New Ceiling Fan
25 It is undisputed that at the time when the incident occurred there was a 900mm to 1 metre fan located close to the South West corner of the building ie: within the Southern third of the roof. At the time of the incident again there is no dispute that the fan was both in good condition and no more than two years old.
26 Again there is no dispute that a fan of this type is necessary to assist in the proper ventilation of a panel beating workshop where fumes and dust and the like are prevalent. It is also the fact, as the defendants' contend, that the fan itself was not damaged by the impact of the crane upon the roof. Furthermore there is no dispute that the fan has vanished.
27 The defendants' contend that the fan was removed at the time of the dismantling of the Southern section of the roof (which is obvious) and could have been safely stored until it could be re-installed. The defendants' also point to plans prepared by DW Knox & Partners for repairs to the building. It is true, as the defendants' contend, that those plans do not make provision for the fan. Accordingly, the defendants' submit that the failure to re-instate the fan was a deliberate choice for those acting for Waratah in the re-instatement process. The defendants' then go on to contend that the failure of the builders engaged by Waratah and its insurers to preserve and or re-install the fan can not be attributed to the defendants'.
28 I disagree. It was not put to Mr Rimac that the plaintiff company had no need for the fan. It was not suggested to Mr Rimac that he took part in any decision not to include the fan in the restoration of the premises. Additionally, it was not suggested in cross-examination that Mr Rimac, or any body else to do with the plaintiff company, had secreted the fan away somewhere. I find that the inclusion of the fan as part of the restoration of the plaintiff company's premises is appropriate. The defendants' contention, in my view, is an allegation that the loss of the fan is not a direct result of the damage inflicted upon the building by the crane. In this regard I am of the view that it was foreseeable that during the course of reconstruction certain items might be lost as a result of the builders actions. I repeat what I said about Lord Hope's speech in Lagden v O'Connor. Accordingly, I find that the price of the re-installation of a ceiling fan is a proper subject of claim by the plaintiff company. As there is no issue as to the amount it would cost so to do I allow the sum of $9,048.00 under this head.
29 The next item in dispute is the floor alignment rail system. There were no issues that rails of the type laid in the plaintiff company's premises were an essential part of the panel beating shop. They are used to stretch damaged motor cars, and for other purposes. There was no challenge to the evidence of Mr Rimac or Mr Franco in this regard.
30 The two issues raised by the defendants' were:-
(i) that the rails were still useable and
(ii) even if they were damaged they were damaged principally by the operation of bobcats by the builders during reconstruction work.
31 Mr Rimac deposed that the rails were both corroded and out of alignment and needed to be dug up and replaced. The plaintiff company's expert, Mr Bournelis, deposed that there were areas in the rail system where the brackets used to hold motor vehicles being repaired simply did not fit.
32 Both Mr Rimac and Mr Franco deposed that the misalignment of the rails had been undoubtedly caused by being struck by a bobcat used by the builders during restoration works.
33 In relation to the damage to the rails the defendants' relied heavily upon part of Mr Costin's report, which was in evidence. That part of the report reads as follows:-
"We refute the claim that there is significant corrosion or misalignment that the condition of the alignment rails either immediately after the incident or now after the building reinstatement is such that the alignment rails cannot be used for their intended purpose.
We agree that the alignment rails are "bent or misaligned" but there is no evidence of impact damage to the rails or the surrounding concrete that contains the rails to support the claim.
There is evidence that the alignment rails were, in fact, installed in the original concrete in this condition.
There is no evidence that the "specially made brackets" referred to can no longer fit into the rails.
We note that a 1m by 2m section of concrete together with new steel cross rails welded between longitudinal rails appears to be newly constructed, we assume, as part of reinstatement by the Builder.
We see no evidence of the corrosion claimed due to exposure to the elements.
We do agree that builder's debris may be present within the recess between the rails that may affect the rise of the alignment rails. We are of the opinion though that the building debris could be removed to facilitate use of the rails without the need for demolition and reconstruction of the floor slab and the alignment rails."
34 The defendants' contend that Mr Costin's observations recorded above are a complete answer to the plaintiff company's claim in this regard.
35 Again I disagree. Firstly, because Mr Costin's evidence seems to me to be contrary to the damage revealed in the photographic evidence tendered. Second, I found the evidence of Mr Franco to be compelling. I found him to be a witness of truth and a man experienced in the workings of a panel beating shop. Additionally, I accept Mr Rimac's evidence as to what he observed as to the condition of the rails following the accident and restorative works.
