THE PROPOSED AMENDMENT - PARA 22A
64 Amongst other amendments to its statement of claim, Vassallo seeks to insert para 22A as follows:
22A In the alternative to the allegations of paragraphs 21 and 22 hereof :-
(a) On 29 March 2012 the applicant and the respondent reached consensus, within the meaning of Clause 6 of AS-4000 1997, as to all terms of the formal contract they anticipated executing.
Particulars
(i) email and attachment from Kinneally on behalf of the respondent to Victor Vassallo on behalf of the applicant dated 29 March 2012 at 6:53pm; and
(ii) email from Victor Vassallo on behalf of the Applicant to Kinneally on behalf of the respondent dated 29 March 2012 at 9:46pm.
(b) By email dated 3 April 2012 at 7:37am Ide on behalf of the respondent advised Victor Vassallo on behalf of the applicant he was trying to finalise contract documents today for issuing.
(c) By email dated 3 April 2012 at 10:44am from Ide on behalf of the respondent to Victor Vassallo on behalf of the applicant, the respondent requested the applicant to amend an attached Schedule of Rates for inclusion in the contract.
(d) Agreeing to the request referred to in subparagraph (c) hereof the applicant sent to Ide on behalf of the respondent a further updated tender costing dated 3 April 2012 ("the Third Updated Tender Costing").
(e) By an email dated 3 April 2012 at 5:15pm Ide on behalf of the respondent advised Breadley and Victor Vassallo on behalf of the applicant inter alia:-
(i) "see attached contract";
(ii) "Three copies of the contract and one copy of drawings have been sent to your office"; and
(iii) ''I look forward to progressing the signing of contract and starting construction".
(f) On 3 April 2012 the applicant received an initial letter dated 3 April 2012 wherein Westera by one of its directors, further and alternatively, employees, and further and alternatively, agents, one Bret Arthur, on behalf of the respondent unconditionally advised of the respondent's acceptance of the applicant's third updated tender ("the initial letter of acceptance of the third updated tender").
(g) On 4 April 2012 Damian Vassallo on behalf of the applicant by telephone requested Ide on behalf of the respondent to revise the initial letter of acceptance of the third updated tender.
(h) On 5 April 2012 the applicant received a final and revised letter dated 3 April 2012 wherein Ide on behalf of the respondent unconditionally advised of the respondent's acceptance of the applicant's third updated tender ("the final letter of acceptance of the third updated tender'').
(i) The final letter of acceptance of the third updated tender was "acceptance of tender" within the meaning of clause 6 of the general conditions of contract of AS4000/1997 and further and alternatively clause 6 of the general conditions of contract G09/241A.
(j) In the premises of paragraphs 22A(a) to (i) the applicant and the respondent entered into a contract whereby the applicant agreed to undertake the work defined by the applicant's tender as amended by the first updated tender costing, the second updated tender costing and the third updated tender costing in consideration of the respondent making payments to the applicant for that work ("the alternative Agreement" or " the alternative Contract" and " the alternative Contact Works") .
(k) The express terms of the alternative Contract are to be found in the documents referred to in paragraph 22A(e) (i) and (ii) hereof or alternatively in those documents save for:
(i) the last sentence in the second paragraph in Clause 3.0 of Section One "Form of Formal Instrument of Agreement"; and
(ii) special condition 8 therein and the words in Part B being "Clause 2.5. See attached Special Conditions" therein, each of which was incorrectly included in those documents contrary to the consensus referred to in paragraph 22A(a) hereof.
65 The proposed alternative claim arises substantially out of events after 9 December 2011. I have already set out the correspondence which immediately followed the alleged acceptance. Following that correspondence, on 10 March 2012, Mr Kinneally sent an email to Mr Ide, with copies to Messrs Grimm (the other director of Andergrove), Vassallo and Breadley. The email clearly demonstrates that the terms of any agreement were still being negotiated. It seems that the parties had been proceeding on the basis that Andergrove's financial arrangements were to be in place prior to the execution of a formal and unconditional contract. However, on or before 10 March 2012, Mr Vassallo suggested that they instead enter into a contract which was conditional upon finance being obtained. Mr Kinneally agreed to this proposal. At the end of Mr Kinneally's email he notes:
Next action:
a) Bob to review and send to you works program and resolve with you;
b) RK to review contract and advise if identifies possible additional provisions;
c) Sign Contract subject to finance becoming unconditional.
