The contract work performed related largely to excavation work carried out by Stallion Civil Group Pty Ltd. The variation work related to additional excavation work that Stallion was required to carry out as a result of amended architectural drawings. Initially, Stallion had claimed $423,168 in respect of that additional work. However, Tresedar conducted direct negotiations with Stallion (although Stallion's subcontract was not one of those that included the terms quoted above) and compromised that claim at $243,963.20. The amount claimed in respect of variations includes that amount. The amount of $454,818.33 shown as having been previously paid largely consisted of amounts paid directly by Tresedar for insurance and workers compensation and subcontractors (including Stallion) together with $50,000 paid to PBC. The deposit of $224,000 was an amount payable to PBC under the Gordon BC4 which had not been paid. At least one of PBC's complaints was that it was entitled to be paid that deposit. Tresedar's position appears to have been that, since it was paying subcontractors directly, there was no reason why PBC should be paid the deposit.
19The progress claim was expressed to be a payment claim under the Act. Tresedar did not serve a payment schedule in response to that claim within the time specified in s 14(4) of the Act. As a consequence, under s 15 of the Act, PBC became entitled to recover the amount of its claim as a debt due in any court of competent jurisdiction. It commenced proceedings in this court on 16 July 2008 (the SOPA Proceedings) to recover that debt. It also exercised its right to suspend further work under cl 21 of the Gordon BC4 and ss 15(2)(b) and 27 of the Act.
20On 14 October 2008, Tresedar, together with Tetbury and Mr Aris Evanian as guarantors of Tresedar's obligations, and PBC entered into the Settlement Deed in settlement of the SOPA Proceedings.
21Recital J of the Settlement Deed provides:
The parties agree that the amount due to PB [that is, PBC] is $1,225,650 (incl GST) which includes $925,650 for the builders margin and supervision to complete the Work.
22"Work" is defined in para 1.1(h) to mean:
... the work under the Contract which includes the demolition of 3 dwellings and construction of 2 residential buildings comprising 39 units and basement carpark for 61 vehicles at the Project.
"Contract" is defined to mean the Gordon BC4 and "Project" is defined to mean the Gordon Project.
23Clause 2.1 states that, at the time of execution of the Settlement Deed, the parties must execute the terms of settlement attached to the deed as annexure A. The terms of settlement relevantly provide that by consent the plaintiff (PBC) and the defendant (Tresedar) had settled the matter on terms that included "verdict and judgment for the plaintiff in the amount of $1,001,015.33 (inclusive of GST)".
24Clause 3 of the Deed is in the following terms:
3. Obligations of the parties
3.1 At the time of executing the Deed, Tresedar is to execute an unregistered second mortgage over the Development being Lot 101 in DP 1128185 in favour of PB in the amount of $224,634.67 in the form attached hereto and marked "B".
3.2 The parties agree the unregistered mortgage will give PB a caveatable interest in the Development and PB may, at its sole discretion, lodge a caveat over the Development.
3.3 PB must discharge the unregistered second mortgage once payment of the amount of in clause 5.1 has been paid in full by Tresedar.
3.4 Within 5 days of entering into this Deed the parties are to execute a Tripartite Deed in substantially the same terms as the existing tripartite deed between the parties and the Bank but which incorporates this Deed.
The "Development" referred to in cl 3.1 is the Turramurra Project.
25Clause 4.1 provides:
Tresedar will pay PB the amount of $925,650 (incl GST) for the following:
(a) PB's builders margin for the Work - $605,000 (incl GST); and
(b) PB's supervision for the Work - $320,650 (incl GST).
26Under cl 4.2(a), the $605,000 was payable in one instalment of $110,000 payable on 17 October 2008, one instalment of $55,000 payable on the last business day of October 2008 and instalments of $44,000 payable on the last business day of each month starting in November 2008 and finishing in August 2009. Under cl 4.2(b), the amount of $320,650 was payable in one instalment of $23,650 payable on or before 17 October 2008, instalments of $22,000 payable on the last business day of each month commencing in October 2008 and ending in October 2009 and an instalment of $11,000 payable on the last business day of November 2009.
27Clause 4.3 provides that, if practical completion under the Gordon BC4 occurred before 30 November 2009, Tresedar would pay on practical completion the balance of the amount of $925,650 then owing.