36 As far as damage being caused to the rails by the use of bobcats by the builders during restoration, I repeat what I have said earlier in these reasons when dealing with the law as adumbrated by Lord Hope in his speech in Lagden v O'Connor.
37 I thus find that damage had occurred as deposed to by Mr Rimac and that such damage was foreseeable. There being no challenge to the cost of repairs as claimed by the plaintiff company I would award the sum as claimed, namely $46,488.75 under this head.
38 The next item of claim is the concrete slab which constitutes the floor of the plaintiff company's premises. Here there is no dispute between the parties that the floor is damaged and requires restoration.
39 However, the defendants' contend :-
(a) that the condition of the floor, as deposed to by Mr Costin, is consistent with its age, and not consistent with impact damage and, as I understand the submission,
(b) if impact damage, is caused by the operation of equipment by the builders during restoration and is thus not claimable.
40 On the other hand the plaintiff company's expert, Mr Bournelis, deposed that the damage to the surface of the slab was in fact impact damage. The plaintiff's expert does not suggest, I should add, that the damage to the floor was caused by the impact of the crane on the premises.
41 Again, I am of the view that, on balance, the most likely cause of the damage to the slab was in fact the operation of equipment such as bobcats by the builders carrying out the restoration work. In so finding, I am relying particularly upon my acceptance of Mr Rimac's evidence as to the condition of the floor prior to the accident and its condition at present.
42 As I have already indicated, I am of the view that damage caused by building restoration work is properly claimable by the plaintiff company for the reasons I have already given.
43 The defendants' contend that repairs to the slab and repairs to the floor alignment rail system would be carried out at the one time - indeed Mr Bournelis suggested that very thing. While the costing of the repairs to the slab in the sum of $15,812.50 was not challenged by the defendants' they rightly submit that as the repairs to the floor alignment rail system and the slab would be carried out at the one time a deduction of $800.00 for the hiring of a concrete pump for the purposes of performing these works should be deducted from the amount claimed for repairs to the slab. I agree. Accordingly, making that adjustment, I allow the sum of $15,012.50 under this head.
44 The next area of dispute is damage alleged to have been caused by the defendants' action to the mezzanine office / lunch room. Here the dispute revolves around both the questions of causation and the amount of damage which actually occurred to this area.
45 Mr Rimac deposed that in the week following the incident the office resembled a waterfall. As I have already noted, during that week more than 20mm of rain were recorded by the weather bureau. Mr Rimac did however concede in cross-examination that a box gutter in the area of the roof above the office had been replaced shortly before the subject incident.
46 The defendants' contention, as supported by Mr Costin, is that the roof damage occasioned by the impact of the crane on the building was so remote in terms of distance from the office area that the entry of water into the office area could not have been occasioned by the incident. In my view, this submission must succeed. In this instance I do not find Mr Bournelis' evidence as to how water entered the office area to be persuasive - particularly in view of the distance between the roof damage and the office area. Additionally, the defendants' contention that the recently renewed box gutter could have been the cause of the accident adds weight to the submission that the damage occasioned to the roof of the building by the crane could not have caused water to enter an area of the building where the roof still remained intact. Not only that, I accept Mr Costin's evidence that the damage which had occurred to the office could also have been related to a past water ingress problem. I find this evidence reinforced by Mr Rimac's concession that it was necessary prior to the incident to have repairs carried out to the box gutter.
47 In short, I am of the view that the plaintiff company has not satisfied me on a balance of probabilities that any damage to the mezzanine office and the staff lunch room area by virtue of water access was related in any way to the damage occasioned to the building by the impact of the crane upon it. Accordingly, I disallow this head of claim.
48 Also, the plaintiff company claims the cost of the replacement of workshop racks and shelving. That shelving, as Messrs Franco and Rimac deposed, was on the Western wall of the building. The defendants' contend that I would not be satisfied that the shelving in fact existed. In support of this contention the defendants' point to the fact there is no photographic evidence that the shelving existed.
49 As I have already found, I am of the view that Messrs Rimac and Franco are witnesses of truth. Accordingly, despite the absence of photographic evidence to support their evidence, I am of the view that I should accept their evidence that the shelving was in place as they have stated.
50 There is no issue that the shelving is no longer there. Again, there is no suggestion made that Mr Rimac has secreted the shelving away. To me the most probable explanation of the disappearance of the shelving is that it was removed by the builders during the course of the restorative works which were carried out. Once more, I refer to the fact that such removal by a builder during restorative works is a matter which is foreseeable as a consequence of the damage caused by the collapse of the crane onto the subject building. This being so, I am of the view that the defendants' contention must in this case fail and that I should allow the unchallenged costs of the replacement of the shelving in the sum of $29,348.00.