66 On 14 March 2012 Mr Kinneally sent an email to Mr Damian Vassallo, proposing arrangements for communications between the parties, in negotiating the contract and thereafter. He proposed that "[f]or communications with entering into the contract", he would deal with Mr Vassallo (not Mr Damian Vassallo) and Mr Breadley, copying correspondence to Mr Ide and Mr Damian Vassallo. He distinguished between that correspondence and, "all communications after that in the administration of the contract", which correspondence was to be between Mr Ide and Mr Damian Vassallo. Mr Vassallo (not Mr Damian Vassallo) replied as follows:
I concur with your comments.
The chain of command from our end will be all contractual matters are to go through Damian Vassallo … Gary Brittian … and Sam …
…
Once a contract has been entered into than no more correspondence will be sent to you directly.
…
67 On 16 March 2012, under cover of an email to Mr Vassallo, Mr Kinneally forwarded a draft "side agreement" with "CBA", presumably concerning finance. On 17 March 2011 Mr Kinneally forwarded Annexure Part B to the standard conditions, proposing its inclusion in the contract. He also forwarded proposed special conditions, one of which was the condition as to finance.
68 On 19 March 2011 Mr Vassallo advised Mr Kinneally that he was seeking legal advice concerning the side agreement. In another email dated 19 March 2011 Mr Vassallo advised that:
We are currently looking at the special conditions you require and will let you know of any changes.
The changes you require to the AS4000 contract have been forwarded to our solicitor and I will get back to you once I have his comments.
69 On 19 March Mr Vassallo sent an email to Mr Carey, his solicitor, as follows:
See attached Emails from Ross Kinneally requesting the following to form part of the contract for a Lakes Subdivision in Mackay.
The attachments are as follows:
1. Changes requested to the AS 4000 standard contract (this was not provided at tender and has only now been forwarded to us).
2. Additional special conditions to the contract.
3. CBA's request to include a Builders Side Deed as part of the contract.
4. Draft contract negotiated and agreed previously between the Consulting Engineers and ourselves.
Look at the changes to amend AS 4000 (we believe that our first position should be not to accept any changes and see how we go).
We will look at the special conditions and let you know what we are prepared to agree to and suggest any changes (I will forward this to you separately for your comments).
Review the Builders side Deed and advise if we should accept it as is or if any changes should be made. We have already agreed to the Draft Contract and are happy to proceed with it.
Please review the documents and get back to me ASAP as Ross and we are fairly keen to finalist this contract.
70 On 22 March 2012 Mr Vassallo sent an email to Mr Kinneally. It contained comments concerning the proposed amendments, special conditions and the side agreement. He refused to agree to the inclusion of Annexure Part B. He sought to amend a proposed clause providing for a "fixed cost lump sum" contract which may have excluded price variations attributable to, "incorrect quantities in the bill of quantities". Mr Vassallo also rejected proposed special condition 4 which provided that there be no variations to the contract sum unless the cost was included in the progress claim for the relevant period. Proposed special condition 6 provided for the possible extension of the works. It provided that any such work would be paid at the rates set out in the bill of quantities. Mr Vassallo said that whilst Vassallo "generally" accepted the proposal, he did not believe that it should be part of the contract. He also requested amendments to the proposed side deed. Although Mr Vassallo also accepted the proposed condition as to finance, on 23 March he sent an email to Mr Kinneally, seeking to limit the time period during which the contract would remain conditional.
71 Mr Vassallo's proposal that the parties enter into a conditional contract is of some interest. It is difficult to reconcile his claim that he already had an enforceable contract with his suggestion that the parties enter into a conditional contract. It would be very curious if he were suggesting that he wanted a conditional contract in place of an unconditional contract. However he may have understood that any agreement made on 9 December 2011, by virtue of the attached letter, was conditional upon finance. Nonetheless it is also difficult to see why Mr Vassallo would have raised the question of another conditional contract if he believed that he already had such a contract. His immediate problem, as he would have seen it, was the delay in obtaining finance. A request for a time limit on the condition may have been understandable, yet that was not his initial request. His initial request was for a conditional contract. That request was consistent with a belief that there was no binding contract and a desire to obtain as much certainty as he could concerning Andergrove's commitment to the proposed contract. Perhaps one should not put much weight on this matter for present purposes, but it may go to Vassallo's prospect of success at trial.
72 On 25 March 2012 Mr Kinneally sent an email to Mr Vassallo in which he accepted Mr Vassallo's rejection of Part B to the general conditions. He also accepted proposed amendments to the side agreement and the amendment to the finance condition. Mr Kinneally identified two matters as still in issue between the parties. Both seem to have involved the drafting of further provisions for inclusion in the contract. One matter concerned Mr Kinneally's proposal that claims for variations be included in the progress claim for the relevant period. The other matter related to a clause which would have provided for the extension of the works being undertaken, and the rates at which such additional work was to be performed.
