23 May 1998 an employee of LBJ, Rodney Michael Fox ('Fox'), sustained fatal injuries when struck by a Tangara passenger train travelling on the Down Main line between Burwood and Strathfield Railway Stations, west of the Wentworth Road overbridge, Burwood.At all material times RSA had the principle function of supplying goods and services to the rail industry.
(2) At all material times RSA was engaged in stage six of the Central to Strathfield overhead wiring upgrade/replacement ('the work'). The work involved the delivery and erection of metal structures that support aerial wires from which electric trains obtain their power. Five earlier stages had been successfully completed without incident.
(3) At all material times RSA had employed subcontractors, including LBJ Crane and Rigging Pty Limited ('LBJ').
(4) The incident occurred immediately adjacent to the work site where the work was being undertaken. At the work site, RSA had possession of the four southern lines, that is (from south to north), the Down Local, the Up Local, the Down Suburban and Up Suburban lines. Trains were running on the two remaining 'live' tracks, that is from south to north still, the Down Main and Up Main lines. The distance between the closest rails of the adjoining Up Suburban line and the live Down Main line was approximately 3.5 metres.
(5) Twelve of the metal structures, or beams, that were being delivered and erected were of a length of approximately 15 metres. The remaining two beams were approximately 25 metres in length. LBJ was to unload the beams from trolleys on the Down Suburban line and place the beams in designated positions to be erected sometime later by another crane.
(6) At about 6:00pm on the said day the two larger beams were moved by means of the Kato (owned by LBJ) and Franna (owned by Harley Cranes Pty Ltd) mobile cranes, one crane at each end. Each of the cranes had headlights. The Kato/LBJ crane was operated by Rodney John Wigzell ('Wigzell'). Fox was acting as Dogman for Wigzell. The last beam was to be placed in the four foot area of the Up Suburban line. The load was 29 metres long by approximately 2 metres high and almost parallel to the track. It was while this last beam was being lifted into a position length wise on the Up Suburban line that Fox moved into the six foot area near the live Down Main line. Annexed to this Statement and marked 'A' is a diagram providing a layout of the immediate vicinity of the incident.
(7) Fox was in all likelihood directing the lift in accordance with WorkCover's 'Guide for Dogman and Crane Chasers' which states that 'when lifting with 2 cranes only one person is directing the lift'. Both cranes were working in the boom-out fashion because of the overhead wiring. The overhead wiring was not live but contact with the wiring was to be avoided to ensure that no damage was done to it.
(8) The Franna/ Harley crane at the Strathfield end of the load did not have a rotating boom nor did it have stabiliser leg. It was an articulated four-wheel drive vehicle with the crane driver/operator positioned under the boom. The Kato/LBJ crane at the opposite end of the load (for which Fox was Dogman) had a rotating boom and stabiliser leg. The operator cabin was located on the right had side of the boom, when viewed from behind.
(9) Fox had to move to the live side of the Kato/LBJ crane in order to talk with the crane operator as the crane boom blocked the operator from him if he remained on the left side.
(10) Both cranes lights were pointing forwards, both crane operators were facing forward (that is, toward the load slung between them), consequently Fox needed to be in their view to control the dual lift.
(11) The Kato/LBJ crane had its end of the load suspended above the point where it would eventually place it. Both cranes had secured the load at a point approximately two metres in from the end of the load. This was necessary because knee braces were already attached to the beam. This meant that the ends of the load were close to the front of the crane body. This coupled with the angled (relative to the track) position of the cranes meant that Fox, in all probability, could not clearly see the ends of the load from anywhere but the 'live' side of the possession.
(12) In his statement to Inspector Vierow, Kim Easther stated:
'When Harley's crane lifted their end approximately 300 millimetres above the ground and it slewed towards Rodney, it appeared to startle him, and it appeared to me that he stumbled to the north towards the live line.'
(13) Fox was last seen by Wigzell to be standing to the right hand side of the Kato/LBJ crane between the live (Down Main) line and the dead (Up Suburban) line. At the time the deceased was struck he was wearing a reflective vest and hard hat.
(14) The train which struck Fox was travelling at approximately 70 kilometres per hour. Approximately 30 metres past Burwood Road Bridge on the Strathfield side the driver heard a noise that sounded like the wheels of the train running over ballast as a result of which he applied the brakes and came to a stand approximately 100 metres from Strathfield station. The train guard looked back up the track but was unable to see anything. The train then proceeded on.
(15) On 23 May 1998 at approximately 10:00pm Inspector Kumar attended and made an inspection of the incident site. A series of coloured photographs were taken.
(16) On the day of the incident Fox had been picked up by a work mate, Wigzell, at about 2:00am. They drove to Lilyfield and picked up the crane and then went to the work site arriving at about 3:00am.