51 The next item of the plaintiff company's claim involves damage to airlines and a compressor. Here the plaintiff company relies upon the evidence of Mr Rimac that water has entered both the steel and rubber airlines. As far as the steel airlines are concerned they were rusted and as far as the rubber airlines are concerned the presence of water within the lines could contaminate paint in such a way as to prevent a proper spray-painting job being affected. The defendants' point to the fact that Mr Bournelis deposed that the airlines that contain the spray paint for vehicles were not cleaned, thus causing the paint within them to congeal and clog the lines.
52 Despite this contradiction, I am of the view that I should accept Mr Rimac's evidence as to the rusting of the steel airlines and the contamination of the rubber airlines by water. Water which had entered those lines because of the damage to the roof caused by the collapse of the crane onto it.
53 Mr Rimac also deposed that the compressor used to operate the airlines was unuseable because it had become rusted, again because of water entering it. The defendants' contend that there is no evidence of when it was that the water entered the compressor.
54 In my view there can be no doubt that water entered the compressor during the period when rain fell through the open roof during the time when the plaintiff company was not allowed to be on the premises. On the balance of probabilities, I find that that is when the damage occurred to the compressor and accordingly I would allow the claim in full. There being no issue that the cost of the replacement for the airlines and compressor is $7,500.00 I would allow the plaintiff company's claim under this head.
55 The next head of damage claimed by the plaintiff company is the reconnection of the power supply and the alarm system.
56 Essentially, the plaintiff company's claim is that during the course of the restoration works the builders removed the electrical cabling and the alarm system. On the plaintiff company's case this was a necessary part of the works being carried out by the builders for restoration. It is no part of the plaintiff company's claim that this removal of the cabling and alarm system was the direct result of damage occasioned to the building by the collapse of the crane. The fact that cabling was removed by the builders during restoration works is hardly a surprising matter. Accordingly, I am of the view that this removal was entirely foreseeable and that the plaintiff company's claim succeeds under this head. I would thus allow the sum of $47,564.00, which was the unchallenged amount costed in the report tendered by the plaintiff company in relation to this matter.
57 Finally, under the head of physical damage, I turn to the plaintiff company's claim for damage and missing chattels. This part of the plaintiff company's claim results from a number of items of personal property being removed from the building and placed in a pile outside it following the incident. These items of personal property principally involved motor vehicle parts such as bumpers, bonnets and gearboxes. Additionally, there were many other motor vehicle parts together with paint and tools. It was Mr Rimac's evidence that these items were all damaged and had been removed from the building for inspection by an insurance assessor. Once the materials were placed in a pile Ms Gibbs, who was Mr Rimac's secretary, wrote down the items identified to her by Mr Rimac. She deposed :-
"When we wrote them down they were in the front of the workshop area, like where we parked all the cars, but they had been moved from out from inside the workshop, they weren't always scattered out there, they were on the premises, but we had to try to bring them to the front and keep them out of the way of the building collapsing."
Mr Rimac valued the damaged items in the sum of $62,902.00, excluding GST. Of that sum Mr Rimac attributed some $28,835.00 worth of goods as being owned by him personally. Accordingly, senior counsel for the plaintiff excluded that sum from the claim, making the claim $34,067.00.
58 The defendants' contended that Mr Rimac failed to identify which of the damaged parts were his personal property as against the property of the company. However, he did depose that the parts as itemised in the invoice prepared by Ms Gibbs and himself, which became exhibit G in the proceedings, were the items which were placed outside and had been itemised and valued. The fact that no specific identification was made of the $28,835.00 worth of goods belonging to Mr Rimac personally can not be used to defeat the claim. In short, as far as this contention is concerned I accept Mr Rimac's evidence that, of the goods itemised in exhibit G, $28, 835.00 worth of the goods were his. Accordingly, ex facie, the plaintiff company is entitled to have the sum of $34,067.00 allowed under this head of claim.
59 However, the defendants' contention does not end there. Once more, the defendants' contend that water damage to mechanical components such as gearboxes was caused by the failure of the builders to take adequate steps to protect what was inside. Again, I am of the view that it was foreseeable that, in the course of building operations, builders would not take care of mechanical parts which, of course, played no part in the building operations which they were carrying out. Accordingly, such damage in my view is foreseeable and I would not accept the defendants' contention in that regard.