73 On 27 March 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
Attached is amended Special Conditions for your approval. I think we got to the stage that as a matter of practice variations will be included in progress claims as they go so the clause is OK. I certainly however don't want this to become a basis of unreasonable variation claims. We believe we have covered most items.
Once the design of tower footing and stays are done it might be something you give a separate price for and do and similarly for ski lodge piers. We can deal with that separately down the track.
Let me know if you have any issues with the attached amended special conditions.
74 On 28 March Mr Vassallo sent an email to Mr Kinneally saying:
Please find attached a few minor changes to the special conditions. Please note, we agree as a matter of practice, claiming variations would generally be done within the month that the work is undertaken. As discussed however, we do not believe that clause 4 is necessary as the Principle is adequately covered by AS4000 and this clause is to be deleted. As such, all variations should be identified by the Superintended under AS4000, even if they are not claimed within the month the works are undertaken. Please call me if you need to discuss further.
75 On 29 March Mr Kinneally sent an email to Mr Vassallo saying:
We accept below position. Attached are amended conditions to which we have made two minor changes as raised by Sam as follows;
1. Clause 4(b) - Contractor not being responsible for early works area but is still responsible for own employees, subbies and supplies in early works area and defects in WUC; and
2. Clause 8 last sentence as reference to "other contractors" means other contractors engaged by Principal but Contractor is still responsible for its own sub-contractors.
The reference to the "below position" may have been to Mr Vassallo's email under reply. Mr Kinneally's email was copied to Mr Ide. The last paragraph stated:
Sam [Mr Ide] could you please assemble contract using attached Special Conditions and get to Victor for signing by Vassallo Constructions Pty Ltd. Chris is back Easter Weekend and can sign for us or we can both do on 16th.
76 On Thursday 29 March 2012 Mr Vassallo sent an email to Mr Kinneally as follows:
Thanks for your email.
I wish to confirm that we are in full agreement and as stated below once the contract documentation has been sent to us I will sign and return for you and Chris to countersign.
We look forward to commencing the works once all financial documentation has been executed and the site has dried out enough.
Damian will be contacting Sam to see if we can do some temporary drainage works to clear some of the surface water to allow the site to dry out quicker (if we don't do this it could be months before we can enter the site).
We look forward to commencing the project.
77 Vassallo submits that this email constituted an acceptance of an offer, creating a concluded agreement. I shall return to this matter. It would be odd, however if, having spent so much time in negotiating the terms of a written agreement, and with its execution imminent, the parties should, for the first time, choose to be legally bound prior to such execution.
78 On 30 March 2012 Mr Ide sent an email to Mr Vassallo as follows:
Drainage works sounds sensible. Can you or Damian please provide scope of proposed works and cost? I know it is included in WUC however we just need to monitor costs while the contract is not signed and finance pending.
Let me know if you have any questions.
79 Mr Ide clearly indicated that there was, as yet, no contract. Mr Vassallo did not contradict him. On Monday 2 April 2012 Mr Vassallo sent an email to Mr Ide as follows:
I am taking two weeks leave starting Good Friday and returning back to work on 23/04/12. It would be good if we could execute the contract documents this week if possible.
80 On 3 April 2012 Mr Ide sent an email to Mr Vassallo as follows:
I am trying to finalise contract documents today for issuing.
81 On that day, Mr Ide also forwarded a schedule of quantities, asking Mr Vassallo to make amendments to it. Later that day, Mr Breadley returned the amended document. In a later email to Messrs Breadley and Vassallo on that day Mr Ide said:
Contract documents are on the way to your office. Items to note:
1. Liquidated damages has been left blank. Note that under AS4000 if this is left blank it does not preclude the Principal from claiming liquidated damages however the cost must be verified.
2. Special conditions included in annexure B as discussed between Victor and Ross. I added a condition 8 which is a copy and past (from sentence in form of contract.
3. See attached contract. Three copies of contract and 1 copy of drawings has been sent to your office. Three copies are to allow 1 for you, 1 for Ross and 1 for us. If you have any questions regarding the contract please contact me.
I look forward to progressing the signing of contract and starting construction. We have received approval for construction drawings from Council and just need to lodge the compliance certificate (and associated fees) 7 days prior to a proposed pre-start meeting. See attachment fyi.
82 Some importance may attach to a letter dated 3 April 2012 (the "tender acceptance letter") from Mr Arthur on behalf of Westera Partners Pty Ltd, to Vassallo. It was as follows:
On behalf of our client, Andergrove Lakes Pty Ltd, we are pleased to advise acceptance of your tender for the Lump Sum of $6,066,455 (G.S.T. excluded).
The Construction Period shall not exceed 30 weeks. The works shall commence as outlined in Clause 2 of the Special Conditions to the Contract
Should you have any queries please contact Sam Ide at our Brisbane office.
