Wollondilly Shire Council v Foxman Environmental Development Services Pty Ltd
[2011] NSWLEC 35
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2011-03-08
Before
Pepper J, Mr P
Source
Original judgment source is linked above.
Judgment (6 paragraphs)
Introduction 1The background to this judgment, which articulates in greater detail the reasons for refusing the council's application to reopen its case, is contained in Wollondilly Shire Council v Foxman Environmental Development Services Pty Ltd (No 2) [2011] NSWLEC 25. 2This is the council's application, made on the last day of the hearing during closing submissions, to reopen its case to adduce further documentary evidence produced pursuant to a subpoena, issued 25 February 2011, to the Department of Environment, Climate Change and Water ("DECCW"). 3A reason for the late application is because the subpoena issued to DECCW had, pursuant to Wollondilly (No 2), been stood over to 3 March 2011 pending the finalisation of an agreed statement of facts by the parties. While it was anticipated that the agreed statement of facts would be completed by 2 March 2011, the agreement was not tendered until 7 March 2011, the penultimate day of the seven day hearing. 4No explanation was proffered, however, by the council as to why the subpoena to DECCW was not issued until 25 February 2011, that is to say, only one week before the commencement of the hearing.
Application to Set Aside the Subpoena is Refused 5Further complicating matters was the fact that the subpoena had lapsed on 3 March 2011, and therefore, it was necessary for the council to make an application to revive it. That application was granted on 7 March 2011, although when the subpoena was called upon that day by the council, the respondents' oral application to have it set aside referred to in Wollondilly (No 2) was renewed. 6The basis for the application to set the subpoena aside was, first, because it lacked legitimate forensic purpose, and second, because it was too broad, seeking as it did documents from December 2007, whereas the conduct the subject of the proceedings did not, as pleaded, commence until September 2009. 7The Court did not set aside the subpoena. This was because, as submitted by the council, the purpose in obtaining the volumetric surveys the subject of the subpoena was to demonstrate that Botany Building Recyclers Pty Ltd ("BBR") was either in actual, or imminent, breach of its licence to operate its Banksmeadow waste facility by exceeding the amount of material it was licensed to store at the facility. The information would, it was submitted, permit the Court to more readily infer: that BBR had moved the material stored at the waste facility in order to comply with its licence; that the material was transported to the land the subject of these proceedings; and that as a consequence, the material deposited was unwanted and therefore "waste" as defined in the Protection of the Environment Operations Act 1997. 8The Court was further informed by the council that volumetric surveys were not regularly performed by BBR and that in order to capture the volumetric survey closest to the period of time covered by these proceedings, it was necessary to seek all volumetric surveys from the period December 2007 to date. 9On this basis the subpoena neither lacked forensic legitimacy, nor was it impermissibly broad in scope.