28Clause 5.1 provides:
Tresedar will pay PB the amount of $300,000 (incl GST) within 6 weeks after the registration of the strata plan of the Development but in any event before 30 December 2008. Tresedar must raise this amount from the development finance, proceeds of sale and/or refinance (or other finance) of the Development or by any other means.
29Clause 6 provides:
6.1 In respect of clause 4.2 above, if the Works are delayed by inclement weather during any month, then the payment due 3 days after the last business day of that month is extended by the number of business days approved as an extension of time for inclement weather during that month, provided that the payment made on the extended due date in respect of PB's supervision pursuant to paragraph 4.2(b) above is increased on a pro rata basis to account for the extension of time.
6.2 PB may, in its absolute sole discretion, consider a reasonable request to extend the date of 30 December 2008 referred to in paragraph 5 above.
30Clause 7 provides:
Penalty for Non Payment by Tresedar
7.1 Subject to clause 7.3, in the event Tresedar fails to make any of the payments set out in paragraphs 4 and 5 above within the time required all amounts in the Deed ("the Penalty Amounts") become payable immediately and PB may:
(a) enforce the judgment in the Supreme Court Proceedings 55058 of 2008 to recover the Penalty Amounts under the Deed forthwith against Tresedar and the Guarantors; and
(b) suspend work immediately until payment of the Penalty Amounts is made to PB.
7.2 Subject to clause 7.3, the judgment debt outstanding will be immediately enforceable against Tresedar and the Guarantors in the event of a breach of the Deed.
7.3 PB cannot take any steps under clause 7.1 or 7.2 unless the Bank has had the opportunity to make an election under clause 5.1(g) of the Tripartite Deed.
7.4 In the event the Bank makes an election under clause 5.1(g) of the Tripartite Deed, and provided the Bank complies with the election made by it, the judgment shall not be enforceable in respect of the default by Tresedar to make the relevant payment/s.
31Clause 9.1 provides:
Tresedar must on the 15th of each month or as requested by PB, inform PB of the sales, strata registration and financing of the Development.
32Clause 11.1 contains a release by the parties of all claims which any party may have had "in any way related to the Project or the Contract or on any account whatsoever between the parties hereto up to and including the date of these presents".
33Clause 12.1 provides:
Tresedar hereby indemnifies PB against all Claims made against PB or incurred by PB as a result of the excavator, [Stallion], or any Person who performs a part of the Work.
"Claim" is defined broadly to include demands, claims, actions, suits etc. "Person" is defined to mean an individual or corporation.
34The Tripartite Deed referred to in cl 7 was a deed entered into on 20 October 2008 between Bankwest, Tresedar and PBC. Clause 4 of that deed required PBC to give Bankwest at the same time as it gave Tresedar a copy of any notice of "Contract Default" and, as soon as practicable, "details of the occurrence and circumstances of any Contract Default and any action or payment which the Builder considers appropriate to remedy any Contract Default or compensate the Builder for the Contract Default". Clause 5.1 of that deed provided that PBC could not suspend performance of its work or exercise any right or remedy in respect of a Contract Default unless it first gave Bankwest at least 14 business days' notice of its intention to do so. Clause 5.1(g) gave the bank a right exercisable within 21 days of receiving that notice to elect to remedy any default that could be remedied or to assume Tresedar's obligations under the Gordon BC4 if the default could not be remedied.
35The mortgage that Tresedar was required to execute under cl 3.1 of the Settlement Deed contains the following special conditions:
1 This mortgage secures the repayment by the mortgagor to the mortgagee of $224,634.67 ("principal sum") and other money ("secured money") referred to in this mortgage and Memorandum V849099 ("memorandum").
2 The mortgagor will have repaid the principal sum or the balance of it and all secured money once payment of the amount of $300,000 has been paid in full by the mortgagor pursuant to clause 5.1 of the Deed of Settlement and Release made between the Mortgagor, the Mortgagee, Tetbury Pty Limited and Aris Michael Evanian dated 14 October 2008.
Clause 14 of the memorandum of mortgage gave PBC the power to appoint a receiver to the mortgaged property in the event of a default by Tresedar.
36Following the execution of the Settlement Deed, work resumed on the Gordon Project. During the period from 28 October 2008 to 7 April 2009, Tresedar paid PBC a total amount of $540,650 in respect of its obligations under that deed. However, it did not pay the $300,000 that was payable under cl 5.1 by 30 December 2008 and, on 31 December 2008, PBC served what purported to be a payment claim under the Act for that amount together with instalments due under cl 4.2. No payment schedule was served in respect of that claim.
37Two other series of events occurred following the resumption of work which are of particular relevance to the current dispute.
38First, PBC made a number of claims in respect of variations to the contract works. The variations were designed principally to deal with a substantial shortfall in the allowance that had been made in the original cost plan for brickwork. The variations involved substituting concrete blockwork for the brickwork. The overall effect of the variations was to increase the project costs by approximately $5,000. However, a number of variations involved substantial increases in the cost of the contract works (associated with the concrete blockwork), which were offset against decreases resulting from other variations (associated with a reduction in the brickwork). In the variations showing cost increases, PBC claimed under cl 14(h)(i) of the Gordon BC4 additional amounts for the cost of having its foreman on site for the additional time it was claimed it would take to undertake the varied work. PBC also claimed under cl 14(g) an allowance of 20 percent of the cost of the additional work for supervision, overhead and profit.
39In addition, on 23 April 2009, PBC served Delay Claim 1. In that claim, PBC claimed an amount of $307,294.36 in respect of delays said to have arisen from its variation claims. In all, 99 days of delay were claimed. The amount of $307,294.36 was calculated by taking the amount claimed for "Forgone Builders Margin" of $40,000 per month and "Foregone Foreman Costs" of $20,000 per month and calculating the average number of working days per month as being 19.33 to arrive at a figure for the foregone margin and costs per day of $3,103.98 and multiplying that figure by 99. A revised claim (Delay Claim 1A) was sent on 31 May 2009. It claimed $248,318.68 for 80 days' delay calculated on the same basis.
40Variation 7 was a credit of $156,818.18 arising from reduction in scaffolding associated with the reduced brickwork. It was stated to be contingent "upon the owner accepting all prior numbered variations in respect of the Works". The prior variations showed increases in the costs of the work including increases in the amount allowed for builders margin and foreman costs.
41Similarly, Variation 9 showed large reductions in the cost of the brickwork. Variation 10 showed a reduction in administration costs. Both variations were expressed to be "contingent upon the owner consenting to Variation 11". Variation 11, which like Delay Claim 1 was dated 23 April 2009, did not show any variation to the actual work. Rather, it showed variations to the budget which involved creating a new budget item called "Builders Contingency" comprising amounts proposed to be saved as a consequence of other variations (including Variations 9 and 10). It also showed payments to the builder in respect of Delay Claim 1 (of $307,294.36) and the additional claims for having its foreman on site ($47,520.00) and the additional claim for supervision, overhead and profit ($157,833.29) arising out of a number of the variations. The result was that PBC would not agree to the reduction in the brickwork unless Tresedar agreed to pay it an additional $512,647.65. Tresedar took objection to that claim.
42The second relevant series of events concerned the recovery of the $300,000 payable under the Settlement Deed. As I have said, the obligation to pay that amount was secured by a mortgage over the Turramurra Project. That project consisted of 6 townhouses and 6 villas. PBC was also the builder of that project. Although there is a dispute about when practical completion of work under the relevant building contract occurred, it is clear that the project was substantially complete in early 2009. PBC lodged a caveat over the property on 19 February 2009 and, at about the same time, Tresedar sought to register the strata plan in respect of the development. In view of the caveat, it required PBC's consent to do so. Tresedar's position was that it intended to use the proceeds of sale of lots in the Turramurra Project to pay the $300,000 due under the Settlement Deed.
43Mr Hovig Evanian (Mr Aris Evanian's son, who also worked for Tresedar) met with Mr Phontos in early March and asked him why he had lodged the caveat and asked him to remove it. According to him, Mr Phontos replied "I am trying to put pressure on you to accept my variations at the Gordon project". Mr Phontos denies that he said that and Mr Evanian's evidence seems contrived and is difficult to reconcile with what happened subsequently. I do not accept it.