83 Mr Vassallo was unhappy with the sentence dealing with the construction period and proposed that it be amended to provide that:
The construction period shall be 30 weeks in accordance with the conditions of contract AS4000.
He considered that this amendment would provide scope for extensions in the case of bad weather. On 5 April 2012 Vassallo received the amended tender acceptance letter, still dated 3 April 2012. At first blush, that letter (in its original form and as amended) may seem to have contractual effect. However, in an email dated 30 April 2012 Mr Kinneally asserted to Mr Vassallo that Mr Ide had sent it to Vassallo with the intention that it be included in the contract. Mr Vassallo did not contradict this assertion. Indeed, in Vassallo's supplementary outline at para 71, it submits that the amended tender acceptance letter was, "but a machinery step facilitating the execution of a formal instrument of agreement in a given time frame." Vassallo goes on to submit that alternatively, it may have constituted the acceptance of an offer, namely Vassallo's final tender. I shall return to these matters. A draft letter, in similar, but not identical terms had been amongst the proposed contract documents forming part of the alleged acceptance.
84 On 5 April 2012 Mr Vassallo signed the contract on behalf of Vassallo, but only after amending it further. Concerning these amendments he said at para 110 of his affidavit:
110. In relation to "VGV47", I make the following comments:
110.1 I amended the Second Special Conditions by:
(a) removing paragraph 8 which stated "Where an item is shown on the engineering drawings and is not listed in the Bill of Quantities, the item shall be deemed to be included in the lump sum" ("the BOQ Amendment"); and
(b) inserting a new paragraph that said " Total liquidated damages shall be limited to 10% of the contract amount" ("the Liquidated Damages Amendment").
110.2 I made the Liquidated Damages Amendment on the basis that my trust in Kinneally had broken down and I was concerned that he was trying to set me up to broaden the potential damages payable by Vassallo Constructions. In particular I was concerned that in the circumstances where we did not deliver and he had some contracts for houses that fell through, that he'd try to sue Vassallo Constructions for all of the resulting losses.
110.3 I believe that capping the liquidated damages at 10% was not unreasonable because $600,000 was a significant penalty if we failed to deliver.
110.4 I made the BOQ Amendment because, in my view, its effect would be that we had to rely that their bill of quantities being correct and if it wasn't we would then, effectively, wear the consequences of that as it would be deemed to be part of the lump sum.
110.5 I thought by signing the contract with those changes sending it off to Kinneally it may help punch through the parties' differences and allow the parties to finalise their positions.
85 On 10 April 2012 Mr Damian Vassallo sent an email to Mr Ide and Mr Kinneally as follows:
I have sent the three signed copies of the Andergrove Lakes contract via courier this morning. Please note that we have made a few minor changes.
… Where an item is shown on the engineering drawings and is not listed in the Bill of Quantities, the item shall be deemed to be included in the Lump Sum Price.
As previously discussed, we do not accept this clause and as such, have removed it.
… Part B of General Conditions of Contract - Clause 2.5 see attached "Special Conditions". - Appears to have been left in by mistake so has been removed.
… Item 8 of Special Conditions - Where an item is shown on the engineering drawings and is not listed in the Bill of Quantities, the item shall be deemed to be included in the Lump Sum Price.
As previously discussed, we do not accept this clause and as such, have removed it.
… Special condition Item 8 added - Total liquidated damages shall be limited to 10% of the contract amount. Considered necessary as no value has been included for liquidated damages.
Also, could you please provide an estimate of when possession of site is likely to occur so that we can begin resourcing this project.
We look forward to starting this project and should you wish to contact me, please feel free to do so.
86 These issues seem to have related to matters identified by Mr Ide in his third email dated 3 April 2012. On 10 April 2012 Mr Vassallo sent an email to Mr Damian Vassallo (with copies to Mr Ide and Mr Kinneally) saying:
I should also add that I included a liquidated damages rate of $1,000 per day. Although we expect to complete the project within the agreed timeframes, it was difficult for me to accept the risk of an open ended liquidated damages liability rate in the unlikely event that this was to apply.
Damian was not aware of this addition as I made it prior to leaving on holidays.
I hope that you understand us adding this in and please feel free to contact Damian should you have any concerns and he will pass them onto me.
87 On 11 April 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
Hi Victor,
I gather you are on leave to. Given we are in contract entry stage still it is appropriate that I communicate directly with you on the below Issues.
I don't have in front of me documents Sam sent to you for signing so my following comments are based on what appears below and recollection.
