(ii) it also knew what type of work was to be undertaken in the building:-
so that it could not have been satisfied that it was appropriate to leave it to the project manager to ensure that the building would not be left in a condition which might create a real risk of injury to a visitor of the class of persons of which the plaintiff was ultimately a member.
52 For my part, all other things being equal, I would have difficulty in accepting that an occupier of these premises who was not physically present at the premises and who wished to have refurbishment work of the type here involved carried out, would have failed to act reasonably if it did no more than to appoint a company which appeared to be competent as project manager of the works. Whilst there was still one tenant remaining in the building and certainly the probability that members of the public might visit that tenant, the subject works are not shown to have been inherently dangerous. Dealing with the particular facts which ultimately occasioned the plaintiff's accident and injuries, this was no more than replacement of carpet on stairs. Conventionally this operation ought not occasion any particular risk if carried out with care.
53 There are two problems with this proposition in terms of the current proceedings on appeal.
54 The first is that expert evidence was called before the trial judge on the duties of a project manager including the matter of the adequacy of periodic inspections by a project manager. The trial judge dealt with this evidence. Quadrant had called Mr Lowry who under cross-examination was asked whether (leaving aside the terms of the agreement) the project manager could ascertain that the work was being properly carried out by periodic inspections. His evidence had been that the project manager could ascertain that the work was being properly carried out provided the project manager was doing what was required of him under the contract. Generally his evidence was that the project manager should carry out his duties in accordance with the terms of the contract.
55 Howse called expert evidence from Mr Farmer. His evidence was that he was confident that anyone entering into the project management agreement would have understood that there would be full-time supervision for the relevant fee. His evidence was that in his view Mr Dwyer, on noting that the nosings were incomplete and in bringing that to the attention of the representative of Bianco on site, had discharged his obligation to supervise. For reasons explained in the judgment the trial judge formed the view that Mr Farmer had become an advocate for Howse and was not prepared to accept his opinion where it was in conflict with that expressed by Mr Lowry.
56 The second and critical problem with this proposition holding good in this case concerns the circumstance that Quadrant had itself, on the evidence, made side arrangements with an outside carpet company to supply and install the carpet in question. There was no evidence at all given to the effect that Quadrant had properly or at all apprised either Howse or Bianco of these arrangements or as to when they would be effected or of the extent, if any, to which the extant contractual obligations of Howse or Bianco were to be regarded as now extended to embrace obligations to supervise or to participate in any way at all in the matter of the installation of the new carpet by the outside carpet contractor. Once this parameter of the facts is taken into account, there can be seen to be a very grave problem for Quadrant in its attempt to ground its reasonable conduct upon its appointment of a competent project manager.
57 By definition Quadrant is now required to adopt some fallback position, as by a contention that its arrangements with the outside carpet contractor were sufficient to justify its assumption that the carpet laying works would be carried out competently and carefully. Its problem in this regard is that it did not call any evidence at all on the subject.
58 Although the trial judge did not approach the matter in this fashion, to my mind the evidence on this basis would clearly have justified a finding that Quadrant, as a matter of the sensible adjustment of reasonable expectations, had not taken the precautions which it could be reasonably required to have taken in the circumstances. Its negligence in this regard is shown up by the circumstance that the new carpet when laid was incomplete because the rubber inserts had not been fixed into the grooves. This satisfies the plaintiff's onus of proof of negligence in the matter. Quadrant's negligence in this regard is shown up by a combination of:
· the duty of the occupier here to appoint a competent person to supervise the laying and installation of the new carpet;
· the failure of the occupier here to coordinate on the one hand, the operations of the duly appointed project manager and/or the operations of the company appointed by the project manager to carry out the building works, and on the other hand, the operations of the outside carpet contractor with which the occupier had made its own entirely private arrangements;
· the inability of the court to infer that proper arrangements with that outside carpet contractor (which were not put into evidence), must have been made.
59 Counsel for Quadrant submitted that the plaintiff at trial had not pleaded that Quadrant was vicariously liable for its agents and had not suggested at the trial that Quadrant improperly retained a third party contractor. The submission although literally true is one without substance when faced with the manner in which the trial at first instance was conducted, taking into account the several modes in which particulars were furnished of the allegation of negligence. Quadrant either carried out the work itself or arranged for the work to be carried out by others. It seeks and sought to assert that it had employed a competent carpet layer to carry out the work. Quadrant face at least an evidentiary onus to prove that Auction Centre Ltd was a competent carpet layer.
60 Counsel for Quadrant sought to take issue with the proposition that Quadrant bore such an evidentiary onus, submitting that this turned upon whether:
· a prima facie duty to supervise must be said to exist unless Quadrant could show that it had appointed a competent contractor; or
· prima facie no duty of supervision can be said to exist unless Quadrant suspected that the contractor it had approved was incompetent.
61 There is no substance in Quadrant's submissions in this regard. Whether or not a duty to ensure adequate supervision of particular works arises in a particular occupier will always depend upon the particular circumstances. Indeed under ordinary principles of the modern law of negligence, the duty is a duty to take reasonable care to avoid foreseeable risk of injury to the plaintiff, the practical extent of the duty being governed by the circumstances of the case: Jones v Bartlett (2000) 205 CLR 166 at 184 per Gleeson CJ. The particular circumstances before the trial judge were extremely unusual, particularly in relation to Quadrant by side arrangement, moving outside of its other arrangements to have the general refurbishment works project-managed by Howse. The evidentiary onus referred to above devolved upon Quadrant by reason of the way in which the trial was pleaded and litigated in terms of the whole of the facts which arose for determination: once the plaintiff proved the position of the occupier, the defective nosings, the nature of the stairs, and the fact of recent works, the evidentiary onus shifted: cf. U.S. Surgical Corporation v Hospital Products (1983) 2 NSWLR 157 at 258 per Glass JA. In this regard I note the acceptance by Brennan CJ, Dawson, Gaudron, Gummow and Kirby JJ in Northern Sandblasting Pty Ltd v Harris (1996-1997) 188 CLR 313 of the proposition that the landlord had discharged its duty of care to the occupants in relation to a particular repair activity by engaging a qualified contractor whose confidence it had no reason to doubt.
62 In the result the plaintiff succeeds on its notice of contention in that:
· the evidence established that Quadrant arranged and engaged an outside entity (whether or not Auction Centre Pty Ltd was itself a carpet company or contractor or merely a middle-man does not appear from the evidence) to replace the carpet on the stairs of the premises;
· the accident on the evidence is shown to have occurred as a result of the negligent manner in which the outside agent did its work .
63 This should suffice to deal with all of the issues on both appeals in terms of liability.
64 In deference however to the trial judge's careful reasoning it is convenient to revisit her findings which were, inter alia: