Is the draft LEP immininent and certain?
48The weight to be attributed to a draft environmental planning instrument will be greater if there is a greater certainty that it will be adopted ( Terrace Tower Holdings Pty Ltd v Sutherland Shire Council (2003) NSWCA 289 at par 5). Relevantly, in Terrace Tower , Spigelman CJ states at pars 6 and 7 that:
6. Notwithstanding 'certainty and imminence', a consent authority may of course grant consent to a development application which does not comply with the draft instrument. The different kinds of planning controls would be entitled to different levels of consideration and of weight in this respect.
7. Where a draft instrument seeks to preserve the character of a particular neighbourhood that purpose will be entitled to considerable weight in deciding whether or not to reject a development under the pre-existing instrument, which would in a substantial way undermine that objective.
49In Blackmore Design Group Pty Ltd v North Sydney Council [2001] NSWLEC 279, Lloyd J relevantly states :
30. Whether one applies the test of "significant weight", or "some weight", or "considerable weight" or "due force" or "determining weight" to the later instrument is not, however, the end of the matter. The savings clause still has some work to do. The proposed development is a permissible development by dint of the savings clause. In giving the 2001 LEP the weight of being imminent and certain, that does not mean that there is no further inquiry. It is necessary to look at the aims and objectives of the later instrument and then see whether the proposed development is consistent therewith. Various expressions have been used to define this concept, but the approach which has been favoured in the Court of Appeal is to ask whether the proposal is "antipathetic" thereto (Coffs Harbour Environment Centre Inc v Coffs Harbour City Council (1991) 74 LGRA 185 at 193).
31. This approach was adopted in the cases to which I have referred. In Mathers v North Sydney Council Talbot J (as noted in par [22] above) attributed significant weight to the then draft LEP to the extent the Court ought to be satisfied that approving the development would not detract from its objectives as expressly stated or reflected in the proposed controls.
32. In that case Talbot J refused the appeal on the ground that the proposed development was inconsistent with the proposed planning controls in the draft local environmental plan.
33. Similarly, in Architects Haywood & Bakker v North Sydney Council after stating that significant weight should be placed upon the provisions of the draft plan, Pearlman J considered whether the proposed development accorded with the planning approach and objectives of the proposed controls in the draft local environmental plan. It was the fact that the proposed development ignored the planning approach adopted by the draft LEP that led Her Honour to refuse the application in that case.
34. In Edward Listin Properties v North Sydney Council Talbot J said (at par [15]):
Although it may not be appropriate to dwell too heavily upon the detailed controls implemented by the draft LEP, it is certainly important to have regard to the broad objectives which the draft planning instrument seeks to achieve.
35. His Honour further stated (at par [35]):
...If what is proposed is unsatisfactory in general terms and inconsistent, in particular, with the expressed future planning objectives for the area, then it should be rejected.
36. In Walker v North Sydney Council Cowdroy J found that the evidence established that the development application was contrary to the planning objectives of the locality, for which reason His Honour rejected the development application.
50In our view, the questions to be answered are firstly, whether the draft LEP is imminent and certain and if so, what weight should the draft LEP be given in the consideration of the application. Secondly, and if it is found to be imminent and certain, whether the proposal will undermine the expressed future planning objectives in the draft LEP.
51On the question of whether the draft LEP is certain, we accept that the draft LEP is likely to be gazetted as it is well advanced in the plan making process. The experts agree that the preparation of the draft LEP is at an advanced stage. The difference in time of likely gazettal between Ms Fadeer and Mr Player is the end of June 2011 and around August 2011, respectively. Considering the time since the implementation of the draft LEP process (March 2007), even Mr Player's estimate must be regarded as imminent.
52The question of certainty centres on whether the site (and the Oxford Falls Valley area) will be a deferred matter or zoned E3 - Environmental Management. We do not accept Mr Player's evidence that the site may be given some other zoning under the draft LEP as there is no evidence to support this proposition. We accept that over the time, the potential zoning of the site in the draft LEP has been discussed between the council and the Department of Planning, however as the finalisation of the draft LEP has drawn closer, the evidence suggests that the site is likely to be zoned E3 - Environmental Management rather than deferred. We base this conclusion on the most recent e-mail from the Departmental of Planning, dated 31 May 2011 (Ms Juliet Grant, Regional Director, Sydney East) in response to an e-mail from the council (Mr David Kerr, Manager Strategic Planning) on the same day.