In principle if the change is a correction to something we agreed that that is fine. e.g point 2 below. You have been quite particular in recent emails to call a closure to changes to the contract which I accept and in any event it will mean going back to the bank to have your contract re-approved.
- Point 1 deletion is anew request. It has been in contract since start. It is important because without that paragraph it may continually come down to definitional issues in every single item set out in the Bill of Quantities. i.e. the contractor claims every item as being the absolute minimum for that item. I haven't Bill of Quantities in front of me but is an item was "100 mm conduit rate $X/m" the principal has the expectation that rate includes everything to supply, trench, sand, backfill, compact, etc. If the rate is not take to include the other work the contractor can claim the rate as just supply of 100mm conduit and claim trenching, sanding, backfilling an compaction as variations.
While we understand the risk we are taking if quantities are incorrect, deleting this clause opens up an entirely new issue which we are unable to accept. You have considerable experience In this type of work and have had all drawings for 5 months or so and complete access to Sam for clarification. Could I recommend that you review the drawings again and satisfy yourselves based on your experience if anything is not covered by your rates. We are prepared to accept the risk of quantities being inaccurate.
- Point 2 as I accept if a mistake as should be corrected subject to review on my return.
- Point 3 same as point 1.
- Point 4 is new as a limit plus in your further email suggestion [liquidated damages] of $1,000 per day is new. I am prepared to accept the limit (subject to confirmation from Chris) but not $1,000 stipulation. I haven't calculated what real [liquidated damages] will be and most contracts just leave blank and it becomes a matter of proof later on so we are not wasting our time unnecessarily now. We are not expecting any delays and the contract has the usual provisions fairly protecting contractor and principal when it comes to extensions.
We gave the tenants notice at the end of last month and my recollections is they need to be out by about 23rd of this month. CBA requested an updated valuation because of the size of the project. Herron Todd White expect to be come third week of April. I expect we can give you the letter from CBA as all finance conditions are satisfied about first of May.
Our preference is to work with you on this project. Yours was not the cheapest tender. If you are having second thoughts for whatever reason we would not hold it against you but would like to know urgently.
88 Mr Vassallo replied on 11 April 2012 as follows:
Hi Ross,
I will begin be assuring you that we are not having any second thoughts and are in fact looking forward to constructing this high profile project, we simply want the contract to be fair for both us, us as the Contractor, and you as the Principle.
Please find below a response to your comments:
Points 1 & 3 - Ross, both these items actually appeared to us as a surprise as we did not notice this change in the Form of Agreement until the finalised documents had been sent. On further review however we do acknowledge the this clause had been added into the second draft, however our concentration was on the items specifically referred to in the associated email and must have been overlooked.
As you are aware, all our discussions have centred around us wanting to undertake the works under AS4000 and the clauses referred to are a large deviation from the intent of AS4000.
After reviewing your comments, we do however understand your concerns. We have also done some checks on the Bill of Quantities and are reasonably confident that there should not be any surprises however we do not wish to accept the risk that something may have been overlooked in scheduling this project. We are however keen to negotiate a clause that better suits both parties. Please find below a clause which is based on another contract which we believe addresses both parties concerns.
Minor omissions in the description of items in the Bill of Quantities but which are necessary for the satisfactory completion and performance of the works under the relevant scheduled items shall be supplied and executed by the Contractor and shall be deemed to be included in the item rate.
We believe that this clause added into the special conditions will address the concerns raised in your example and cover us if an item has been completely missed in the Bill of Quantities.
Point 4 - My apologies for throwing this in at the last minute. It was my belief that these kind of items would simply be filled out with the standard rates which we usually see (usually $500- $1,000 per day). I did not anticipate this being left blank and was not aware of the potential claims if it was. Since we have been contracting, we have never had a contract where [liquidated damages] have not be stipulated and formed part of the contract.
Our concern is that, for example, one day past the specified completion date, a potential claim against us could be "loss of revenue if land purchasers were to pull out of the contract''. This would open us up to potential huge costs for simply being one day late. This is a risk that we are not able to accept as it is out of our control.
Generally we see [liquidated damages] rates of $500 per day however have recently noticed ones slightly higher. We based our $1,000 per day [liquidated damages] on an interest rate of 6% per annum of the contract amount which we believe is reasonable. We are however open to negotiate this rate if you believe your reasonable costs would be higher.
As the signed documents have already been sent, I would suggest that the relevant pages are re-issued by email so that we can sign and send back.
I believe that the hard yards are done and we look forward to addressing these few last concerns so that we can finalise the contract.
Please let me know if you can agree to these changes.
89 Plainly, Mr Vassallo, in amending the draft contract, indicated that he did not accept any offer inherent in Mr Ide's conduct in sending the draft to him. It also follows that Mr Vassallo did not consider that the letter of 5 April 2012 had resulted in the formation of a binding contract, probably because the parties had been, for some time, negotiating the terms to be included in a formal, written contract.