44On 16 March 2009, Gilbert + Tobin, who were PBC's lawyers at the time, responded to Mr Evanian's request to remove the caveat to Raj Lawyers, who acted for Tresedar at the time. The letter said in part:
Our client has provided the following instructions:
1. our client will not agree to the removal of the registered caveat as this is not necessary for your client to register a strata plan over the Property;
2. formal consent will be provided by the caveator to enable the registration of the strata plan over the Property subject to our client's caveated rights being preserved;
3. upon the registration of the strata plan our client's caveat is to be registered over all strata lots created;
4. the second mortgage provided over the Property will be amended so that the mortgage will be over all strata lots created;
5. Tresedar's solicitor are to prepare all necessary consents, amendments to the second mortgage and any other documentation necessary; and
6. Tresedar to pay all costs including our client's legal costs incurred up to date in registering the caveat, and to be incurred in relation to the above.
As you are aware your client is in breach of the Deed of Settlement and Release and substantial amounts are owing to our client. If and when our client is paid in full, our client will provide consent for the removal of the caveat.
It appears that by this stage Tresedar had exchanged contracts in relation to one of the units in the development.
45Raj Lawyers responded to that letter on 23 March 2009. In that response, they said relevantly:
... We note that your client has agreed to give its formal consent to registration of the SP, subject to preservation of your client's caveated rights. Our client agrees to this course of action and seeks to enter further discussions on the issue of the caveat once the consent is lodged and the SP is registered.
46On 3 April 2009, Mr Hovig Evanian wrote to PBC. The letter was largely concerned with PBC's claims in respect of the variations and asked PBC to remove the claim "for extra builder's foreman, supervision, overhead & profit" in an invoice that PBC had sent Tresedar on 31 March 2009. The letter also said:
We have agreed PBC may after consenting to registration of strata replace their mortgage and caveat interest on 4 lots which would more than cover the mortgage amount secured in the deed. The reason for this is that Tresedar would agree to then auction four lots and pay PBC from the proceeds of these sales. ...
The letter asked for an urgent response "as considerable delays have already been caused by PBC in not consenting to registering of the strata and refusing to communicate any resolution as to the above".
47Mr Phontos responded to that letter by email on the same day saying that PBC would respond to the letter in due course. In response to that email, Mr Hovig Evanian sent Mr Phontos a fax on 4 April 2009. He referred back to Gilbert + Tobin's letter dated 16 March 2009 and stated that Tresedar would agree to grant caveats over the 12 strata lots and to vary the second mortgage. The letter went on:
Furthermore, as per the spreadsheet which has been provided to you as an attachment to our letter dated 3 April 2009 in respect of payment to the builder under clause (5) we foresee that payment will be finalized on the sale of the fifth lot. We will use our best endeavours to ensure this occurs.
Mr Phontos said in evidence that this condition was unacceptable to him. His position was that the payment secured by the second mortgage was already overdue, and he was not prepared to wait until the sale of the fifth lot to receive it.
48On 9 April 2009, Mr Deutsch of Raj Lawyers sent PBC's solicitors an email attaching an amended mortgage and a consent to registration of the strata plan. The email said:
My client has asked that I emphasize the urgency of this matter and that any delay may cause the expected sale [of one of the villas] to fall through.
49Nothing further happened in relation to the caveat until 30 April 2009. In addition, PBC served two additional claims. One was dated 24 April 2009 and was expressed to be a progress claim for $1,839,015.56. The details of the claim are not important. The second was dated 30 April 2009 and was expressed to be a payment claim under the Act for $1,381,994.05. That claim related to a number of variations that increased the costs of the work together with Delay Claim 1.
50On 30 April 2009, Tresedar wrote to PBC objecting to the progress claim dated 24 April 2009 and asking for a response in relation to the variation of the second mortgage over the Turramurra land.
51On 4 May 2009, PBC sent a fax replying to Tresedar's faxes dated 3 April 2009 and 30 April 2009. In that response, it reiterated its position that it still required a caveat over all 12 lots to be created on registration of the strata plan.
52On 6 May 2009, Mr Hovig Evanian wrote to PBC setting out the then current position in relation to lots in the Turramurra Project. At that time, contracts had been exchanged on the sale of one lot (lot 2), contracts for sale in relation to a second lot had been issued but not yet exchanged, a number of lots were tenanted and all the remaining lots (including those tenanted) were available for sale.
