At paragraph 37 his Honour said:
"Although no previous case has dealt with the situation where a party giving a Notice to Complete has purported to extend the time specified in it, the matter is I think determined by the principle that both parties are bound by a valid Notice to Complete, once it has been given. In addition, as pointed out by Mr Officer, any other view would be productive of great uncertainty. Presumably, any notice extending the time would have to be given a reasonable time before the time specified, producing real questions as to what would be a reasonable time. Once a Notice to Complete has been given, the other party would presumably feel obliged to incur whatever trouble and expense was necessary to comply with it, which could be wasted if the party giving the Notice to Complete could simply extend the time which it specified."
19 It will be seen that the Court, in effect, accepted as correct the submission made by Mr Officer QC. The result in the present case is that, as Mr Skinner contends, Mr Klinger's letter of 3 December 2002 could not operate to waive compliance by the First Defendant with the requirement of the Notice to Complete to complete the contract by 4 December 2002. But this does not really take the Defendants' case anywhere. Time remained of the essence for completion as at 4 December and as the contract had not been completed on that date the Plaintiff was thereafter entitled to terminate. As I have noted, the settlement did not occur on 4 December 2002.
20 It is a fair inference from Mr Bahar's assertions that the Notice to Complete was invalid, that the First Defendant was indicating that it would not attend settlement on 4 December, so that Mr Klinger would be justified in not attending at the time and place specified for settlement in his Notice to Complete.
21 Nothing happened after 4 December except that Mr Klinger required completion on 20 December but Mr Bahar continued to deny the validity of the 20 November Notice to Complete. When settlement did not occur on 20 December, time for completion on 4 December having been made of the essence and the First Defendant being in breach of that extension condition, the Plaintiff was entitled to terminate.
22 It is important to emphasise that no allegation has been made by the Defendants of any conduct after 4 December founding an estoppel or waiver or amounting to an election on the part of the Plaintiff which would deny it the right to rescind on 23 December, as it has done. The case has been fought entirely upon the issue whether the Notice to Complete given on 20 November was effective in the circumstances which thereafter occurred.
23 The result is that, in my opinion, the Plaintiff validly rescinded the contract on 23 December 2002 for the First Defendant's non-compliance with the Notice to Complete which had been given on 20 November.
24 As to forfeiture of the deposit, Mr Skinner said at the outset of his submissions that if it were decided that the contract had been validly rescinded by the Plaintiff, he would not press any submission that the deposit should not be forfeited to the Plaintiff.
25 The Plaintiff is therefore entitled to the declarations sought in paragraphs 1 and 2 of its Summons. There will also be an order in terms of paragraph 3 of the Plaintiff's Summons. There will be a reference to the Master to enquire as to what damages, if any, have been occasioned to the Plaintiff by the breach of contract by the First Defendant. It follows from what I have said that the Defendants' Cross Claim will be dismissed. The Defendants will pay the Plaintiff's costs of the Summons and the Cross Claim on a party/party basis.
26 I will stand the proceedings over for a short time to enable the parties to bring in Short Minutes of Order reflecting these reasons and the orders which I propose to make, and providing for a calculation of interest on the deposit. If desired, I will set a timetable for a reference to the Master for an enquiry as to damages.
- oOo -