90 On 12 April 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
Hi Victor,
I understand your position as you understand this contract is the first of many civil contracts on the estate. I will discuss with Chris and Sam next week and come back to you but I still have concerns. I have the advantage of being involved in many projects as a lawyer dealing with construction contracts upfront and in resolution acting for principals, contractors and project managers/civil engineers as well of a principal but most have been limited to South -East Queensland where there is many quality contractors as well as those who take short cuts contractors who you avoid. Most contracts I see including those prepared by Project Managers and Civil Engineers have Part B amendments to AS4000 as I previously presented to you so that the contract is more of a turn key contract project delivery intent where the contractor delivers the project rather than just looks at individual elements. Government contracts often have more extensive part B amendments.
I can understand in Mackay your position is fairly special in that you don't have much competition as a quality contractor. Also most construction contractors in SE Qld are totally focused and dependent on contracting where you have a broad diversified revenue base. I know you do Main Roads Work and perhaps they are more work undertaken basis or the work is more uncertain. I am surprised you haven't been in contracts with Part B amendments and can only conclude perhaps as not the turn key project delivery intent we usually see.
We are extremely cautious and don't wish to see variations, first as it shows a deficiencies/lack of control in tendering and contractor selection phases, second as changes feasibility and third as risks being unfunded. We very reluctantly deleted the clause of having to include all variation claims in the progress claim relative to the period when the work was undertaken and with respect couldn't see how you would be unfairly treated. You very firmly rejected that request. If you have never entered contracts and have no need or wish to enter contracts to be awarded projects that include clauses dealing with discipline of including variations in progress claims and taking responsibility for overall delivery then I understand your position of not being prepared to on this instance and I would take the same position.
Let me come back to you on points 1 and 3. I am unsure if we are able to agree on deletion of this provision as I am not sure if our company should take on additional risk in project delivery. If we have no choice we will naturally have to but that is not clear. The example I gave is the obvious one but even on your suggested wording there is still the risk for dispute as whether something is minor or not minor. As I said were were looking for the contactor to be responsible for project delivery and if anything has been missed in Bills of Quantities with your experience you would know and have requested clarification or identified it as an omission in tender submission. Could I suggest you review the drawings and Bill of Quantities again and see if anything has been missed. If following your review your position changes please come back to me by email asap.
Point 4 [liquidated damages] I am prepared to do calculations and discuss with you further.
Subject to weather we would like to be underway first week of May hence we need to resolve this one way or the other asap. I will be back in the office on Monday.
91 On 13 April 2012 Mr Vassallo sent an email to Mr Kinneally as follows:
Hi Ross,
I appreciate you do not want any surprises, our main concern regarding Points 1 and 3 is that we have seen many poorly designed and scheduled contracts.
On further review and discussion with my team, we have formed the view that Westera appear to have done a good job designing and scheduling the project. The only missing item that we are aware of and have previously identified is the removal of the houses.
As such, in order to illustrate our commitment to the project we will accept the clause in questions with an exception added for the removal of the houses which we will discuss with Sam on possession of the site.
I will await your response regarding [liquidated damages] and discuss with you further.
We have begun scheduling our resources to begin first week of May if the site is dry enough to ensure no delays of the project.
92 On 18 April 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
In your previous email you mentioned about resourcing up for a start early May and Sam mentioned Bob requesting something yesterday. Until such time as the contract is agreed and signed and the conditions precedents are satisfied you should not do anything that you are not prepared to loose if the contract doesn't go ahead. We know we are committed to paying for grass stockpiling and drainage to the limits as authorised but that is all.
We are working up eastern precinct design and as of yesterday we identified an issue that is going to require design changes to the Western Precinct as well as authorisation from Council and it is unlikely we will be able to start within the month.
93 On 18 April 2012 Mr Vassallo sent an email to Mr Kinneally as follows:
Thanks for the update Ross.
We have put a fair bit of internal commitment to resourcing the project team and scheduling of plant, but have not placed any orders or commissioned any subcontractors.
I'll be back at work next Monday and we can discuss the design issues then.
94 On 19 April 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
As I said until such time as the contract is agreed and signed and the conditions precedents are satisfied you should not do anything that you are not prepared to loose if the contract doesn't go ahead. We know we are committed to paying for grass stockpiling and drainage to the limits as authorised but that is all.
The directors have identified a serious issue with the proposed contract with you which we are reviewing and it may not go ahead.
Mr Vassallo responded on 24 April 2012 as follows:
I am back at work and tried to call you yesterday.