53On 12 May 2009, Mr Phontos sent an email to Mayne Investments Limited, the lender in respect of the Turramurra Project, which was copied to Mr Evanian. In that email Mr Phontos said:
Considering there is 1 exchanged contract to date we seek your approval to the following:
1. We receive $150,000 from the settlement proceeds of the sale of lot 2 for a withdrawal of caveat over that lot;
2. We receive $150,000 from the settlement proceeds of the sale of the next lot for a withdrawal of caveat over that lot, but if a third sale has exchanged prior to that settlement, then we receive $75,000 from the second settlement and $75,000 from the third settlement for the respective withdrawal of caveats over the particular lots as they settle;
3. Any other money secured by the second mortgage, costs, interest etc, be included with the last instalment due as above and be accompanied with a withdrawal of caveat of all of the other lots; and
4. If any new security is created over the properties then the balance owing is to be paid.
In addition to your approval, the above is also subject to:
1. The approval of the owner including to interest on the amount owing at 20% pa from 30 December 2008;
2. The owner and the builder resolving the builders variation claims in respect of the Gordon job; and
3. The approval of our lawyers and appropriate documentation.
The actual first mortgagee was Perpetual Nominees Limited. The precise relationship between it and Mayne Investments is not apparent from the evidence. Nothing, however, turns on the relationship and it is convenient to refer to the first mortgagee in respect of the Turramurra land interchangeably as Mayne Investments and Perpetual, as the parties did in their correspondence. As at May 2009, Mayne Investments was owed approximately $5.7 million in respect of the Turramurra Project.
54Also on 12 May 2009, Tresedar served what was described as a payment schedule pursuant to s 14 of the Act in respect of the payment claim dated 30 April 2009. In that schedule, Tresedar asserted that the only amount due was $66,000, which was said to be payable under cls 4.2(a) and 4.2(b) of the Settlement Deed. The schedule asserted that the balance was not payable because, among other things, the variations were carried out without the prior consent of the owner. It paid the $66,000 on the same day.
55On 20 May 2009, Walters Solicitors, acting for Mayne Investments, wrote to Mr Phontos proposing that PBC provide a withdrawal of caveat in relation to the first three sales in exchange for $100,000 - presumably from each sale. Mr Andersen of Mayne Investments followed up that letter by email on 27 May 2009. Mr Phontos replied that he had forwarded the letter to Tresedar's lawyers who had come back with a series of questions which he needed to consider and discuss with them. What those questions were is not clear from the evidence.
56On 5 June 2009, in purported exercise of rights conferred by the Act, PBC served a notice of intention to suspend work on the Gordon Project relying on the claim it had made on 30 December 2008 for the payment of the $300,000 under cl 5 of the Settlement Deed. A copy of that notice was sent to Bankwest on the same day. On 9 June 2009, PBC served a default notice on Tresedar in relation to the payment of the $300,000 and the failure to make the payments said to be due under cl 4 on 28 November 2008 and 29 May 2009 totalling $132,000. A copy of that notice was sent to Bankwest on 10 June 2009 inviting it to make an election under cl 5.1(g) of the Tripartite Deed in respect of that default. By notice dated 11 June 2009, PBC gave notice that it suspended the carrying out of construction work in exercise of its rights under s 27(1) of the Act, relying on the notice it had sent on 5 June 2009. PBC never resumed work on the site.
57On 15 June 2009, Mr Andersen sent Mr Phontos a further email asking for a response to his earlier proposal.
58On 17 June 2009, Tresedar paid PBC the amount of $132,000.
59On 18 June 2009, PBC sent Tresedar a notice of dispute under cl 26 of the Gordon BC4. The notice of dispute complained that Tresedar had failed to provide it with reasonable evidence of Tresedar's capacity to pay for the works in response to requests that it do so that were sent on 4 May 2009 and 11 June 2009. It also complained that Tresedar had failed to provide written instructions to PBC in a timely and proper manner in breach of cl 2(d) of the Gordon BC4. It proposed a meeting in accordance with cl 26.
60It appears that Mr Andersen rang Mr Phontos on 22 June 2009. Following that telephone call, Mr Phontos sent Mr Andersen an email in which he said:
We are in a continuing relationship with Tresedar P/L and our mortgage makes provision for other monies which have or may become due by it to be also secured by the mortgage.
In those circumstances, we propose to consent to the registration of the strata plan on the basis that we receive $100,000 from each of the first three settlements. We will provide a withdrawal of caveat for the particular unit sold only, in exchange for each $100,000 payment. This proposal is made subject to our lawyers satisfaction and without prejudice to our rights to obtain payment from Tresedar by other means.