60 The defendants' also contend that there was no evidence of damage to paint, which is part of the claim made under this head. Again, it was Mr Rimac's evidence that all items contained in exhibit G had been damaged. I see no reason why I should not accept his evidence in this regard. Accordingly, I am of the view that I should allow the sum of $34,067.00 as claimed by the plaintiff company under this head.
61 Finally I turn to the plaintiff company's claim for economic loss. This claim has two components, first, the plaintiff company's claim for loss of profits and second, the plaintiff company's claim for loss of goodwill, ie: loss of value of the business.
62 In relation to past loss of profits the plaintiff company's claim is for a sum of $778,889.00 plus interest. In respect of loss of goodwill the plaintiff company claims a sum of $444,185.00 plus interest. This claim was based upon calculations made by a chartered accountant, Mr Arnold Shields.
63 On the other hand the defendants' contend, relying upon the expert evidence of another chartered accountant, Mr Dorfan, that the plaintiff company's past loss of profits is $438,019.00 and that the allowance made for loss of goodwill is $202,843.00.
64 In determining future economic loss I believe that Palmer J accurately stated the law in Benward Pty Ltd & Ors v Metal Deck Roofing Pty Ltd & Ors [2001] NSWSC1053 where he said :-
"No exactness can be achieved in the task of awarding compensation for future economic loss - to a considerable degree, it depends upon impression and a sense of balance. One tries to avoid a munificence inspired by sympathy for a plaintiff's misfortune without succumbing, on the other hand, to a niggardliness born of the gloomy conviction that all of life's bright hopes are bound to end in disappointment. One bears in mind that although many commercial enterprises which started with vision and energy fail, many others which are, in addition, well managed, competitive and adequately supported by working capital have achieved great success. Track record, quality of management, competitiveness and the financial ability of the business to ride out the vicissitudes of economic life are all indicators assisting in the assessment of business prospects when future economic loss is claimed."
65 Why then is there such a vast difference between the calculations made by the experts called by the parties? I note that in fact there is some measure of agreement upon the manner in which these calculations should be made. In a joint statement of the experts dated 14 July 2005 both Messrs Shields and Dorfan agree on the methodology used to assess the loss of profits claim. Second, they agree on the manner in which the gross profit ratio is to be calculated. They also agree on the level of all overhead expenses with the exception of what they believe is an appropriate calculation of the salary to be paid to Mr Rimac. Furthermore, they also agree that the calculation of loss of goodwill crystallises in the date when it is appropriate to bring an end to the loss of profits claimed. Indeed, they also agree that the value capitalising the future maintainable earnings of a business is at a rate of return commensurate with the risk involved in its operation.
66 They differ on three means of calculation in relation to the claim for loss of profits and on the calculation to be applied in assessing the loss of goodwill.
67 The three points of difference in relation to the plaintiff company's claim for loss of profits are as follows :-
(1) the level of the plaintiff company's sales between the years 2002-2004;
(2) the allowance to be made for the salary paid to Mr Rimac as a business expense and
(3) the duration of the plaintiff company's claim for loss of profits.
68 As to the issue relating to the level of the plaintiff company's sales in the years 2002-2004 Mr Shields calculates that they would have been $1,165,695.00 whereas Mr Dorfan arrives at a figure of $962,000.00. As to Mr Rimac's salary Mr Shields allows the sum of $59,142.00 per annum whereas Mr Dorfan uses a figure of $85,800.00. Mr Shields, in determining his figure, uses a commercial calculation whereas Mr Dorfan uses the actual wages paid to Mr Rimac at the time of the subject incident. I should add that the actual salary paid to Mr Rimac was half the amount used by Mr Dorfan in his calculation but the fact was that the same amount was paid to his wife, who did not do any work for the company. What Mr Dorfan has done is to treat the payment of a salary to Mr Rimac and his wife as an income splitting device and has merely put them both together to come up with Mr Rimac's salary. I should immediately state that I believe Mr Dorfan's approach in calculating Mr Rimac's salary on this basis in the past is correct, in that it seems to me to be obvious that the payment of a salary to Mr Rimac and his wife of the same amount is plainly an income splitting device and Mr Rimac's actual salary must be taken as the combined salary of his wife and himself. Whether or not this is an appropriate means of bringing Mr Rimac's salary into account in determining loss of profits is a matter I shall deal with later in these reasons.
69 Finally, the two experts differ as to the duration of the plaintiff company's claim for loss of profits. Mr Shields makes his calculations up to 30 June 2004 whereas Mr Dorfan terminates the losses as of 30 June 2003.
70 I shall deal with these differences in turn.