Findings
69Section 79C(1)(a)(ii) of the Act requires me to consider any proposed environmental planning instrument that has been the subject of public consultation and has been notified to the consent authority. Section 79C(1)(e) requires consideration of the public interest.
70The planners agree that Draft BLEP 2103 is neither imminent nor certain and is in a 'queue' with other draft instruments. Given the number of recommended amendments, there is also uncertainty as to whether the Draft LEP will need to be re-exhibited. Clearly, if it is re-exhibited, the time until gazettal will be lengthy.
71The public interest was not raised as a separate contention but underlies the council's first contention and submissions regarding council's need of the site for the construction of a drainage basin. Although I am satisfied of council's reasoning for the proposed re-zoning of at least part of the applicant's land, the minutes of the December 2013 meeting indicate there was considerable opposition from similarly potentially affected land owners across the LGA and there is more consultation to be undertaken.
72It is common ground that it is open for the council to seek to acquire the land. Section 54(1) of the Land Acquisition (Just Terms Compensation) Act 1991 (LA-JTC Act) states:
(1) The amount of compensation to which a person is entitled under this Part is such amount as, having regard to all relevant matters under this Part, will justly compensate the person for the acquisition of the land.
73Possible acquisition is contemplated in the minutes of council's meeting of December 2013 as well as in the Perrens Report.
74In determining the amount of compensation, amongst other things, s 55(a) requires regard must be had to the market value of the land on the date of its acquisition.
75Section 56(1) states (relevantly):
(1) In this Act:
market value of land at any time means the amount that would have been paid for the land if it had been sold at that time by a willing but not anxious seller to a willing but not anxious buyer, disregarding (for the purpose of determining the amount that would have been paid)):
(a) any increase or decrease in the value of land caused by the carrying out of, or the proposal to carry out, the public purpose for which the land was acquired, and
76Item 2h in council's minutes reiterates this:... the value of the property and its improvements based on the underlying zoning and not the acquisition purpose....
77While I agree in principle that the creation of public reserves and the management of stormwater are in the public interest, it is hard to ignore the proposition that if the council was intent on acquiring the site as a portion of the land identified 10 years ago as being necessary for a drainage basin, it has had ample opportunity to do so. I also note that apart from the applicant's property, the design of the proposed drainage basin would occupy all or part of 10 or 11 other lots, most of which contain dwellings and other structures.
78Council's minutes of the December 2013 meeting indicate there is a range of means by which council may fund land acquisition. While mention was made during the hearing of a '$20m funding source' and a new s 94 contributions plan, Resolution 13 (at [34]) indicates that the $20m fund is yet to be established and the new s 94 plan can't be made until the new LEP is made. It appears that any acquisition would require a circuitous financial pathway and is unlikely to be immediate or imminent.
79It is also hard to ignore the fact that none of the three potential drainage basins identified in the Perrens Report have been constructed. Apart from Mr Merrilees' preliminary design for the detention basin in question, no evidence was adduced that council has engaged in any further detailed preparatory work across this drainage system to further advance the implementation of the measures identified in the Perrens Report. Although I understand the rationale for relocating the basin to the corner of Newton Road and Meroo Street, I agree with the applicant that it demonstrates the location is somewhat flexible. On Dr Martens' evidence, there are other engineering options that would enable the construction of the basin in some form that would not require the whole of the applicant's site. That is, the use of the site for residential purposes does not preclude the construction of a drainage basin in some form. The planners agreed that should it be required, the eastern portion of the site, proposed as common open space, could be incorporated into future public open space should the basin be constructed.
80Therefore, I agree with Mr Staunton that there has been no demonstrated urgency in acquiring the land and that having purchased the land, his client has proceeded to apply for a development permissible with consent under the current zoning.
81For these reasons I find that the appeal cannot be dismissed on the basis of contention 1.
82Notwithstanding the considerable level of agreement between the drainage experts on most of the particulars raised in contention 5, the remaining areas of disagreement concern the possible impacts of increased flood levels on adjoining properties as a consequence of the proposal and criteria used in flood modelling. In addition, Mr Merrilees is also concerned about the safety of anyone who may be using the common open space in the event of a major flood.
83After careful consideration of the generally agreed without prejudice conditions of consent in Exhibit Q, and while I acknowledge there is an elevated risk to occupants of units 1-4 and to anyone using the common open space, I am satisfied that in the event of a 1 in 100 year flood event, the detailed drainage requirements specified in condition 6.2.3 and the associated amendments to the architectural plans detailed in condition 6.2.8 provide for the safe access, use and occupation of the site for residential purposes. These conditions include the need to provide flood warning signs in potentially affected areas of common and private open space and the development of a Flood Management Plan to be prepared and permanently affixed to each unit. Council has a standard flood warning sign and the uncontested evidence is that these have been approved for nearby developments.
84I am also satisfied that the proposal includes compliant areas of private open space so that the residents are not reliant on potentially flood affected common open space. I agree with Dr Martens that it is highly unlikely that anyone would remain outside in the weather conditions that would lead to a major flood event.
85Condition 10.6.12 requires a positive covenant that the openings under the driveway and Units 1-4 shall not be used for storage and that a report of inspections be provided to council on an annual basis. Given this condition, the proposed bars and lockable access under the driveway, and location of the driveway and its construction as an elevated driveway above a substantial width of concrete pavement, the propensity for blockage appears low and therefore Dr Martens' blockage factor of 15% does not seem unreasonable.
86While this site like many others in the vicinity is in a flood risk zone, I am satisfied to the extent required by s 79C that subject to the imposition of the proposed detailed conditions, consent can be granted to this development.