(17) Anwar Abdelmessieh, Ganger, was RSA's Acting Site Supervisor on the said day. Approximately two weeks prior to the date on which the work was undertaken, Abdelmessieh had walked the section with site managers and other supervisors, including Peter Petrovski. At that time Abdelmessieh had discussed what could be done in the possession, the work method, the plant and equipment required for the work and how to get it to the locations.
(18) Abdelmessieh gave a work site induction to the crane crew at approximately 4:00am on the said day at RSA's Burwood site office, including a briefing in relation to what protection was in place. He also walked the first part of the Burwood stockpile site with the crane crew explaining what they had to do.
(19) John Arthur Quinn, RSA Construction Worker, held the Electrical Permit on the said day. At 4:00am Quinn was instructed by Abdelmessieh to sign the electrical permit and to induct personnel in the overhead wiring, advising what wires were live and what wires were dead.
(20) Together with Abdelmessieh, Quinn gave a briefing at the Burwood site office at the country side of Strathfield station to all work site staff including subcontractors, crane operators, riggers and dogmen from some time after 4:00am to about 8:00am regarding the power outage and the running of trains on the live lines. Quinn's briefing covered what procedures were to be undertaken that day. Quinn told the staff which overhead power wires were live and which ones were dead and informed them that the Up and Down Mains were live with trains running. Quinn asked the staff present if they understood and to sign the personnel register saying that they understood by printing their name and then signing.
(21) As such, Quinn instructed Fox and Wigzell in relation to the power on/power off situations and in relation to which lines trains were running, and, at about 8:00am, signed Fox and Wigzell onto the Electrical Permit.
(22) Prior to the work commencing Quinn was instructed by Abdelmessieh to check the possession protection and the protection of the work site.
(23) In this regard Quinn physically walked to the Country end of the work site. He checked the possession protection was still in place - and found protection on the Down Local, Up Local, Down Suburban and Up Suburban consisting of a red flag in the four foot of each line and three detonators on the country end of the red flag.
(24) Quinn then walked through the job site to the City end of the work site - and confirmed protection on the Down Local, Up Local, Down Suburban and Up Suburban, consisting of a red flag in the four foot of each line and three detonators on the city end of the red flag.
(25) At about 10:00am Fox, and Wigzell, were escorted onto the work site.
(26) Subject to meal breaks, Fox and Wigzell then worked until about 6:00pm at which time they were packed up and ready to go home. They were then approached and told that the Harley's crane was coming around and to give a hand to unload two more stanchions.
(27) The work was expected to be finished by about 4:30pm on the day. However, due to the overhead wiring train which was conducting work on the track in front of the exit from the storage depot where the beams were held prior to their movement to the track, there was a three and half hour delay to the work of placing the beams.
(28) Once night fell, lighting at the area where the lift was being undertaken was provided by the headlights and boom lights of the Kato/LBJ crane and the headlights of the Franna/Harley mobile crane, both of which were undertaking the lift.
(29) John Tadic, RSA Construction Worker, checked the qualifications of all riggers during the course of his shift on the said day. He had the riggers sign on the paper putting their names and the companies they worked for prior to the commencement checking their rigging tickets, safety boots and helmets and safety vests.
(30) The beams were being laid out at various locations in the work site. They were being loaded from the Country end of Burwood station on to trolleys which were pulled down to the locations by balloon tyre dumpers. These dumpers were escorted by PW11 Hand Signallers. Tadic was with the crane at the location where the beams where unloaded. After unloading each structure, before moving to the next location, Tadic and Quinn would walk the Dogman to the next location before the movement of the crane. Tadic would point out to the Dogman where the beam was supposed to go, but asked the Dogman's opinion as to whether the beam could be put there. If the Dogman advised no, Tadic would ask where the possible place to put it was. Quinn would then walk with the Dogman back to the crane and then they would walk together to the next location for unloading. At times the crane driver would accompany them as well.
(31) As at the said date RSA's procedures for work on or about railway lines was governed by a written manual entitled 'Safe working procedures for Engineering Work' - the 900 series. This manual was developed prior to the disaggregation of SRA in 1996. When disaggregation occurred SRA kept control of the Safe Working Units ('SWU's'). All persons working on or near railway lines were required to comply with them. The manual set out the procedures to be adopted when any type of engineering work was carried out on or about railway infrastructure. The work could relate to the repair, maintenance or upgrading or railway tracks or associated works. This manual comprised a significant number of individual SWU's identified and distinguished by numbers. The individual SWU's were not intended to be implemented in isolation but considered as forming part of the 900 series such that, depending on the prevailing circumstances, individual SWU's could be implemented in concert in any one work situation.
(32) Safe Working Unit 900 provided, inter alia, the following:
· This manual sets out the procedures which must be adopted when any type of engineering work is to be carried out on about Railway Infrastructure. This work may relate to the repair, maintenance or upgrading of railway tracks, rolling or associated works and equipment [SWU 900[a]];