7 I think it is unrealistic to view those offers in isolation. To begin with, the Walker defendants were represented throughout the proceedings by the one set of legal representatives. Further, it is admitted on behalf of those defendants that the second, third and fifth defendants enjoyed the benefit of an indemnity by WCL in relation to their liability, if any, to CCG in the proceedings.
8 Those offers followed by a special sitting of the reference, attended by the principal officers of CCG and WCL, held for the purpose of outlining to them, in some detail, the nature and relationship of each of the several disputes and the quantum in issue. It was an informal exercise in preparing the ground for settlement of what was, undoubtedly, an extraordinarily complex set of issues, both of fact and of law.
9 The referee's outline was a careful and useful description of the disputes, without expressing any views as to the likely outcome of any of them.
10 For example, in relation to the quantum meruit claim the referee expressed the matter thus:
"One way in which the plaintiff puts the case is to say, "We have a claim under the contract. The contract sum is $83m." We know that's right. They say, "We want variations to which we're entitled of another $7m, making a total of $90m. We have been paid $75m. Therefore, the plaintiff says we want $15m."
In addition, they say, "We want interest" and that would be in the order, I imagine, of $2m to $3m by now. They have fairly unspecified acceleration costs and time related costs.
In the order of magnitude, it is a claim for some $18m-odd plus the cost of the litigation. Those costs must now be several million dollars.
The only uncertainty on that claim, assuming it is legally sound, which it may or may not be, I haven't heard argument about it, the only uncertainty in those figures is the question of how much the variations are.
…
The variations resolve into three segments: the first I shall call general variations, which are variations increasing or decreasing the contract price. We've had a team of people working on those. They are agreed. I think I'll be told the figure today or tomorrow, but it is in the order of $1m or slightly more in favour of the plaintiff.
The second aspect of variations are what I've called the electrical variations, and the amount in dispute there is in the order of $1m, perhaps a little more. That has not been resolved. It is in the process of being resolved. I hope it will be resolved next week. If it is not, I will endeavour to resolve it before Christmas, or at least hear all the evidence and then go away and write about all that.
The third variation is the so-called Hoyts variation, the change from the eight complex to the 12 complex of theatres. Both sides have engaged quality surveyors. The difference between the quantity surveyors is the plaintiff's quantity surveyor says the figure is about $3.4m, Walker's quantity surveyor says the figure is about $500,00. So there is about a $3m swing in that.
In relation to that, we all know that at some point of time a deal was done in relation to the Hoyts variation at $2.225m, but that was to include an acceleration claim of some $400,000 and what are called the electrical variations. That came unstuck because the underlying assumption of agreement about the electrical variations proved not to be so.
In the order of things, there is a $1m general variations, $1m electrical variations, and that is an uncertain figure, and there's somewhere between a half and $3.5m. So we're talking in the order of somewhere between $1m and $5 million for variations is likely to be the outcome.
That, you might think, resolved the first equation that I put to you. But then the defendant says, "You're not entitled to that 15 or adjusted for variations for a number of reasons."
Principally, they are two. The first is that the defendant says the works were both incomplete and defective and it particularises claims for rectification of the works. The figures that have been given to me show a claim for rectification of defective works of about $9m, and a claim for responding to retailer's claims and damages due to the leakages that occurred in the building of another $3m; a total of some $12m.
Secondly, because they say, "You're not entitled to that sum because we are entitled to liquidated damages." Practical completion was certified, I think on 9 October 1998 and the claim is that the developer is entitled to liquidated damages at about $54,000 a day from mid-March to mid-October, a figure in the order of $9m.
They say $9m rectification costs, $9m liquidated damages, $3m tenancy claims, a round figure of $21m.
If those claims all succeeded by way of defence or set-off or cross-claim, however they are pleaded, you would then have rather than the plaintiff succeeding with a claim in the order of $18m, the defendant succeeding with a claim in the order of $3m, and whoever succeeds will be likely to have an order for costs in their favour.
You have a swing of about $21m. That's the area at which both parties are at risk."
(T 2299:6- T 2299:21, T 2299:29- T 2300:57)