© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2001] NSWIRComm 97
Industrial Relations Commission (NSW)
2001-05-11
Hungerford J, Mr P
Original judgment source is linked above.
Industrial Relations Commission of New South Wales in Court Session
CITATION : WorkCover Authority of New South Wales (Inspector Carmody) v Develco Project Pty Ltd (No 1) [2001] NSWIRComm 97 PROSECUTOR WorkCover Authority of New South Wales (Inspector Martin Carmody) PARTIES : DEFENDANT Develco Project Pty Limited FILE NUMBER: IRC 2636 of 1999 CORAM: Hungerford J CATCHWORDS : Courts and Judges - Bias - Disqualification on ground of pre-judgment in related proceedings - Same issue of fact - Credibility of same witness - Principles to apply - Held, disqualification from proceedings required. LEGISLATION CITED : Occupational Health and Safety Act 1983 s 16(1) Australian National Industries Ltd v Spedley Securities Ltd (In Liq) (1992) 26 NSWLR 411 Livesey v New South Wales Bar Association (1983) 151 CLR 288 R v Australian Stevedoring Industry Board, Ex parte Melbourne Stevedoring Co Pty Ltd (1953) 88 CLR 100 CASES CITED : R v Masters (1992) 26 NSWLR 450 R v Perry (1993) 29 NSWLR 589 Re JRL, Ex parte CJL (1986) 161 CLR 342 Re Polites, Ex parte Hoyts Corporation Pty Ltd (1991) 173 CLR 78 WorkCover Authority of New South Wales (Inspector Carmody) v Byrne Civil Engineering Constructions Pty Ltd (No 1) [2001] NSWIRComm 33 HEARING DATES: 03/22/2001; 04/19/2001 DATE OF JUDGMENT: 05/11/2001
PROSECUTOR Mr W G Roser of counsel Solicitor: Ms M Lagana WorkCover Authority of New South Wales LEGAL REPRESENTATIVES: DEFENDANT Mr P M Hall QC and Mr A B Gotting of counsel Solicitor: Mr D Cross Allen Allen & Hemsley
JUDGMENT: - 1 - INDUSTRIAL RELATIONS COMMISSION OF NEW SOUTH WALES IN COURT SESSION CORAM: HUNGERFORD J Friday, 11 May 2001 Matter No IRC 2636 of 1999 WORKCOVER AUTHORITY OF NEW SOUTH WALES (INSPECTOR MARTIN CARMODY) v DEVELCO PROJECT PTY LIMITED Prosecution under section 16(1) of the Occupational Health and Safety Act 1983. JUDGMENT [2001] NSWIRComm 97 1 The application before me by the defendant, Develco Project Pty Limited, is that I disqualify myself from the further hearing of this matter on the ground of reasonable apprehension of pre-judgment. I propose to accede to the application, albeit with extreme reluctance and not without some hesitation, and will state as succinctly as I can my reasons for so deciding. 2 The substantive matter before the Court is a prosecution filed on 28 May 1999 by Martin Carmody, as an inspector of the WorkCover Authority of New South Wales, of the defendant for a breach of s 16(1) of the Occupational Health and Safety Act 1983 in that between 16 June 1997 and 15 December 1997 it failed to make arrangements for ensuring safety and absence of risks to health in connection with excavation work carried out adjacent to a free-standing brick wall on a construction site at Kent Road, Mascot; as a result of the said failure, two persons not in the defendant's employment sustained fatal injuries when the wall collapsed onto them on 15 December 1997. 3 The defendant was the developer of the site for the construction of a purpose-built development being an office/factory complex. It engaged Consolidated Constructions Pty Limited as the principal contractor for the construction work who in turn sub-contracted the excavation works to Byrne Civil Engineering Constructions Pty Limited. The defendant pleaded not guilty to the charge and it was scheduled to proceed before me as a defended hearing commencing on 9 October 2000. However, on the matter being called that day, the prosecutor offered no evidence and accepted the appropriate course as being the dismissal of the charge; the defendant then made an application for costs which was opposed by the prosecutor. It is as to the question of costs that the present application for disqualification relates. 4 It is necessary so as to properly understand the basis for the disqualification application to trace how this matter developed. Similar prosecutions were instituted against both Consolidated Constructions and Byrne Civil Engineering Constructions relating to the subject incident at Kent Road, Mascot on 15 December 1997 when the brick wall collapsed. Originally, in all three prosecutions the respective defendants pleaded not guilty and, by agreement of the parties, they were scheduled to proceed as a joint defended hearing to commence on 9 October 2000 for a period of 21 days. As I have said, on 9 October 2000 the prosecutor withdrew the charge against the present defendant. As to Consolidated Constructions, a plea of guilty was entered and the issue of penalty was heard on 10 May 2001 to be continued on 13 June 2001. As to Byrne Civil Engineering Constructions, it continued its plea of not guilty and, after a hearing on 9, 16-19 October 2000, on 9 March 2001 I found the offence proven; on 7 May 2001 I heard submissions on penalty and the decision was reserved. 