Could you please let me know how things are going and whether I can assist to resolve any design or contract issues.
95 On 25 April 2012 Mr Vassallo sent an email to Mr Kinneally as follows:
Further to my email on Tuesday, I would like the opportunity to discuss the matters raised in your emails of Wednesday and Thursday last week (18/4/12 & 19/4/12). You initially indicated that the project may be delayed due to a design issue and then subsequently said that the Directors had a problem with the contract with us and that it may not proceed.
Until receipt of these last two emails, we were operating in good faith that formalisation for signing of the contract had been resolved, and that as discussed we were progressing toward a start in late April/early May. As I stated in my last email, we have programmed work in progress to ensure that personnel and resources are ready for an immediate start and undertaken preliminary administrative and site works.
We received a "Letter of Intent" dated 9 December 2011 and subsequently a "Letter of Acceptance" dated 3 April 2012, which in effect constitute a contract under AS4000. All subsequent work has been carried out in good faith on the basis of that correspondence.
Given that the recent lack of communication and failure to my calls, I am now concerned about your intentions with regard to the contract in so far that you have previously stated that you have adequate presales to satisfy your finance obligations which is the only condition requiring confirmation.
I remain hopeful that we can resolve any new issues quickly with a view to commencing on site as soon as possible in order to maximise the current "dry" period.
Please advise by no later than 5.00pm Thursday 26 of April 2012 how you intend to proceed.
96 On 26 April 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
I will give you a call tomorrow morning. I have meetings all day. Clearly outstanding is [liquidated damages].
97 Mr Vassallo sent an email dated 26 April 2012 to Mr Kinneally as follows:
Thanks for your email.
Please advise the best time to expect your call, and I will ensure that I am available. We can discuss the [liquidated damages] tomorrow as I see this as a fairly minor issue.
98 On 27 April 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
Before we discuss further matters we need to clarify the status of the contract you refer to in your below email. The fundamental legal and commercial position is that where it is contemplated that a formal agreement will be agreed and signed then the parties are not bound until the formal agreement is agreed and signed. I looked at AS4000 particularly clause 6 and can see the confusion re if there was issued an unconditional "Letter of Acceptance". The issue of a Letter of Intent is exactly that but is not a contract.
Sam sent Bob on 22 February a draft of a contract which had embodied in it was a copy of Letter of Acceptance. Sam sent ob on 3 April 2012 a copy of contract for signing by all parties which had embodied in it a Letter of Acceptance which as the party to it Westera Partners signed. The Letter of Acceptance embodied in the contract was dated 3 April, 2012 included Construction Period shall be 30 weeks. You contacted Sam and asked him to amend the Letter of Acceptance to say the Construction Period shall not exceed 30 weeks which Sam reissued to you on 5 April, 2012 but it remained dated 3 April, 2012. The letter was to be embodied in the contract the contract signed and returned.
So in your email below what Letter of Acceptance are you saying formed the contract (the one sent and dated 3 April, 2012 or the one emailed to you on 5 April, 2012 and dated 3 April, 2012) and what then is the contract date?
99 On 27 April 2012 Mr Vassallo sent an email to Mr Kinneally as follows:
I just tried to call you in relation to your email. Could you phone me when you are free please.
Mr Kinneally sent an email to Mr Vassallo on the same day as follows:
As I said, before we discuss further matters we need to clarify the status of the contract you refer to in your below email (25 April). The points you make in your below email are technical and unless we understand your position we do not have a benchmark to go forward.
Please reply to those points as soon as possible by email.
100 Mr Vassallo replied on 29 April 2012. After first complaining about the fact that he had not been able to speak to Mr Kinneally by telephone he continued:
As I see it, what constitutes the contract are the facts of each sides actions and the documents and correspondence supporting them. The actual date can be determined at any time now or in the future and I will not comment on this matter until I have sought expert advice (bearing in mind your professional qualifications).
I want to know if you intend to continue on with this contract with us, as you seem to still be implying in your emails. We need clear direction. We will continue to act as if we will be constructing this project until you tell us otherwise. Due to the size of this contract we have forgone tendering numerous large projects and declined good jobs that we could have undertaken.
We have recently heard from one of our major suppliers that you awarded this contract to another contractor approximately two weeks ago and they are currently resourcing the project. Please confirm if this is correct so that we know what our position is.
If my comments above are incorrect then you should, as promised in your email of 12 April 2012, Point 4 [liquidated damages] "prepare calculations for discussion" and confirm your verbal advice that the finance condition has been satisfied by way of documentation.
I look forward to hearing from you by close of business 30 April 2012.
101 On 30 April 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
At this stage we are intending to proceed with another contractor. I have not called you back due to how negotiations have been handled to date.