61A day later, on 23 June 2009, PBC sent a copy of the notice it had sent to Tresedar under cl 26 of the Gordon BC4 to Bankwest. The letter to Bankwest did not propose any specific steps that Bankwest should take to rectify the breaches about which PBC complained. It did refer on a "without prejudice basis" to various steps that might be taken including the establishment of a project management committee. The letter concluded:
We propose a meeting as soon as possible with representatives of Bankwest to discuss the above for the mutual advantage of all involved. Alternatively, the consultants of the builder and owner and the banks Quantity Surveyor could meet to discuss the above. We welcome your comments.
62On 3 July 2009, Colin Biggers and Paisley, who then acted for Tresedar, wrote to Gilbert + Tobin reiterating Tresedar's request that PBC consent to registration of the strata plan and proposing (assuming that Mayne Investments agreed) that PBC receive $100,000 from the sale of each of the first 3 strata lots. It also proposed that, on receipt of those payments, PBC deliver withdrawal of caveats in relation to the other lots. If that proposal was acceptable, Tresedar agreed to pay PBC's reasonable legal costs and interest on the outstanding balance calculated at 10 percent per annum from 31 December 2008.
63On 10 July 2009, PBC provided its consent to registration of the strata plan. On the same day, it served a further notice suspending work on the site on the basis that Bankwest had not made an election to remedy the default under cl 5.1(g) of the Tripartite Deed in respect of the notice it served on 10 June 2009.
64There was then further correspondence between Colin Biggers & Paisley and Gilbert + Tobin. It appears from the correspondence that there was some urgency in completing one sale and that PBC had agreed to sell two units to relations of Mr Evanian. Gilbert + Tobin pressed for more information in relation to those two sales and for an agreement that settlement would occur by a particular date. Colin Biggers & Paisley pointed out that Tresedar could not settle by the date indicated and made it clear that, on payment of the $300,000, PBC should withdraw the other caveats.
65In August 2009, Tresedar retained Bransgroves for a period of time. Bransgroves wrote to Gilbert + Tobin on 19 August 2009. They indicated that the properties were encumbered to Perpetual for an amount that "far outweighs the equity which your client purports to maintain in these three properties". They offered an undertaking that Tresedar would ensure that 100 percent of the sale proceeds would be paid to the first mortgagee. On that basis, they demanded that the caveats be withdrawn and threatened to commence court proceedings if they were not. They also made it clear that, once the first mortgagee had been paid in full, Tresedar would pay the sum of $224,634.67 into court and that it was entitled to the balance of any amount realised from the sale of the properties. Tresedar commenced these proceedings on the same day seeking damages on the basis that PBC had wrongfully suspended the building works.
66There was subsequent correspondence between the parties' solicitors. The details are not important to the way in which Tresedar puts its case. PBC permitted the sale of one lot to settle on 4 September 2009. However, agreement was not reached on the terms on which PBC would remove the other caveats.
67On 12 October 2009, PBC sent Tresedar a letter purporting to set out further reasons which were said to justify the suspension of works on the Gordon Project on 11 June 2009. Three reasons were advanced. The first was that Tresedar had not obtained Bankwest's consent to the variation work in accordance with a request that PBC had made on 1 May 2009. The second was that Tresedar had not paid a number of subcontractors. The third was that on 4 May 2009 PBC had requested Tresedar to provide it with reasonable evidence of its capacity to pay for the works in accordance with cl 2(c) of the Gordon BC4 and Tresedar had failed to do so.
68On 28 October 2009 Tresedar filed a motion in these proceedings seeking an order that PBC provide a withdrawal of caveat over a number of lots and, on 25 November 2009, PBC appointed a receiver to the Turramurra Project. On 26 November 2009, the court made an order that the caveats be withdrawn on condition that Tresedar pay PBC the sum of $312,107.93. On or about 3 December 2009, Mayne Investments appointed a receiver to the Turramurra Project. In the meantime, on or about 9 November 2009, Tresedar terminated the Gordon BC4.
69No progress was made on the Gordon Project and, on 14 July 2010, Bankwest appointed a receiver to that project. On or about 20 January 2011, the receiver sold the property comprising that project for $6,988,264.28.