5 As it happened, on 9 March 2001, after publishing judgment in Byrne Civil Engineering Constructions ([2001] NSWIRComm 33), I heard the costs application by the present defendant and reserved, subject to leave to the parties to file further written submissions within 14 days. The opportunity for those further submissions was sought by counsel for the defendant, Mr A B Gotting, as he said, "given the reasons for judgment handed down this morning in the matter of Byrne Civil Engineering … , particularly the distinction between the immediate cause and the effective cause (of the collapse of the brick wall)". 6 In earlier written submissions by Mr P M Hall QC and Mr Gotting for the defendant, in support of its costs application, the precise basis for such relief was stated as : (i) the existence from the outset of a fundamental flaw in the case brought by the Prosecutor, namely, the non-application of the provisions of s 16 to the defendant and the absence (on Mr Leavy's report) of the requisite causal nexus;
(ii) the existence of the flaw in the case was readily ascertainable and should, in the course of prosecutorial decision-making, have been checked and if necessary cross-checked, both in the public interest and as a matter of fairness to the defendant;
(iii) the attempts that were made on behalf of the defendant to have the Prosecutor revisit and reconsider the prosecution and the grounds upon which it had been brought; and
(iv) the failure by the Prosecutor to identify the matters that led to him not offering any evidence until immediately prior to the hearing. 7 The written submissions, which were amplified by Mr Gotting during the hearing, identified two essential elements to establish the s 16(1) offence and which were said to be absent so as to support a costs order in favour of the defendant on the charge not being continued by the prosecutor: first, that the defendant was not an "employer"; and, second, the causation question which concerned the report by Daniel Joseph Leavy, a senior professional engineer with the WorkCover Authority's construction industry team. It was that second element, having in mind that Mr Leavy's report was relied upon by the prosecutor in Byrne Civil Engineering Constructions, that the potential for pre-judgment arose. 8 In the judgment in Byrne Civil Engineering Constructions (from [13] to [22]), I dealt in detail with Mr Leavy's report, including a supplementary statement made by him, and his oral evidence as to the causes of the collapse of the brick wall. The report covered in that respect the conduct of the defendant, van der Meer Bonser Pty Limited (the design engineer for the project), Consolidated Contractions and Byrne Civil Engineering Constructions. In relation to Mr Leavy's evidence, I concluded (in [22]) : As a general proposition, I found Mr Leavy's evidence to be credible. It was clearly and forcefully presented and in a manner consistent with the supporting technical details referred to by him. Of importance to me, he outlined an objective analysis of the history and condition of the site, the free-standing brick wall's foundations and construction, modifications made to the wall, excavations near the wall, digging at the footings of the wall, work done on the adjacent driveway (including the saw cuts), on-site activities and mechanisms of the failure of walls by reference to the brick wall here concerned; his conclusions were cogent. In particular, his comment that a visit to the site would have raised his concern about the brick wall because, as he said, "one of the fundamental rules of engineering is beware of freestanding structures", I found to be quite telling and meaningful in my consideration of the task in determining the liability of the defendant for the present offence. I accept his evidence. 