53The council's e-mail makes the following enquiry of the Department of Planning:
From your e-mail and our discussions, my understanding is that the draft Warringah LEP is with Parliamentary Counsel's Office and will be sent on to the Director General for final endorsement with it anticipated that the LEP will be made by the end of June 2011. I also understand that the matters of the Brookvale and Oxford Falls Valley (in respect of which deferral has previously been contemplated) are no longer proposed to be deferred and zones for these areas will be included in the draft LEP in accordance with the exhibited version (ie, E3 for Oxford Falls Valley).
I'd be grateful if you would confirm whether my understanding is correct
54The response from the Department of Planning states:
David, that is certainly what we are working towards. But note that until they Minister has signed off on the dLEP, we cannot guarantee an outcome.
55Prior to this e-mail, other e-mail correspondence on 8 April 2011 between the Department of Planning (Ms Sabina Miller) and the council (Ms Noo Porima) supports this conclusion and states:
This email is just to advise that land at Oxford Falls Valley, 638 Pittwater Road, Brookvale and the Brookvale Centre will now be included in the draft Warringah LEP 2011.
Would it be possible to amend the maps to put those areas back into the Plan.
56From the evidence, we understand the reference to amending maps is a reference to the council including the site into the draft LEP as E3 - Environmental Management on the maps accompanying the draft LEP.
57From the evidence, we are satisfied that there is a high level of certainty that the site will be zoned E3 - Environmental Management consistent with council's intentions for the site and the wider Oxford Falls Valley. The council's position in relation to the site and the land within the Oxford Falls Valley is that it seeks to protect the natural features and values.
58In our opinion, the question of certainty is more critical than the issue of imminency in determining the weight that should be attributed to the draft LEP, particularly given the little differences in time frames provided by the experts. It would seem that the particular provisions of the draft LEP have greater bearing on the question of weight than when the draft LEP is finalised, subject of course to the finalisation being within a reasonable timeframe.
59The next question is whether the proposed development will, as stated in Blackmore Design (at 35), in general terms be inconsistent with the expressed future planning objectives for the area. As Seniors housing is a prohibited development within the zone, we accept that there is a potential inconsistency although this by itself is not a reason to refuse the application because of the savings provisions in cl 1.8A. Further guidance on this question can be obtained from the zone objectives for the E3 - Environmental Management, which are:
- To protect, manage and restore areas with special ecological, scientific, cultural or aesthetic values.
- To provide for a limited range of development that does not have an adverse effect on those values.
- To ensure that development, by way of its character, design, location and materials of construction, use integrated into the site and natural surroundings, complements and enhances the natural environment and has minimal visual impact..
- To protect and enhance the natural landscape by preserving remnant bushland and rock outcrops and by encouraging the spread of indigenous tree canopy.
- To protect and enhance visual quality by promoting dense bushland buffers adjacent to major traffic thoroughfares.
60If the objectives for zone E3 - Environmental Management are considered collectively, the clear focus is protect and manage the natural qualities of the area but allow a limited range of developments that do not affect these natural qualities. The objectives also seek to "restore" and "enhance" the natural qualities of the area. If compared to the proposed development we can comfortably conclude that there is a fundamental inconsistency with the expressed future planning objectives for the area through the following:
- the proposed development is a prohibited use under the draft LEP,
- the natural qualities of the area, being its native vegetation and natural features, are unacceptably impacted on by the proposed development through the construction zone and the need to provide extensive APZs,
- the proposed development cannot "restore" and "enhance" the natural qualities of the area as the proposed landscaping is limited by the available area within the construction zone and the need to significantly reduce the native vegetation for the extensive APZs, and
- the proposed development will result in a dense urban form that is concentrated on one part of the site.
61If the weight to be given to the draft LEP is considered against its imminency, certainty and consistency with the expressed future planning objectives for the area, we are satisfied that the draft LEP should be given determinative weight and as the proposed development will be so inconsistent with the character envisaged by the draft LEP, the application should be refused for this reason alone.
62For completeness we will briefly deal with the other issues raised in the proceedings.