Ucak v Avante Developments
[2007] NSWSC 367
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2007-04-19
Before
Hammerschlag J
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
Introduction 1 This is an application by motion to strike out two paragraphs of the defendant's Construction and Technology List Response ("the Response") invoking the Proportionate liability provisions in Pt 4 of the Civil Liability Act 2002 (NSW) ("the Act"). The Act came into force on 20 March 2002. Part 4 was introduced into the Act by the Civil Liability Amendment (Personal Responsibility) Act 2002 (NSW) which came into force on 1 December 2004. 2 The application raises what might be considered to be the significant issue of what is required to be pleaded by a party wishing to raise the defence contemplated by ss 34 and 35 (within Pt 4) of the Act that his or her liability is to be limited because he or she is, in relation to the claim against him or her, a concurrent wrongdoer, that is, a person who is one of two or more persons whose acts or omissions (or act or omission) caused, independently of each other or jointly, the damage or loss that is the subject of the claim. 3 The motion prays in aid Pt 14 r 14.28 of the Uniform Civil Procedure Rules 2005 (NSW) ("UCPR") which provides that the Court may at any stage of the proceedings order that the whole or any part of a pleading be struck out if it discloses no reasonable cause of action or defence or other case appropriate to the nature of the pleading, or has a tendency to cause prejudice, embarrassment or delay in the proceedings, or is otherwise an abuse of the process of the Court. Although Pt 14 of the UCPR applies only to proceedings commenced by statement of claim and these proceedings are commenced in this List by summons, accompanied by a Technology and Construction List Statement ("Statement"), the Court has, as a necessary incident of its jurisdiction, the power to control its own proceedings and procedure in the same way as if the proceedings were conducted on pleadings in the strict sense. 4 Practice Note SC Eq 3 applies to these proceedings. Paragraphs 8 to 17 of the Practice Note deal with pleadings. The Practice Note requires a defendant in this List to file and serve a Technology and Construction List Response setting out in summary form, amongst others, its response to the plaintiffs' Statement including the legal grounds for opposition to the relief claimed in the summons. Both the Statement and Response must avoid formality. 5 Paragraph 51 of the Practice Note concerns applications to strike out or for summary judgment, which may be entertained when appropriate. Applications such as the present will not generally be entertained in this List and strictness will be applied in declining to entertain such applications unless appropriate. 6 Albeit that a plaintiff's Statement and a defendant's Response can and should avoid formality, the Practice Note does not dispense with the fundamental requirement that each disclose a reasonable cause of action and defence respectively. The legal grounds for opposition to the relief claimed must, even though informally expressed, disclose a cognisable defence. 7 The principle that the Court has as an incident of its jurisdiction the power to, and will, strike out a pleading which discloses no reasonable cause of action or defence, or which has a tendency to cause prejudice, embarrassment or delay in the proceedings or which otherwise is an abuse of the process of the Court, is recognised in par 51 of the Practice Note and applies to a Statement and Response in this List with no less force albeit Pt 14 of the UCPR does not strictly apply. 8 The management procedures in this List are directed to the just, quick and cheap disposal of proceedings. Those aims will not be achieved by permitting Statements and Responses which fail to comply with the Practice Note in material respects. Background 9 The plaintiffs, who are individuals, own a property situated at 164 Brooks Street, Coogee in the State of New South Wales. They allege that in about July 2003 the defendant company undertook excavation works in the course of developing residential units including basement car parking on the defendant's property next door. Those works, they say, had the effect of removing lateral support for their land. Their property was damaged and they have suffered economic loss as a consequence. 10 By summons dated 8 December 2006 accompanied by a Construction and Technology List Statement, which includes a section entitled The Plaintiffs' Contentions ("the Contentions") they sue the defendant company for damages under two heads; firstly, for breach of the duty of care not to do anything which would remove the lateral support for the plaintiffs' property and, secondly, for trespass committed by the installation of ground anchors beneath it. 11 Paragraphs 20 and 21 of the Response are in the following terms: "20. Further, and in answer to the whole of the Plaintiffs' Contentions, the Defendant says that if the Plaintiffs suffered loss and damage as alleged, which is not admitted, the liability of the Defendant for that such [sic] loss and damage must be limited to the extent of the Defendant's responsibility for the damage or loss in accordance with Part 4 of Part 4 [sic] of the Civil Liability Act 2002 (NSW). 21. Further, in answer to the whole of the Plaintiffs' Contentions and in accordance with section 35A of the Civil Liability Act 2002 (NSW) the Defendant says that if it is liable to the Plaintiffs ( which it denies), Henry & Hymas, Pile & Bucket Pty Limited, Geotechnique Pty Limited, Geoform Design Architect Pty Limited and SW Healey & Associates may be concurrent wrongdoers in respect of the claim." 12 On 16 March 2007, in a letter to the defendant's solicitors, the plaintiffs' solicitors complained that each of the paragraphs "is not in proper form and is liable to be struck out". They requested further and better particulars of par 20 including a request in the following form: "What are the facts, matters and circumstances relied upon which are alleged to limit your client's liability in the proceedings?" They complained that par 21 failed to comply with the requirements of s 35A(1)(b)(ii) of the Act, and in relation to that paragraph included a request in the following form: "What are the facts, matters and circumstances relied upon to assert that each of the named parties is or may be a concurrent wrongdoer in relation to the claim?" They threatened a strike out application if full particulars were not provided or the paragraphs were not amended so as to be pleaded in proper form. 13 The defendant's solicitors responded in a letter dated 21 March 2007. With respect to pars 20 and 21 of the Response they stated that: "The circumstances that make those other persons potential concurrent wrongdoers are detailed below: 1. Henry & Hymas were retained by the Defendant to act as structural engineers in relation to the development of 162 Brook Street, Coogee. Henry & Hymas oversaw the Excavations Works noted in paragraph 7 of the Summons. 2. Pile & Bucket were retained by the Defendant to carry out the Excavation Works noted in paragraph 7 of the Summons. 3. Geotechnique Pty Limited were retained to provide geotechnical engineering services in relation to the Excavation Works. 4. Geoform Design Architect Pty Limited were retained by the Defendant as architect for the Development Property. 5. SW Healey & Associates Pty Limited were retained by the Defendant as structural design certifier for the Development Property. If your clients' claim is successful and the Court accepts that the Excavation Works noted at paragraph 7 of the Summons were carried out in breach of a duty of care, this is a liability which should be attributed to the concurrent wrongdoers noted above. We do not believe there is any requirement on our client to identify the extent of the comparative responsibility of each party alleged to be a concurrent wrongdoer. Rather, the extent of the comparative responsibility of each party is a matter to be determined by the Court. We put you on notice we will oppose any Notice of Motion seeking to strike out paragraphs 20 and 21 of our client's Defence."