9 The defendant's submission here made it plain that it challenged Mr Leavy's final report and, hence, and necessarily, the findings made by me in Byrne Civil Engineering Constructions. It is to be noted, however, that the contest arose not in relation to Mr Leavy's initial report but in the supplementary statement made by him on or about 14 September 2000 which apparently qualified the opinion first expressed by him in relation to the cause of the collapse of the brick wall by reference to its then condition as it might involve the defendant but about which there was no issue in Byrne Civil Engineering Constructions. In moving the disqualification application, Mr Hall made clear that insofar as the defendant was concerned the difficulty did not relate to Mr Leavy's first report but to his supplementary statement which, relevantly for the costs application, raised the question whether "the prosecution ever had evidence against the defendant which would have established necessarily to the required standard of causation or not". 10 In the written submission later filed for the defendant on the disqualification aspect, it was stated : 14. The issue as to how, why, in what circumstances and upon what basis Mr Leavy altered his opinion in the way earlier referred to a few weeks prior to the scheduled hearing, against a background when it had been pointed out by the defendant's solicitors that there were problems on causation, raises directly the question which the Commission, it is submitted would need to be satisfied about: was the revision of his opinion made in circumstances where the Commission could be satisfied for itself that the "supplementary statement" was made in fact upon a reliable and sound basis? The Commission would necessarily be concerned and entitled to know whether or not the underlying validity and integrity of his first report was legitimately altered so as to strengthen the case against the defendant in particular.
The novel doctrine for which Livesey's case is responsible is that where a judge determines either an issue or the credibility of a witness in one case and the same issue or the credibility of the same witness arises in a later case, he disqualifies himself from hearing that later case if a hypothetical observer might possibly suspect that he will be biased in embarking on the later case. It is a Spartan doctrine. It has been rendered increasingly so both by constant judicial narrowing of the scope of "necessity" as an exception to the rule, and by the developing law on the attributes of the hypothetical observer. The High Court has decided several times that the knowledge of the individual does not extend to the knowledge that a judge is capable of putting aside evidence heard and findings made in a previous case and deciding the case before him only on the evidence led in that case: Vakauta v Kelly (1989) 167 CLR 568 at 573 and 585, Livesey (at 298), Grassby v The Queen (1989) 168 CLR 1 at 21, Laws v Australian Broadcasting Tribunal (1990) 170 CLR 70 at 87-88, and Re JRL; Ex parte CJL (1986) 161 CLR 342 at 357 and 370. With the greatest respect for the authorities which undoubtedly bind me, I should have thought than any reasonable observer who was acquainted with the idea of a judge at all would assume that a judge had precisely that capability, whatever other virtues or defects he might have.
The upshot is that, judged from this austere and unrealistic standpoint, Cole J should have disqualified himself and the appeal must be upheld. 23 I have to say that I find myself in the same position as Meagher JA identified Cole J found himself. The application that I disqualify myself on the ground of a reasonable apprehension of pre-judgment must, therefore, be upheld. 24 However, I cannot part with this matter without referring to the consequent and regrettable position in which the prosecutor, without any fault on his part, has been placed. As Mr Roser put in his written submissions : 10. No application was made from the 9 October 2000 until the 22 March 2001 although the defendant knew that your Honour would be considering and making factual findings in the cases of Byrnes Civil Engineering Construction Pty Ltd and Consolidated Constructions.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
WorkCover Authority of New South Wales (Inspector Carmody)
Develco Project Pty Ltd
(1992) 26 NSWLR 411
(1983) 151 CLR 288
(1953) 88 CLR 100
(1992) 26 NSWLR 450
(1993) 29 NSWLR 589
(1986) 161 CLR 342
(1991) 173 CLR 78
(1976) 136 CLR 248
(1977) 52 ALJR 155
(1980) 55 ALJR 12
(1969) 122 CLR 546
(1989) 167 CLR 568
(1989) 168 CLR 1
(1990) 170 CLR 70