He then gave his version of the events which had occurred since 9 December 2011. He concluded:
You should urgently brief a lawyer with the relevant expertise to advise you on your legal position. Unless I hear from you by close of business today that you withdraw your assertion of a legal contract I will assume that you continue to standby that assertion in which case we will need to seek an urgent determination of the issue which will have negative cost implications. We are not prepared to let the matter go on.
102 On 1 May 2012 Mr Vassallo sent an email to Mr Kinneally as follows:
Hi Ross,
Thank you for finally being honest with me. I am curious as to how long you would havecontinued the farce of pretending to move forward. I can only assume that you hadn't sewn everything up with the other contractor and wanted to keep me on the hook for as long as it suited you. I can also understand why you didn't want to talk to me directly given the way you have conducted yourself.
I am very disappointed that you didn't even give me the courtesy of a phone call before making your decision to go with another contractor. I have always acted honestly and fairly with you throughout the process and the accusations you have made regarding the negotiations are unjust, and can't go unanswered.
None of the Special Conditions or Annexure B were revealed to us at the time of tender (other than the finance condition) and in fact we had been told that the contract was to be administered under AS4000 unamended. When we received the special conditions and Annexure B mid March this year, and with great surprise to see new conditions, we entered into negotiations in good faith in an effort to achieve a fair outcome for both parties. At no time during the negotiations did either party have any sort of advantage over the other. You were not forced to make any compromises and I can only assume that you did so because they were fair and reasonable. All negotiations were amicable and I believed were all but resolved, with only a couple of minor issues to be finalised when you got back from holidays. In our experience, it is always best to have all contractual issues resolved up front so that there are no surprises down the track.
In your most recent correspondence, you have placed a great deal of emphasis on the need to minimise your risks. I can only state the obvious by saying that it goes both ways. I am sure that if you were acting for us in your professional capacity on any other project, you would have agreed with our approach. You will always find a contractor who is willing to take on extra risks in order to win a contract, especially in a depressed market. We have seen many of them go broke or leave town if things go bad. We have been in business in Mackay for nearly twenty years and I can assure you that we have established our good reputation because we are careful and always provide quality work and within the project timelines.
The Letter of Intent dated 9 December 2011 was issued so that we could do everything necessary to ensure a hasty commencement of thecontract in March or as the weather permitted. We have expended a considerable amount of time and money readying for this project. To my mind the only risk was that you may not get finance (and you confirmed that pre-sales were in place to satisfy your finance commitment at our meeting of 9/03/12). At no time did I consider that you would renege on a signed Letter of Intent and a Letter of Acceptance, as I had assumed that you had higher business ethics than that. Your only concern now is to protect your own interests by asserting that we undertook the preliminary work at our own risk.
There is of course a contract, and the signed Letter of Acceptance and your actions affirms this. Furthermore, I believe that if the tables were turned and we had walked away from the project because we had a better offer elsewhere, you would have been quick to take legal action. Whether we choose to take this action is another matter. Any sort of litigation or the potential for such would only serve to hold your project up and provide me with an unneeded distraction. Whilst I am extremely tempted to do so, given the deceptive way that you have conducted yourself of late, I don't wish to prolong my association with your group.
My position on this matter will of course be based on your prompt payment for all costs undertaken to date. A full account will be forwarded shortly.
In closing I can only say that your company has missed a great opportunity to work with a good local contractor and an excellent team of highly qualified personnel.
103 On 2 May 2012 Mr Kinneally sent an email to Mr Vassallo as follows:
Hi Victor,
I don't wish to be too pointed but you are an experienced and extremely robust commercial negotiator and I understand your motivation in relation to pushing the boundaries and reducing your risk wherever possible. I respect your commercial skills. However we found in the circumstances your approach too strong and even over the last 2 weeks when we obviously put out our concerns you did persist with claiming there was a contract. To make that claim when it was legally untrue meant that neither of us could be as open as we were previously. Iam not naive to keep speaking openly when serious legal claims are being made. You had tied our hands.
My email of 30 April was very professional. I referred to your strong approach to the negotiations we had. I did not make comments about your intentions, honesty or ethics as that would have been unnecessary and I don't intend to correct the inaccuracies nor respond to the unnecessary judgements in your below email.
We have no reason to speak in any negative terms about your company's ability to deliver and will not do so. While you may never wish to engage with us again we will not make the same claim but more items would be resolved earlier.
Provided that your costs are substantiated and limited to the authorised amounts they will be paid promptly. Please email your invoice and details of your costs through to me this week for payment.
104 The "authorised amounts" are, I assume, the amounts outstanding with respect to the work performed under special arrangements, to which work I have previously referred.