13 Clearly it is purported that was done on 9 September 2002.
14 The fitting of a cowl to the top of the shaft is the minor outstanding work required to be done. It is not clear from the present evidence whether some machinery also needs to be installed but, for the reasons that I will explain in a moment, that presently does not have a significant bearing on the Court's determination. Of course, if that still needs to be done, then the operation of a restaurant that relies upon the ventilation shaft in the meantime, pending a final determination, is more serious.
15 A potential problem is identified by reference to the impact of other restaurant developments in the locality. However, if the defendants are correct, the status quo in respect of the location of the work has already been achieved, except for the fitting of the cowl over the exhaust shaft.
16 Again on the basis that is correct, the fitting of the cowl will not mean that rectification, if it is necessary in due course, or to put it another way, the damage that might be suffered, will not be irreparable. The position will not be capable of being recovered. In other words, if the council is ultimately successful, which it may well be because there is a serious question to be tried, the re-location of the shaft will be no more difficult, in my opinion, than it already is. If the council is right, then the defendants have a very serious problem on their hands. It may well be a problem that sounds in damages against some other person, or may even be found to be on their own head.
17 I have taken into account, as I was reminded by Mr Brockwell, that it is only a new business that will be interfered with. The Court realises that the consequential factors associated with an injunction impacting on the establishment and opening of a new business may not be potentially as serious as the circumstances where a business has been carried on for some significant period of time.
18 However, the most telling factor is that the council has known since the construction certificate was approved on 9 September 2002 that this problem existed. It has stood by in the meantime, either by oversight or lack of diligence, while the building was constructed. It is no more obvious now than it was on 9 September 2002 that the location of the shaft onto which this cowl is to be placed was different in whatever respect, material or minor, to that shown on the plans approved by the Court.
19 The other relevant parts of the building, that are otherwise the subject of these proceedings, have been built in accordance with the plans the subject of the construction certificate.
20 Notwithstanding that an undertaking as to damages has been formally offered by the council and the fact that I have identified there is a serious question to be tried, I am not satisfied in the circumstances that interlocutory relief should be granted for the reasons that I have outlined.
21 The work, according to the respondents, is effectively completed. If the respondents elect to risk exposure to an injunction in due course which requires the building to be altered in a material way after business is commenced, then it will be on their own head. However, the lack of diligence on the part of the council and the balance of convenience dictate that no order should, in my opinion, be made at this point. Particularly as the work to be completed is, according to the respondents, now only minor in the sense that only the cowling needs to be placed on the exhaust outlet.
22 Again, if there is in fact a greater quantity of work to be done before a certificate of occupancy can be issued, and if a certifier is persuaded to issue a certificate of occupancy, and the business commences and ultimately the council's case is proved, then the consequence of proceeding with the work and carrying on in the meantime with whatever it is that goes on in this building will be at the respondents' risk.
23 I make the decision to refuse interlocutory relief notwithstanding there is a serious question to be tried and the council has furnished an undertaking as to damages. Although there is some evidence about the detrimental effect caused at other properties, there is no relevant or direct evidence of potential environmental harm arising from the re-location of this particular shaft.
24 In the circumstances where this defendant has been allowed to proceed to this point, relying on a construction certificate that has been in the council's hands since September without intervention until February this year, the balance of convenience dictates that the Court should not make an order at this stage.
25 The Court does not usually come to the assistance of those who have delayed or failed to take action when the opportunity to act has existed from an earlier time. No explanation is given for the delay between 9 September 2002 or thereabouts when the construction certificate was approved and lodged with the council and when the council first took action, albeit perhaps pursuant to an order that was lacking in legal veracity. Even though the council is acting in the public interest, that interest will not, in this case as a matter of convenience, be severely detrimentally affected if the resolution of the dispute is further delayed to the final hearing.
26 In the circumstances, I propose to refuse to grant interlocutory relief. The exhibits may be returned. Any question of costs is reserved until the ultimate outcome of the proceedings has been determined.
27 Does the matter have to go to callover or has it got a running life of its own?